21RS-8,23RS-7
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $2,068,376 | ||
| 2 | P. H. Broughton & Sons, Inc. | $2,101,109 | +1.6% | |
| 3 | Truman L. Flatt & Sons Co., Inc. | $2,128,243 | +2.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 P. H. Broughton… | #3 Truman L. Flatt… |
|---|---|---|---|---|---|---|---|---|
| 1 | X1400349 | SOLAR-POWER FB INSTLN | 2 | EACH | $3,570.00 | $4,508.73 | $3,468.00 | |
| 2 | X4405020 | LONG PAR DEP REM 2 | 2,000 | FOOT | $4.18 | $6.31 | $6.61 | |
| 3 | X4420900 | LONG PART DEPTH PATCH | 50 | TON | $252.97 | $375.22 | $326.06 | |
| 4 | Z0076600 | TRAINEES | 2,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 5 | Z0076604 | TRAINEES TPG | 2,500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 6 | 35101400 | AGG BASE CSE B | 1 | TON | $106.65 | $250.00 | $151.31 | |
| 7 | 40600290 | BIT MATLS TACK CT | 50,822 | POUND | $0.9000 | $0.5600 | $0.6600 | |
| 8 | 40600370 | LONG JOINT SEALANT | 27,454 | FOOT | $2.58 | $2.79 | $2.58 | |
| 9 | 40600405 | MATL TRANSFER DEVICE | 5,496 | TON | $2.74 | $3.49 | $3.44 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 1,321 | SQ YD | $7.44 | $19.12 | $16.60 | |
| 11 | 40600985 | PCC SURF REM BUTT JT | 296 | SQ YD | $7.44 | $30.87 | $7.35 | |
| 12 | 40602965 | HMA BC IL-9.5FG N50 | 3,851 | TON | $113.70 | $112.82 | $113.33 | |
| 13 | 40603215 | P HMA BC IL-9.5FG N50 | 728 | TON | $124.87 | $122.12 | $120.30 | |
| 14 | 40604050 | HMA SC IL-9.5 C N50 | 4,622 | TON | $112.45 | $108.07 | $109.29 | |
| 15 | 40604150 | P HMA SC IL-9.5 C N50 | 874 | TON | $115.66 | $117.38 | $117.46 | |
| 16 | 40800029 | BIT MATLS TACK CT | 1,221 | POUND | $0.8400 | $1.50 | $0.6600 | |
| 17 | 40800050 | INCIDENTAL HMA SURF | 361 | TON | $238.73 | $225.17 | $224.08 | |
| 18 | 44000155 | HMA SURF REM 1 1/2 | 39,884 | SQ YD | $1.85 | $1.12 | $2.39 | |
| 19 | 44200050 | WELDED WIRE REINF | 35 | SQ YD | $25.20 | $26.84 | $25.50 | |
| 20 | 44200956 | CL B PATCH T2 9 | 375 | SQ YD | $231.00 | $316.68 | $300.90 | |
| 21 | 44200962 | CL B PATCH T3 9 | 35 | SQ YD | $227.85 | $316.68 | $300.90 | |
| 22 | 44201298 | DOWEL BARS 1 1/4 | 594 | EACH | $28.35 | $21.47 | $20.40 | |
| 23 | 44213200 | SAW CUTS | 1,406 | FOOT | $9.45 | $6.39 | $6.07 | |
| 24 | 48102100 | AGG WEDGE SHLD TYPE B | 1,511 | TON | $28.63 | $30.33 | $28.82 | |
| 25 | 48203008 | HMA SHOULDERS 2 3/4 | 9,866 | SQ YD | $18.06 | $19.34 | $22.14 | |
| 26 | 60920048 | PIPE CULV CLEANED 48 | 80 | FOOT | $86.05 | $118.09 | $112.20 | |
| 27 | 64200108 | SHOULDER RUM STRIP 8 | 29,038 | FOOT | $0.2500 | $0.4500 | $0.4700 | |
| 28 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,199.34 | $3,083.29 | $2,694.20 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $54,753.06 | $42,982.16 | $39,300.60 | |
| 30 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $10,500.00 | $15,029.10 | $14,280.00 | |
| 31 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $4,601.18 | $13,472.51 | $7,395.15 | |
| 32 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $111.88 | $128.82 | $103.80 | |
| 33 | 70300100 | SHORT TERM PAVT MKING | 7,404 | FOOT | $1.09 | $1.61 | $0.4200 | |
| 34 | 70300150 | SHRT TRM PAVT MK REM | 2,468 | SQ FT | $0.0100 | $2.35 | $3.18 | |
| 35 | 78009000 | MOD URETH PM LTR-SYM | 94 | SQ FT | $4.20 | $4.29 | $12.24 | |
| 36 | 78009005 | MOD URETH PM LINE 5 | 66,430 | FOOT | $0.9800 | $1.00 | $0.7100 | |
| 37 | 78009006 | MOD URETH PM LINE 6 | 534 | FOOT | $1.18 | $1.20 | $0.7700 | |
| 38 | 78009012 | MOD URETH PM LINE 12 | 176 | FOOT | $2.35 | $2.40 | $12.24 | |
| 39 | 78009024 | MOD URETH PM LINE 24 | 162 | FOOT | $4.73 | $4.83 | $20.40 | |
| 40 | 78100100 | RAISED REFL PAVT MKR | 402 | EACH | $37.52 | $38.36 | $47.96 | |
| 41 | 78300200 | RAISED REF PVT MK REM | 402 | EACH | $10.15 | $9.46 | $8.41 |