Bid tab 74D57

Let Sep 19, 2025 · District 7 · Effingham

‹ Sep 2025 results

(26-0,1)MED

Let date
Friday, September 19, 2025
Contract
74D57 · job page
District
District 7
County
Effingham
Highway
Limits
Installation of a median crossover on I-70 approximately 0.4 miles west of the IL 128 interchange.
Classification
·
Project number

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Howell Paving, Inc. Low bidder $860,301
2 Samron Midwest Contracting, Inc. $879,804 +2.3%
3 William Charles Construction Company, LLC $981,669 +14.1%
4 McCarthy Improvement Company $992,663 +15.4%
5 Kinney Contractors, Inc. $1,055,968 +22.7%
6 Phoenix Corporation of the Quad Cities $1,079,481 +25.5%
7 G. M. Sipes Construction, Inc. $1,176,495 +36.8%
8 Kieffer Bros. Construction Co., Inc. $1,789,231 +108.0%

Bid tab: unit prices 22 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Howell Paving, …#2 Samron Midwest …#3 William Charles…#4 McCarthy Improv…#5 Kinney Contract…#6 Phoenix Corpora…#7 G. M. Sipes Con…#8 Kieffer Bros. C…
1X2600002 RECOVERABLE DELINEATR36EACH $110.00 $80.00 $112.00 $123.00 $200.00 $110.00 $200.00 $320.65
2X6015000 REM CONC HDWL P DRNS2EACH $666.26 $800.00 $2,100.00 $200.00 $260.00 $375.00 $250.00 $371.00
320200100 EARTH EXCAVATION570CU YD $47.38 $40.00 $67.00 $56.00 $45.00 $46.00 $16.00 $42.40
428000500 INLET & PIPE PROTECT3EACH $504.28 $240.00 $450.00 $630.00 $220.00 $250.00 $250.00 $275.60
535101400 AGG BASE CSE B5,228TON $36.23 $43.50 $41.00 $40.50 $50.00 $50.00 $40.00 $50.88
642000060 WELDED WIRE REINF3,129SQ YD $9.80 $8.00 $20.50 $15.50 $12.00 $27.00 $15.00 $14.63
742000510 PCC PVT 10 1/23,129SQ YD $105.41 $108.00 $106.65 $125.50 $130.00 $125.75 $205.00 $135.68
844004250 PAVED SHLD REMOVAL1,467SQ YD $23.85 $11.00 $30.00 $28.00 $20.00 $22.75 $15.00 $26.50
9542A0220 P CUL CL A 1 1534FOOT $147.23 $110.00 $155.00 $95.00 $95.00 $145.50 $80.00 $82.15
10542A5479 P CUL CL A 1 EQRS 24640FOOT $147.48 $135.00 $166.00 $147.00 $180.00 $194.00 $110.00 $833.16
1154214509 PRC FL END S EQ RS 242EACH $1,831.61 $2,800.00 $3,550.00 $2,400.00 $2,700.00 $2,925.00 $3,000.00 $3,127.00
1260108200 PIPE UNDERDRAIN 6 SP75FOOT $30.67 $34.00 $90.00 $34.50 $52.00 $47.50 $25.00 $56.39
1360224445 MAN TA 7 DIA T1F OL1EACH $9,398.02 $8,800.00 $15,000.00 $10,100.00 $11,000.00 $11,500.00 $8,000.00 $11,978.00
1460224457 MAN TA 8 DIA T1F OL1EACH $10,115.97 $8,200.00 $19,000.00 $16,900.00 $12,000.00 $12,250.00 $9,000.00 $15,211.00
1560236200 INLETS TA T8G2EACH $3,496.68 $3,500.00 $2,500.00 $4,200.00 $3,500.00 $2,000.00 $3,000.00 $3,498.00
1667100100 MOBILIZATION1L SUM $30,935.81 $52,000.00 $66,500.00 $59,000.00 $52,000.00 $72,000.00 $58,000.00 $58,300.00
1770100205 TRAF CONT-PROT 7014012EACH $28,744.03 $23,000.00 $13,000.00 $20,750.00 $24,000.00 $9,400.00 $25,000.00 $128,472.00
1870100420 TRAF CONT-PROT 7014112EACH $1,954.17 $4,500.00 $450.00 $335.00 $500.00 $300.00 $500.00 $19,292.00
1970107007 PAVT MK BLKOUT TAPE 7500FOOT $3.20 $2.50 $3.20 $3.50 $5.00 $3.20 $3.00 $7.00
2070107025 CHANGEABLE MESSAGE SN56CAL DA $115.00 $120.00 $158.00 $128.50 $130.00 $115.00 $250.00 $174.90
2170300150 SHRT TRM PAVT MK REM2,225SQ FT $0.3500 $1.00 $0.3500 $0.5000 $2.00 $0.3500 $1.00 $4.20
2270307120 TEMP PVT MK L4 T4 TAPE5,800FOOT $1.48 $1.00 $1.50 $1.50 $2.40 $1.48 $1.50 $3.38