60-(6,7,8,9)RS-1
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company Low bidder | $4,445,900 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Microsurfacing … |
|---|---|---|---|---|---|---|
| 1 | X0301242 | PIEZO AXLE SEN CL 2 | 69 | FOOT | $335.00 | |
| 2 | X0326808 | INTERST WKEND CLSR SP | 1 | L SUM | $750,000.00 | |
| 3 | X1600003 | MICRO-SURF 2 PASS ME | 280,206 | SQ YD | $5.50 | |
| 4 | X4405020 | LONG PAR DEP REM 2 | 77 | FOOT | $40.00 | |
| 5 | X4406020 | PART DEP REM T1 2 | 347 | SQ YD | $200.00 | |
| 6 | X4406220 | PART DEP REM T2 2 | 243 | SQ YD | $175.00 | |
| 7 | X4406420 | PART DEP REM T3 2 | 606 | SQ YD | $155.00 | |
| 8 | X4406620 | PART DEP REM T4 2 | 117 | SQ YD | $140.00 | |
| 9 | X4420900 | LONG PART DEPTH PATCH | 1.98 | TON | $300.00 | |
| 10 | X4421000 | PARTIAL DEPTH PATCH | 155 | TON | $300.00 | |
| 11 | X7030005 | TEMP PAVT MKING REMOV | 112,289 | SQ FT | $0.5000 | |
| 12 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $26,000.00 | |
| 13 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | |
| 14 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | |
| 15 | 40400001 | FIBR MOD ASP CRK SEAL | 140,869 | FOOT | $0.9200 | |
| 16 | 40600290 | BIT MATLS TACK CT | 63,046 | POUND | $1.61 | |
| 17 | 42000060 | WELDED WIRE REINF | 61 | SQ YD | $13.80 | |
| 18 | 44000690 | HMA SURF CORRECTION | 280,206 | SQ YD | $2.20 | |
| 19 | 44201053 | CL B PATCH T4 17 | 61 | SQ YD | $397.80 | |
| 20 | 44201055 | CL B PATCH T2 17 | 18 | SQ YD | $397.80 | |
| 21 | 44201299 | DOWEL BARS 1 1/2 | 92 | EACH | $63.00 | |
| 22 | 44213200 | SAW CUTS | 290 | FOOT | $19.80 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $429,000.00 | |
| 24 | 70100420 | TRAF CONT-PROT 701411 | 20 | EACH | $1,320.00 | |
| 25 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $12,133.41 | |
| 26 | 70100815 | TRAF CONT-PROT 701446 | 1 | L SUM | $11,933.41 | |
| 27 | 70107025 | CHANGEABLE MESSAGE SN | 154 | CAL DA | $65.00 | |
| 28 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $14,515.00 | |
| 29 | 70300100 | SHORT TERM PAVT MKING | 16,585 | FOOT | $1.85 | |
| 30 | 70300150 | SHRT TRM PAVT MK REM | 5,695 | SQ FT | $4.60 | |
| 31 | 70300210 | TEMP PVT MK LTR & SYM | 167 | SQ FT | $1.00 | |
| 32 | 70300220 | TEMP PVT MK LINE 4 | 30,338 | FOOT | $0.0900 | |
| 33 | 70300240 | TEMP PVT MK LINE 6 | 191,813 | FOOT | $0.1200 | |
| 34 | 70300250 | TEMP PVT MK LINE 8 | 8,905 | FOOT | $0.1800 | |
| 35 | 78000100 | THPL PVT MK LTR & SYM | 167 | SQ FT | $5.00 | |
| 36 | 78000200 | THPL PVT MK LINE 4 | 30,338 | FOOT | $0.5500 | |
| 37 | 78000400 | THPL PVT MK LINE 6 | 191,813 | FOOT | $0.6500 | |
| 38 | 78000500 | THPL PVT MK LINE 8 | 8,905 | FOOT | $0.9300 | |
| 39 | 78100100 | RAISED REFL PAVT MKR | 2,698 | EACH | $34.37 | |
| 40 | 78300200 | RAISED REF PVT MK REM | 2,698 | EACH | $12.24 | |
| 41 | 88600100 | DET LOOP T1 | 664 | FOOT | $8.00 |