$58,537.14Avg low bid / L SUM
$43,037.76Avg of all bids
—Avg engineer's estimate
25Jobs · 25 L SUM
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 5 | 5 | $119,426.20 | $47,538.56 |
| 2020 | 10 | 10 | $37,543.20 | $33,817.47 |
| 2019 | 7 | 7 | $19,743.29 | $31,823.87 |
| 2018 | 3 | 3 | $117,554.18 | $107,081.95 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Mar 5, 2021 | 62N16 | WillDistrict 1 | 1 L SUM | $3,500.00 | Eagle Painting & Maintenance Company, Inc. |
| Mar 5, 2021 | 62N12 | CookDistrict 1 | 1 L SUM | $458,657.00 | Capital Industrial Services |
| Jan 15, 2021 | 64P51 | HenryDistrict 2 | 1 L SUM | $4,082.00 | General Constructors Inc. of the Quad Cities |
| Jan 15, 2021 | 66L24 | BureauDistrict 3 | 1 L SUM | $1,500.00 | Three Star Painting, Inc. |
| Jan 15, 2021 | 74A40 | VariousDistrict 7 | 1 L SUM | $129,392.00 | ERA-Valdivia Contractors, Inc. |
| Nov 6, 2020 | 62M89 | CookDistrict 1 | 1 L SUM | $46,432.00 | Capital Industrial Services |
| Jun 12, 2020 | 62K76 | CookDistrict 1 | 1 L SUM | $39,000.00 | ERA-Valdivia Contractors, Inc. |
| Jun 12, 2020 | 64P35 | OgleDistrict 2 | 1 L SUM | $15,000.00 | ERA-Valdivia Contractors, Inc. |
| Apr 24, 2020 | 60D77 | CookDistrict 1 | 1 L SUM | $35,000.00 | Lorig Construction Company |
| Mar 6, 2020 | 72L44 | MacoupinDistrict 6 | 1 L SUM | $6,500.00 | Stutz Excavating, Inc. |
| Jan 17, 2020 | 66K38 | LasalleDistrict 3 | 1 L SUM | $66,250.00 | ERA-Valdivia Contractors, Inc. |
| Jan 17, 2020 | 66K74 | BureauDistrict 3 | 1 L SUM | $37,500.00 | ERA-Valdivia Contractors, Inc. |
| Jan 17, 2020 | 68D86 | WarrenDistrict 4 | 1 L SUM | $13,500.00 | Brandt Construction Co. |
| Jan 17, 2020 | 66K36 | BureauDistrict 3 | 1 L SUM | $79,500.00 | ERA-Valdivia Contractors, Inc. |
| Jan 17, 2020 | 66K37 | DekalbDistrict 3 | 1 L SUM | $36,750.00 | ERA-Valdivia Contractors, Inc. |
| Nov 8, 2019 | 66F75 | LasalleDistrict 3 | 1 L SUM | $77,365.00 | Civil Constructors, Inc. |
| Nov 8, 2019 | 74926 | Effingham, FayetteDistrict 7 | 1 L SUM | $1,000.00 | All States Painting, Inc. |
| Jul 12, 2019 | 64N32 | WhitesideDistrict 2 | 1 L SUM | $7,838.00 | Civil Constructors, Inc. |
| Jun 14, 2019 | 66K13 | DekalbDistrict 3 | 1 L SUM | $500.00 | Three Star Painting, Inc. |
| Apr 26, 2019 | 62H13 | Will, KendallDistrict 1 | 1 L SUM | $20,000.00 | Eagle Painting & Maintenance Company, Inc. |
| Jan 18, 2019 | 62G87 | Lake, Mchenry, CookDistrict 1 | 1 L SUM | $28,000.00 | Eagle Painting & Maintenance Company, Inc. |
| Jan 18, 2019 | 72K97 | MacoupinDistrict 6 | 1 L SUM | $3,500.00 | RCS Construction, Inc. |
| Nov 9, 2018 | 62G89 | CookDistrict 1 | 1 L SUM | $180,010.00 | Capital Industrial Services |
| Nov 9, 2018 | 72K86 | MenardDistrict 6 | 1 L SUM | $6,116.25 | Freesen, a div of UCM, Inc. |
| Aug 3, 2018 | 60N87 | WillDistrict 1 | 1 L SUM | $166,536.30 | D. Construction, Inc. |
| Apr 27, 2018 | 76L36 | WashingtonDistrict 8 | 1 L SUM | $15,000.00 | Plocher Construction Company, Inc. |
| Mar 9, 2018 | 60X10 | WillDistrict 1 | 1 L SUM | $15,300.00 | Judlau Contracting, Inc. |
| Mar 9, 2018 | 62F93 | WillDistrict 1 | 1 L SUM | $30,000.00 | Eagle Painting & Maintenance Company, Inc. |
| Jan 19, 2018 | 62F79 | Cook, DupageDistrict 1 | 1 L SUM | $47,500.00 | ERA-Valdivia Contractors, Inc. |