(54-10)BRR,BDR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $1,347,949 | ||
| 2 | Halverson Construction Co., Inc. | $1,433,651 | +6.4% | |
| 3 | Otto Baum Company, Inc. | $1,555,952 | +15.4% | |
| 4 | Freesen, a div of UCM, Inc. | $1,673,608 | +24.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 Halverson Const… | #3 Otto Baum Compa… | #4 Freesen, a div … |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0323586 | PIPE DRAIN REMOVAL | 702 | FOOT | $11.07 | $25.00 | $3.43 | $22.02 | |
| 2 | X0327980 | PAVMT MRKG REM WTR BL | 1,290 | SQ FT | $1.33 | $1.00 | $1.06 | $1.08 | |
| 3 | X4404260 | PAVED SHLD REMOVAL SP | 1,816 | SQ YD | $24.55 | $20.00 | $16.43 | $51.77 | |
| 4 | X5030250 | BR DECK GROOVING LONG | 764 | SQ YD | $12.16 | $13.25 | $17.34 | $14.78 | |
| 5 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $1,181.84 | $2,980.00 | $3,170.95 | $1,755.00 | |
| 6 | Z0001495 | BR APPROACH SHLD REM | 92 | SQ YD | $139.91 | $105.00 | $31.91 | $146.75 | |
| 7 | Z0001800 | APPROACH SL REP (PD) | 44 | SQ YD | $563.80 | $715.00 | $638.42 | $768.72 | |
| 8 | Z0012130 | BR DECK SCAR 3/4 | 1,202 | SQ YD | $57.14 | $70.00 | $81.41 | $79.18 | |
| 9 | Z0012166 | BR DK MIC C OVL 2 3/4 | 1,202 | SQ YD | $89.31 | $120.00 | $136.64 | $146.46 | |
| 10 | Z0012754 | STR REP CON DP = < 5 | 28.5 | SQ FT | $255.22 | $260.00 | $420.00 | $102.97 | |
| 11 | Z0016002 | DECK SLAB REP (FD-T2) | 9 | SQ YD | $1,325.62 | $1,895.00 | $3,000.00 | $1,424.28 | |
| 12 | Z0029090 | DIAMOND GRIND BR SEC | 1,082 | SQ YD | $19.46 | $25.00 | $24.52 | $22.71 | |
| 13 | Z0040530 | PIPE UNDERDRAIN REMOV | 2,034 | FOOT | $4.56 | $2.25 | $4.74 | $3.17 | |
| 14 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $6,883.95 | $5,600.00 | $21,000.00 | $6,684.78 | |
| 15 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 17 | 21400100 | GRADING & SHAP DITCH | 50 | FOOT | $34.44 | $30.00 | $50.02 | $37.80 | |
| 18 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $11,178.48 | $5,886.00 | $11,226.04 | $6,356.88 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $4.24 | $3.00 | $4.26 | $3.24 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $4.24 | $3.00 | $4.26 | $3.24 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $4.24 | $3.00 | $4.26 | $3.24 | |
| 22 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $10,881.96 | $5,886.00 | $10,933.40 | $6,356.88 | |
| 23 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $3.30 | $9.50 | $3.19 | $5.51 | |
| 24 | 28100107 | STONE RIPRAP CL A4 | 28 | SQ YD | $189.87 | $170.00 | $172.81 | $251.12 | |
| 25 | 28100125 | STONE RIPRAP CL B3 | 6 | SQ YD | $163.86 | $155.00 | $591.39 | $489.74 | |
| 26 | 31101900 | SUB GRAN MAT C | 723 | TON | $70.25 | $65.00 | $49.93 | $71.52 | |
| 27 | 35501316 | HMA BASE CSE 8 | 1,807 | SQ YD | $68.10 | $76.68 | $68.42 | $64.30 | |
| 28 | 35501324 | HMA BASE CSE 10 | 92 | SQ YD | $278.94 | $213.93 | $280.26 | $263.38 | |
| 29 | 40600290 | BIT MATLS TACK CT | 2,538.5 | POUND | $1.15 | $2.00 | $1.16 | $1.09 | |
| 30 | 40600982 | HMA SURF REM BUTT JT | 748 | SQ YD | $11.68 | $15.00 | $19.70 | $23.45 | |
| 31 | 40600990 | TEMPORARY RAMP | 64 | SQ YD | $47.12 | $25.58 | $27.22 | $49.92 | |
| 32 | 40604162 | P HMA SC IL-9.5 D N70 | 539 | TON | $183.01 | $195.76 | $183.87 | $172.80 | |
| 33 | 44000155 | HMA SURF REM 1 1/2 | 267 | SQ YD | $10.32 | $11.50 | $22.52 | $23.45 | |
| 34 | 48102100 | AGG WEDGE SHLD TYPE B | 60 | TON | $78.68 | $110.00 | $121.11 | $183.45 | |
| 35 | 50102400 | CONC REM | 23 | CU YD | $2,313.90 | $3,200.00 | $3,288.66 | $2,912.78 | |
| 36 | 50104650 | SLOPE WALL REMOV | 115 | SQ YD | $98.59 | $200.00 | $116.51 | $136.09 | |
| 37 | 50157300 | PROTECTIVE SHIELD | 1,292 | SQ YD | $2.00 | $1.00 | $31.71 | $59.78 | |
| 38 | 50300255 | CONC SUP-STR | 28 | CU YD | $2,930.50 | $3,200.00 | $3,244.26 | $3,807.74 | |
| 39 | 50300300 | PROTECTIVE COAT | 1,292 | SQ YD | $2.84 | $3.00 | $5.66 | $6.20 | |
| 40 | 50800205 | REINF BARS, EPOXY CTD | 3,500 | POUND | $4.44 | $3.00 | $2.34 | $2.11 | |
| 41 | 50800515 | BAR SPLICERS | 56 | EACH | $40.74 | $50.00 | $19.95 | $20.67 | |
| 42 | 51100100 | SLOPE WALL 4 | 115 | SQ YD | $152.45 | $300.00 | $334.86 | $356.44 | |
| 43 | 52000110 | PREF JT STRIP SEAL | 172 | FOOT | $204.08 | $215.00 | $212.44 | $243.09 | |
| 44 | 54262712 | METAL FL END SEC 12" | 8 | EACH | $230.21 | $450.00 | $344.68 | $421.90 | |
| 45 | 58700300 | CONCRETE SEALER | 29 | SQ FT | $2.16 | $11.00 | $32.67 | $45.52 | |
| 46 | 59300100 | CONTR LOW-STRENG MATL | 78 | CU YD | $172.33 | $350.00 | $249.17 | $278.79 | |
| 47 | 60100060 | CONC HDWL FOR P DRAIN | 8 | EACH | $333.56 | $525.00 | $680.05 | $690.23 | |
| 48 | 60100945 | PIPE DRAINS 12 | 200 | FOOT | $30.48 | $55.00 | $81.47 | $68.47 | |
| 49 | 60108100 | PIPE UNDERDRAIN 4 SP | 140 | FOOT | $21.97 | $35.00 | $20.60 | $20.91 | |
| 50 | 60108104 | PIPE UNDERDR T 1 4 | 2,034 | FOOT | $9.76 | $15.00 | $25.08 | $25.46 | |
| 51 | 61000225 | TY F INLET BOX 610001 | 4 | EACH | $7,331.53 | $4,500.00 | $3,280.40 | $2,616.23 | |
| 52 | 61000335 | TY G INLET BOX 610001 | 4 | EACH | $5,251.51 | $3,500.00 | $2,454.68 | $1,672.05 | |
| 53 | 63000001 | SPBGR TY A 6FT POSTS | 1,000 | FOOT | $20.12 | $19.00 | $24.69 | $20.52 | |
| 54 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $2,647.67 | $2,500.00 | $3,788.12 | $2,700.00 | |
| 55 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $2,647.67 | $2,500.00 | $3,229.48 | $2,700.00 | |
| 56 | 63200310 | GUARDRAIL REMOV | 1,357 | FOOT | $7.41 | $7.00 | $7.61 | $7.56 | |
| 57 | 64200116 | SHOULDER RUM STRIP 16 | 2,034 | FOOT | $4.21 | $4.50 | $1.84 | $1.87 | |
| 58 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1,849.22 | $2,604.27 | $2,239.12 | $3,038.54 | |
| 59 | 67100100 | MOBILIZATION | 1 | L SUM | $79,528.99 | $86,019.08 | $75,034.69 | $114,343.95 | |
| 60 | 70100207 | TRAF CONT-PROT 701402 | 1 | EACH | $92,702.38 | $39,650.00 | $101,689.00 | $84,715.13 | |
| 61 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $24,876.94 | $13,229.96 | $1,596.12 | $121.54 | |
| 62 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $21,886.95 | $1,500.00 | $1,596.12 | $9,234.00 | |
| 63 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $148.02 | $150.00 | $159.61 | $139.59 | |
| 64 | 70300100 | SHORT TERM PAVT MKING | 395 | FOOT | $1.45 | $2.00 | $5.32 | $1.62 | |
| 65 | 70300150 | SHRT TRM PAVT MK REM | 132 | SQ FT | $2.68 | $1.00 | $5.32 | $3.75 | |
| 66 | 70400100 | TEMP CONC BARRIER | 750 | FOOT | $27.45 | $32.00 | $39.30 | $25.65 | |
| 67 | 70400200 | REL TEMP CONC BARRIER | 750 | FOOT | $7.24 | $6.00 | $8.51 | $4.26 | |
| 68 | 70600260 | IMP ATTN TEMP FRN TL3 | 2 | EACH | $6,382.43 | $8,800.00 | $9,151.07 | $7,274.74 | |
| 69 | 70600332 | IMP ATTN REL FRN TL3 | 2 | EACH | $2,019.96 | $2,500.00 | $1,968.55 | $2,430.75 | |
| 70 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $37.07 | $35.00 | $42.56 | $37.80 | |
| 71 | 78009005 | MOD URETH PM LINE 5 | 3,095 | FOOT | $3.71 | $3.69 | $2.98 | $3.02 | |
| 72 | 78100100 | RAISED REFL PAVT MKR | 12 | EACH | $43.42 | $355.45 | $378.23 | $383.89 | |
| 73 | 78200005 | GRDRAIL REF TYPE A | 20 | EACH | $10.59 | $10.00 | $9.58 | $10.80 | |
| 74 | 78300200 | RAISED REF PVT MK REM | 12 | EACH | $10.38 | $101.98 | $54.14 | $67.11 |