60-(7,8,9)CJS-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Complete Asphalt Service Co. Low bidder | $141,648 | ||
| 2 | Kinney Contractors, Inc. | $164,987 | +16.5% | |
| 3 | Huff Sealing Corporation | $184,525 | +30.3% | |
| 4 | Keller Construction, Inc. | $228,844 | +61.6% | |
| 5 | Denler, Inc. | $234,103 | +65.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Complete Asphal… | #2 Kinney Contract… | #3 Huff Sealing Co… | #4 Keller Construc… | #5 Denler, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $37,812.00 | $27,200.00 | $37,200.00 | $50,000.00 | $64,000.00 | |
| 2 | 45100100 | CRACK ROUTING (PAVT) | 174,307 | FOOT | $0.0100 | $0.0100 | $0.00 | $0.1500 | $0.1000 | |
| 3 | 45100200 | CRACK FILLING | 57,521 | POUND | $1.57 | $2.08 | $2.39 | $2.04 | $2.25 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $8,400.00 | $10,000.00 | $5,000.00 | $7,210.00 | $14,000.00 | |
| 5 | 70107025 | CHANGEABLE MESSAGE SN | 85 | CAL DA | $1.00 | $40.00 | $10.00 | $37.00 | $50.00 | |
| 6 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $3,300.00 | $3,000.00 | $4,000.00 | $25,000.00 | $5,000.00 |