1B-R-1
- Let date
- Friday, April 27, 2018
- Contract
- 76L36 · job page
- District
- District 8
- County
- Washington
- Highway
- Limits
- Joint repair and deck waterproofing on bridge SN 095-0023 carrying IL 127 over Crooked Creek Overflow; 5 miles north of IL 177.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Plocher Construction Company, Inc. Low bidder | $829,378 | ||
| 2 | The Kilian Corporation | $853,827 | +2.9% | |
| 3 | Keeley & Sons, Inc. | $1,017,759 | +22.7% | |
| 4 | Kovilic Construction Company, Inc. | $1,840,374 | +121.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Plocher Constru… | #2 The Kilian Corp… | #3 Keeley & Sons, … | #4 Kovilic Constru… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0327979 | PAVMT MRKG REM GRIND | 900 | SQ FT | $2.00 | $2.05 | $1.93 | $2.00 | |
| 2 | X1200030 | FILL INLETS TEMP | 2 | EACH | $3,600.00 | $500.00 | $2,465.00 | $250.00 | |
| 3 | X4811800 | AGGREGATE SHLDS SPL | 3,163 | SQ YD | $0.5000 | $0.0100 | $8.45 | $18.00 | |
| 4 | X5870015 | BR DK CONCRETE SEALER | 6,679 | SQ FT | $0.6000 | $1.25 | $1.14 | $1.00 | |
| 5 | X6310214 | TRAF BAR TERM T6 SPL | 4 | EACH | $3,200.00 | $2,900.00 | $2,907.00 | $4,000.00 | |
| 6 | X7030005 | TEMP PAVT MKING REMOV | 1,060 | SQ FT | $1.45 | $1.50 | $1.48 | $3.00 | |
| 7 | X7040125 | PIN TEMP CONC BARRIER | 12 | EACH | $22.00 | $25.00 | $27.80 | $25.00 | |
| 8 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $3,025.00 | $3,500.00 | $3,085.50 | $4,000.00 | |
| 9 | Z0007114 | C&D N LEAD PT CL RES | 1 | L SUM | $15,000.00 | $40,000.00 | $11,959.50 | $14,000.00 | |
| 10 | Z0012754 | STR REP CON DP = < 5 | 332 | SQ FT | $80.00 | $125.00 | $167.80 | $125.00 | |
| 11 | Z0016002 | DECK SLAB REP (FD-T2) | 50 | SQ YD | $250.00 | $500.00 | $487.90 | $900.00 | |
| 12 | Z0016200 | DECK SLAB REP (PART) | 1,100 | SQ YD | $182.00 | $70.00 | $267.20 | $675.00 | |
| 13 | Z0033700 | LONG JOINT SEALANT | 1,924 | FOOT | $10.35 | $7.50 | $10.71 | $7.00 | |
| 14 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 15 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 16 | 20200600 | EXC & GR EX SHOULDER | 4 | UNIT | $2,000.00 | $645.00 | $297.80 | $2,500.00 | |
| 17 | 35600716 | HMA BC WID 10 | 200 | SQ YD | $108.00 | $98.00 | $109.79 | $120.00 | |
| 18 | 40600295 | P BIT MATLS TACK CT | 1,634 | POUND | $1.50 | $1.00 | $1.23 | $3.00 | |
| 19 | 40600982 | HMA SURF REM BUTT JT | 107 | SQ YD | $62.00 | $25.00 | $62.69 | $50.00 | |
| 20 | 40603540 | P HMA SC "D" N70 | 266 | TON | $140.00 | $155.00 | $142.43 | $200.00 | |
| 21 | 44004250 | PAVED SHLD REMOVAL | 153 | SQ YD | $49.00 | $30.00 | $11.20 | $18.00 | |
| 22 | 50102400 | CONC REM | 18.7 | CU YD | $1,300.00 | $2,150.00 | $1,690.00 | $2,500.00 | |
| 23 | 50300225 | CONC STRUCT | 2.3 | CU YD | $2,000.00 | $3,875.00 | $4,985.00 | $2,500.00 | |
| 24 | 50300255 | CONC SUP-STR | 21.5 | CU YD | $1,200.00 | $3,525.00 | $1,999.00 | $2,500.00 | |
| 25 | 50606701 | C & P STRUCT STL L1 | 1 | L SUM | $60,000.00 | $80,600.00 | $60,180.00 | $78,000.00 | |
| 26 | 50800205 | REINF BARS, EPOXY CTD | 2,570 | POUND | $2.00 | $2.50 | $2.30 | $3.00 | |
| 27 | 50800515 | BAR SPLICERS | 56 | EACH | $26.00 | $30.50 | $32.58 | $50.00 | |
| 28 | 52000050 | PREF JOINT SEAL 4 | 136.5 | FOOT | $180.00 | $280.00 | $237.40 | $250.00 | |
| 29 | 58100200 | WATERPRF MEMBRANE SYS | 3,167 | SQ YD | $24.00 | $25.00 | $21.99 | $70.00 | |
| 30 | 63000001 | SPBGR TY A 6FT POSTS | 300 | FOOT | $22.00 | $23.00 | $22.80 | $30.00 | |
| 31 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $2,750.00 | $2,825.00 | $2,805.00 | $3,600.00 | |
| 32 | 63200310 | GUARDRAIL REMOV | 600 | FOOT | $7.25 | $7.50 | $5.65 | $9.00 | |
| 33 | 67000400 | ENGR FIELD OFFICE A | 10 | CAL MO | $600.00 | $1,400.00 | $1,980.00 | $2,000.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $50,000.00 | $73,500.00 | $57,700.00 | $50,000.00 | |
| 35 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $20,000.00 | $10,000.00 | $17,890.00 | $30,000.00 | |
| 36 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $4,000.00 | $0.0100 | $1,780.00 | $20,000.00 | |
| 37 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $1,500.00 | $0.0100 | $3,003.90 | $10,000.00 | |
| 38 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $2,500.00 | $0.0100 | $1,435.00 | $10,000.00 | |
| 39 | 70103815 | TR CONT SURVEILLANCE | 80 | CAL DA | $80.00 | $0.0100 | $5.00 | $500.00 | |
| 40 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $24,500.00 | $25,000.00 | $23,465.10 | $30,000.00 | |
| 41 | 70106700 | TEMP RUMBLE STRIPS | 12 | EACH | $650.00 | $0.0100 | $663.00 | $850.00 | |
| 42 | 70300240 | TEMP PVT MK LINE 6 | 1,904 | FOOT | $0.6500 | $0.6700 | $0.6700 | $1.00 | |
| 43 | 70300280 | TEMP PVT MK LINE 24 | 48 | FOOT | $13.75 | $14.00 | $14.03 | $20.00 | |
| 44 | 70300520 | PAVT MARK TAPE T3 4 | 3,176 | FOOT | $0.7500 | $2.00 | $1.02 | $2.00 | |
| 45 | 70400100 | TEMP CONC BARRIER | 1,144 | FOOT | $21.00 | $24.00 | $27.80 | $30.00 | |
| 46 | 70400200 | REL TEMP CONC BARRIER | 1,144 | FOOT | $3.00 | $8.00 | $6.90 | $10.00 | |
| 47 | 70600260 | IMP ATTN TEMP FRN TL3 | 2 | EACH | $10,000.00 | $7,500.00 | $3,980.00 | $8,850.00 | |
| 48 | 70600332 | IMP ATTN REL FRN TL3 | 2 | EACH | $2,000.00 | $1,250.00 | $2,115.00 | $2,000.00 | |
| 49 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | $36.00 | $35.70 | $45.00 | |
| 50 | 78000200 | THPL PVT MK LINE 4 | 2,663 | FOOT | $1.75 | $1.80 | $1.22 | $2.00 | |
| 51 | 78100100 | RAISED REFL PAVT MKR | 19 | EACH | $150.00 | $125.00 | $67.68 | $90.00 | |
| 52 | 78200005 | GRDRAIL REF TYPE A | 10 | EACH | $14.00 | $12.50 | $12.50 | $15.00 | |
| 53 | 78200011 | BARR WALL REF TYPE C | 92 | EACH | $15.00 | $13.50 | $13.26 | $20.00 | |
| 54 | 78300200 | RAISED REF PVT MK REM | 19 | EACH | $12.00 | $8.00 | $10.00 | $50.00 |