(118)RS-2,(119)RS-4,SW
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | The Kilian Corporation Low bidder | $2,687,989 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 The Kilian Corp… |
|---|---|---|---|---|---|---|
| 1 | X4200001 | CIR-FDR EMULS ASPHALT | 139,814 | GALLON | $2.55 | |
| 2 | X4200002 | CIP RECYCLING, 4.0" | 96,423 | SQ YD | $3.65 | |
| 3 | X4401198 | HMA SURF REM VAR DP | 96,423 | SQ YD | $1.35 | |
| 4 | Z0012754 | STR REP CON DP = < 5 | 9 | SQ FT | $325.00 | |
| 5 | Z0034105 | MATL TRANSFER DEVICE | 11,681 | TON | $5.00 | |
| 6 | Z0049799 | PROT RESET SURVEY MRK | 3 | EACH | $2,100.00 | |
| 7 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | |
| 9 | 20800150 | TRENCH BACKFILL | 114 | CU YD | $40.00 | |
| 10 | 21400100 | GRADING & SHAP DITCH | 420 | FOOT | $14.50 | |
| 11 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $10,000.00 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $2.00 | |
| 13 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $2.00 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $2.00 | |
| 15 | 25000700 | AGR GROUND LIMESTONE | 0.7 | TON | $1,725.00 | |
| 16 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $6,000.00 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 25 | POUND | $2.75 | |
| 18 | 28000500 | INLET & PIPE PROTECT | 3 | EACH | $140.00 | |
| 19 | 30201700 | PORTLAND CEMENT | 220 | TON | $230.00 | |
| 20 | 40200800 | AGG SURF CSE B | 42 | TON | $57.00 | |
| 21 | 40600290 | BIT MATLS TACK CT | 49,894 | POUND | $1.10 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 4,198 | SQ YD | $7.00 | |
| 23 | 40600990 | TEMPORARY RAMP | 1,557 | SQ YD | $0.0100 | |
| 24 | 40604050 | HMA SC IL-9.5 C N50 | 11,681 | TON | $91.00 | |
| 25 | 40733705 | LONG JOINT SEALANT | 35,640 | FOOT | $2.40 | |
| 26 | 40800050 | INCIDENTAL HMA SURF | 336 | TON | $245.00 | |
| 27 | 44000155 | HMA SURF REM 1 1/2 | 3,736 | SQ YD | $1.70 | |
| 28 | 44000157 | HMA SURF REM 2 | 2,027 | SQ YD | $2.25 | |
| 29 | 44000165 | HMA SURF REM 4 | 1,056 | SQ YD | $4.35 | |
| 30 | 44000600 | SIDEWALK REM | 17 | SQ FT | $10.00 | |
| 31 | 44201789 | CL D PATCH T2 12 | 18 | SQ YD | $230.00 | |
| 32 | 44201794 | CL D PATCH T3 12 | 98 | SQ YD | $200.00 | |
| 33 | 48102100 | AGG WEDGE SHLD TYPE B | 1,537 | TON | $0.0100 | |
| 34 | 50104400 | CONC HDWL REM | 7 | EACH | $1,275.00 | |
| 35 | 50105220 | PIPE CULVERT REMOV | 283 | FOOT | $36.00 | |
| 36 | 542A0223 | P CUL CL A 1 18 | 129 | FOOT | $169.00 | |
| 37 | 542A0241 | P CUL CL A 1 36 | 65 | FOOT | $227.00 | |
| 38 | 54213663 | PRC FLAR END SEC 18 | 2 | EACH | $1,115.00 | |
| 39 | 54215418 | CIP RC END SEC 18 | 2 | EACH | $5,200.00 | |
| 40 | 54215436 | CIP RC END SEC 36 | 2 | EACH | $7,570.00 | |
| 41 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,775.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $122,320.00 | |
| 43 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $550.00 | |
| 44 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $38,500.00 | |
| 45 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $9,150.00 | |
| 46 | 70300100 | SHORT TERM PAVT MKING | 9,720 | FOOT | $3.00 | |
| 47 | 70300150 | SHRT TRM PAVT MK REM | 1,079 | SQ FT | $8.00 | |
| 48 | 78001120 | PAINT PVT MK LINE 5 | 92,809 | FOOT | $0.1600 | |
| 49 | 78100100 | RAISED REFL PAVT MKR | 465 | EACH | $36.00 | |
| 50 | 78300200 | RAISED REF PVT MK REM | 715 | EACH | $0.0100 |