D-7 CRACK SEALING 2020-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $372,278 | ||
| 2 | Complete Asphalt Service Co. | $480,032 | +28.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 Complete Asphal… |
|---|---|---|---|---|---|---|---|
| 1 | X7010410 | SPEED DISPLAY TRAILER | 2 | CAL MO | $1,000.00 | $1,000.00 | |
| 2 | 45200100 | JT CR RT PCC PAV/SHLD | 269,524 | FOOT | $0.3800 | $0.0500 | |
| 3 | 45200300 | JT OR CRACK FILLING | 126,676 | POUND | $1.70 | $3.31 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $21,000.00 | $28,800.00 | |
| 5 | 70100420 | TRAF CONT-PROT 701411 | 4 | EACH | $500.00 | $50.00 | |
| 6 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $6,000.00 | $50.00 | |
| 7 | 70107025 | CHANGEABLE MESSAGE SN | 58 | CAL DA | $95.00 | $110.00 | |
| 8 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $18,000.00 | $9,828.00 |