P(B-2)-BDR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $441,013 | ||
| 2 | Sangamo Construction Company | $522,171 | +18.4% | |
| 3 | White Construction LLC | $536,963 | +21.8% | |
| 4 | Otto Baum Company, Inc. | $544,499 | +23.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 Sangamo Constru… | #3 White Construct… | #4 Otto Baum Compa… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X6024503 | INLET ADJ NEW F&G SPL | 2 | EACH | $5,261.97 | $8,388.48 | $7,500.00 | $4,486.82 | |
| 2 | X7010200 | TC-PROT 701316 SPL | 1 | EACH | $12,115.69 | $36,771.85 | $19,000.00 | $19,333.98 | |
| 3 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $5,667.91 | $3,095.57 | $2,900.00 | $3,483.48 | |
| 4 | Z0012130 | BR DECK SCAR 3/4 | 780 | SQ YD | $73.63 | $88.16 | $125.00 | $78.59 | |
| 5 | Z0012164 | BR DK MIC C OVL 2 1/2 | 780 | SQ YD | $124.79 | $149.56 | $175.00 | $110.75 | |
| 6 | Z0016001 | DECK SLAB REP (FD-T1) | 5 | SQ YD | $845.14 | $2,848.61 | $2,000.00 | $3,585.14 | |
| 7 | Z0041895 | POLYMER CONCRETE | 5 | CU FT | $1,101.41 | $1,573.77 | $1,500.00 | $993.99 | |
| 8 | 40600290 | BIT MATLS TACK CT | 1,063 | POUND | $0.9200 | $1.97 | $1.85 | $1.11 | |
| 9 | 40600982 | HMA SURF REM BUTT JT | 347 | SQ YD | $39.48 | $23.00 | $21.55 | $81.54 | |
| 10 | 40600990 | TEMPORARY RAMP | 92 | SQ YD | $26.09 | $72.21 | $100.00 | $106.06 | |
| 11 | 40604060 | HMA SC IL-9.5 D N50 | 143 | TON | $299.70 | $225.34 | $211.10 | $361.83 | |
| 12 | 48102100 | AGG WEDGE SHLD TYPE B | 23 | TON | $159.17 | $157.16 | $175.00 | $161.40 | |
| 13 | 48203100 | HMA SHOULDERS | 93 | TON | $346.87 | $225.34 | $211.10 | $418.77 | |
| 14 | 50300260 | BR DECK GROOVING | 740 | SQ YD | $15.76 | $10.13 | $15.00 | $14.90 | |
| 15 | 50300300 | PROTECTIVE COAT | 780 | SQ YD | $4.63 | $4.00 | $3.00 | $6.74 | |
| 16 | 63000001 | SPBGR TY A 6FT POSTS | 608 | FOOT | $36.14 | $35.07 | $32.85 | $39.46 | |
| 17 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $4,785.00 | $4,643.35 | $4,350.00 | $5,225.23 | |
| 18 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,888.50 | $3,773.39 | $3,535.00 | $4,246.25 | |
| 19 | 63200310 | GUARDRAIL REMOV | 958 | FOOT | $6.57 | $9.88 | $12.00 | $16.28 | |
| 20 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,849.98 | $2,549.01 | $2,000.00 | $2,616.75 | |
| 21 | 67100100 | MOBILIZATION | 1 | L SUM | $12,251.79 | $30,808.06 | $32,000.00 | $37,478.90 | |
| 22 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $878.55 | $11,211.50 | $5,000.00 | $4,374.01 | |
| 23 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $9,907.91 | $11,181.40 | $15,000.00 | $15,315.32 | |
| 24 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $799.42 | $1,766.51 | $700.00 | $840.84 | |
| 25 | 70107025 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $66.00 | $178.27 | $80.00 | $96.10 | |
| 26 | 70300100 | SHORT TERM PAVT MKING | 76 | FOOT | $1.78 | $1.98 | $3.00 | $4.20 | |
| 27 | 70300150 | SHRT TRM PAVT MK REM | 26 | SQ FT | $3.84 | $3.18 | $40.00 | $21.14 | |
| 28 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $52.25 | $50.70 | $297.50 | $57.06 | |
| 29 | 78001120 | PAINT PVT MK LINE 5 | 3,028 | FOOT | $1.60 | $1.55 | $1.45 | $1.93 | |
| 30 | 78200005 | GRDRAIL REF TYPE A | 30 | EACH | $10.45 | $10.14 | $9.50 | $11.41 | |
| 31 | 78300200 | RAISED REF PVT MK REM | 6 | EACH | $36.24 | $14.02 | $1,000.00 | $267.91 | |
| 32 | 78300201 | PAVMT MRKG REM GRIND | 973 | SQ FT | $4.40 | $4.27 | $4.00 | $9.61 |