Bid tab 72L22

Let Sep 18, 2020 · District 6 · Various Sign up free

‹ Sep 2020 results

HIGH MAST LIGHT TOWER REP 2019

Let date
Friday, September 18, 2020
Contract
72L22 · job page
District
District 6
County
Various
Highway
Limits
Removal and replacement of high mast light towers on I-55 at the Litchfield and Elkhart interchanges.

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Bodine Electric of Decatur Low bidder $47,248
2 Capitol Construction Group, LLC d/b/a Egizii Electric $73,025 +54.6%
3 Wissehr Electric, Inc. $118,604 +151.0%
4 J. Ranck Electric, Inc. $154,550 +227.1%

Bid tab: unit prices 6 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Bodine Electric…#2 Capitol Constru…#3 Wissehr Electri…#4 J. Ranck Electr…
1X8420510 REM TOWER FDN2EACH $1,073.03 $1,050.00 $10,000.00 $1,500.00
267100100 MOBILIZATION1L SUM $7,743.04 $9,000.00 $31,976.00 $29,000.00
370100825 TRAF CONT-PROT 7014561L SUM $88.74 $9,000.00 $3,000.00 $25,000.00
483700200 LT TOWER FDN 42D43FOOT $628.10 $775.00 $400.00 $850.00
584400205 RELOC EX LIGHT TOWER2EACH $5,104.08 $7,500.00 $22,988.00 $26,500.00
689502350 REM & RE ELCBL FR CON40FOOT $1.34 $115.00 $11.30 $200.00