D7 BRIDGE REPAIRS 2020-3
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Halverson Construction Co., Inc. Low bidder | $145,001 | ||
| 2 | Keeley & Sons, Inc. | $176,914 | +22.0% | |
| 3 | Sangamo Construction Company | $182,888 | +26.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Halverson Const… | #2 Keeley & Sons, … | #3 Sangamo Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X6330900 | VERT ADJ OF GUARDRAIL | 25 | FOOT | $40.00 | $40.80 | $59.09 | |
| 2 | Z0012754 | STR REP CON DP = < 5 | 10 | SQ FT | $600.00 | $792.64 | $454.69 | |
| 3 | 50102400 | CONC REM | 2.3 | CU YD | $7,900.00 | $2,980.00 | $3,568.50 | |
| 4 | 50300255 | CONC SUP-STR | 2.3 | CU YD | $6,700.00 | $17,890.00 | $6,146.36 | |
| 5 | 50300300 | PROTECTIVE COAT | 15.8 | SQ YD | $90.00 | $104.81 | $22.07 | |
| 6 | 50800205 | REINF BARS, EPOXY CTD | 365 | POUND | $10.00 | $17.85 | $16.11 | |
| 7 | 50800530 | MECHANICAL SPLICERS | 20 | EACH | $95.00 | $89.62 | $163.64 | |
| 8 | 63100085 | TRAF BAR TERM T6 | 1 | EACH | $6,000.00 | $6,120.00 | $6,588.21 | |
| 9 | 63200310 | GUARDRAIL REMOV | 38 | FOOT | $30.00 | $29.80 | $10.63 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $8,700.06 | $22,780.00 | $10,790.40 | |
| 11 | 70100207 | TRAF CONT-PROT 701402 | 2 | EACH | $8,550.00 | $13,165.00 | $25,803.05 | |
| 12 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $10,000.00 | $6,097.00 | $10,850.95 | |
| 13 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,425.00 | $2,145.00 | $1,259.58 | |
| 14 | 70107007 | PAVT MK BLKOUT TAPE 7 | 1,444 | FOOT | $3.50 | $3.96 | $4.63 | |
| 15 | 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $165.00 | $61.20 | $181.57 | |
| 16 | 70400100 | TEMP CONC BARRIER | 1,000 | FOOT | $33.50 | $31.15 | $37.31 | |
| 17 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $3,800.00 | $2,980.00 | $5,948.73 |