D6(CR)SANGAMON CO. 2018
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | CSD Environmental Services, Inc. Low bidder | $64,507 | ||
| 2 | County Contractors, Inc. | $65,311 | +1.2% | |
| 3 | Phoenix Corporation of the Quad Cities | $78,169 | +21.2% | |
| 4 | K. E. Vas Company | $83,964 | +30.2% | |
| 5 | John J. Klein d/b/a Klein Excavating | $85,422 | +32.4% | |
| 6 | Perry Broughton Trucking and Excavating, Inc. | $96,136 | +49.0% | |
| 7 | Prado Construction | $143,700 | +122.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CSD Environment… | #2 County Contract… | #3 Phoenix Corpora… | #4 K. E. Vas Compa… | #5 John J. Klein d… | #6 Perry Broughton… | #7 Prado Construct… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 20800150 | TRENCH BACKFILL | 85 | CU YD | $44.50 | $65.00 | $75.00 | $70.00 | $65.00 | $92.49 | $144.22 | |
| 2 | 44201329 | CL C PATCH T2 8 | 32 | SQ YD | $288.00 | $350.00 | $250.00 | $315.00 | $292.00 | $514.27 | $280.06 | |
| 3 | 44201365 | CL C PATCH T2 11 | 24 | SQ YD | $220.00 | $350.00 | $300.00 | $415.00 | $328.00 | $494.69 | $217.00 | |
| 4 | 50105220 | PIPE CULVERT REMOV | 143 | FOOT | $7.87 | $22.00 | $19.00 | $10.00 | $95.00 | $26.83 | $94.56 | |
| 5 | 542A0235 | P CUL CL A 1 30 | 86 | FOOT | $244.00 | $135.00 | $185.00 | $269.00 | $184.00 | $231.93 | $402.82 | |
| 6 | 542A1069 | P CUL CL A 2 24 | 54 | FOOT | $139.25 | $120.00 | $145.00 | $215.00 | $131.00 | $214.91 | $298.96 | |
| 7 | 54213669 | PRC FLAR END SEC 24 | 2 | EACH | $950.00 | $1,600.00 | $1,500.00 | $1,000.00 | $1,500.00 | $1,321.21 | $3,159.21 | |
| 8 | 54213675 | PRC FLAR END SEC 30 | 4 | EACH | $1,250.00 | $1,800.00 | $1,700.00 | $1,200.00 | $1,860.00 | $1,665.78 | $3,348.21 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $4,200.00 | $5,300.00 | $18,870.00 | $5,000.00 | $5,058.00 | $2,465.60 | $11,995.48 | |
| 10 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,500.00 | $3,250.00 | $1,467.00 | $10,000.00 | $10,700.00 | $12,785.70 | $21,256.68 |