(17X)RS-1,SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $3,597,405 | ||
| 2 | P. H. Broughton & Sons, Inc. | $3,618,306 | +0.6% | |
| 3 | Truman L. Flatt & Sons Co., Inc. | $3,665,028 | +1.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 P. H. Broughton… | #3 Truman L. Flatt… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4240420 | PC CONC SIDEWALK 4 SP | 50 | SQ FT | $60.66 | $90.00 | $121.80 | |
| 2 | X4402020 | CONC MEDIAN SURF REM | 8 | SQ FT | $74.52 | $77.30 | $75.60 | |
| 3 | X4403300 | CONC MEDIAN REMOV | 550 | SQ FT | $14.15 | $25.00 | $18.90 | |
| 4 | X4406824 | PCC SURF REM 3 | 80 | SQ YD | $16.09 | $22.88 | $27.57 | |
| 5 | X8570215 | FAC IN EXIST CAB | 1 | EACH | $7,153.92 | $7,420.44 | $7,257.60 | |
| 6 | X8891013 | VIDEO VEH DET SYS 4 CAM | 1 | EACH | $33,384.96 | $34,628.73 | $33,868.80 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $11,289.84 | $16,103.39 | $4,725.00 | |
| 8 | Z0076600 | TRAINEES | 3,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 3,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 10 | 35101600 | AGG BASE CSE B 4 | 40 | SQ YD | $104.81 | $26.84 | $84.00 | |
| 11 | 35300728 | PCC BSE CSE 14 | 61 | SQ YD | $162.47 | $300.00 | $385.35 | |
| 12 | 40600290 | BIT MATLS TACK CT | 59,217 | POUND | $0.8800 | $0.6600 | $0.6800 | |
| 13 | 40600370 | LONG JOINT SEALANT | 41,662 | FOOT | $2.65 | $3.12 | $2.83 | |
| 14 | 40600405 | MATL TRANSFER DEVICE | 7,026 | TON | $6.19 | $5.24 | $6.12 | |
| 15 | 40600982 | HMA SURF REM BUTT JT | 1,222 | SQ YD | $9.05 | $26.88 | $14.87 | |
| 16 | 40600990 | TEMPORARY RAMP | 610 | SQ YD | $5.84 | $12.02 | $17.43 | |
| 17 | 40603218 | P HMA BC IL-9.5FG N70 | 5,865 | TON | $154.65 | $146.62 | $155.11 | |
| 18 | 40604162 | P HMA SC IL-9.5 D N70 | 7,038 | TON | $152.24 | $151.66 | $152.99 | |
| 19 | 40800029 | BIT MATLS TACK CT | 550 | POUND | $0.8500 | $1.00 | $0.6900 | |
| 20 | 40800050 | INCIDENTAL HMA SURF | 94 | TON | $368.71 | $470.80 | $366.08 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 20 | SQ FT | $51.76 | $75.00 | $63.00 | |
| 22 | 44000154 | HMA SURF REM 1 1/4 | 7,257 | SQ YD | $3.62 | $10.21 | $4.01 | |
| 23 | 44000159 | HMA SURF REM 2 1/2 | 83,640 | SQ YD | $4.50 | $4.21 | $4.78 | |
| 24 | 44000500 | COMB CURB GUTTER REM | 60 | FOOT | $14.48 | $33.56 | $30.09 | |
| 25 | 44000600 | SIDEWALK REM | 50 | SQ FT | $17.37 | $22.54 | $10.91 | |
| 26 | 44200553 | CL A PATCH T2 10 | 73 | SQ YD | $501.98 | $483.10 | $509.25 | |
| 27 | 44200557 | CL A PATCH T3 10 | 35 | SQ YD | $497.84 | $483.10 | $505.05 | |
| 28 | 44200559 | CL A PATCH T4 10 | 73 | SQ YD | $493.70 | $483.10 | $500.85 | |
| 29 | 44213000 | PATCH REINFORCEMENT | 182 | SQ YD | $80.73 | $161.03 | $81.90 | |
| 30 | 44213200 | SAW CUTS | 808 | FOOT | $11.39 | $13.42 | $11.55 | |
| 31 | 44213204 | TIE BARS 3/4 | 30 | EACH | $21.74 | $37.57 | $22.05 | |
| 32 | 48203100 | HMA SHOULDERS | 610 | TON | $132.41 | $172.82 | $166.86 | |
| 33 | 60255500 | MAN ADJUST | 5 | EACH | $1,206.66 | $4,152.55 | $1,026.10 | |
| 34 | 60260100 | INLETS ADJUST | 7 | EACH | $2,233.07 | $2,275.00 | $1,179.84 | |
| 35 | 60265700 | VV ADJUST | 8 | EACH | $768.46 | $1,000.00 | $815.31 | |
| 36 | 60605000 | COMB CC&G TY B-6.24 | 60 | FOOT | $108.23 | $120.00 | $204.75 | |
| 37 | 60618300 | CONC MEDIAN SURF 4 | 8 | SQ FT | $149.04 | $154.59 | $151.20 | |
| 38 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,526.05 | $3,723.39 | $3,076.51 | |
| 39 | 67100100 | MOBILIZATION | 1 | L SUM | $131,188.29 | $98,317.98 | $70,179.72 | |
| 40 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $26,550.36 | $26,838.98 | $36,038.73 | |
| 41 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $36,688.77 | $19,968.20 | $40,086.78 | |
| 42 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1,399.86 | $107.36 | $7,052.09 | |
| 43 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $103.50 | $107.36 | $99.53 | |
| 44 | 70107025 | CHANGEABLE MESSAGE SN | 360 | CAL DA | $65.21 | $67.63 | $105.00 | |
| 45 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $86,063.56 | $50,457.29 | $91,465.30 | |
| 46 | 70300100 | SHORT TERM PAVT MKING | 6,843 | FOOT | $0.0100 | $1.61 | $1.27 | |
| 47 | 70300150 | SHRT TRM PAVT MK REM | 753 | SQ FT | $1.25 | $12.29 | $3.53 | |
| 48 | 78009000 | MOD URETH PM LTR-SYM | 2,069 | SQ FT | $19.67 | $9.13 | $8.93 | |
| 49 | 78009005 | MOD URETH PM LINE 5 | 46,903 | FOOT | $0.7500 | $0.9400 | $0.9200 | |
| 50 | 78009006 | MOD URETH PM LINE 6 | 8,147 | FOOT | $2.07 | $1.13 | $1.10 | |
| 51 | 78009008 | MOD URETH PM LINE 8 | 3,067 | FOOT | $5.18 | $1.93 | $1.89 | |
| 52 | 78009012 | MOD URETH PM LINE 12 | 1,341 | FOOT | $9.32 | $4.03 | $3.94 | |
| 53 | 78009024 | MOD URETH PM LINE 24 | 739 | FOOT | $19.67 | $8.59 | $8.40 | |
| 54 | 78011000 | GRV RCSD PM LTR & SYM | 2,069 | SQ FT | $3.36 | $9.13 | $8.93 | |
| 55 | 78011030 | GRV RCSD PVT MRKG 6 | 46,903 | FOOT | $0.3700 | $0.7000 | $0.6800 | |
| 56 | 78011035 | GRV RCSD PVT MRKG 7 | 8,147 | FOOT | $1.04 | $0.8200 | $0.8000 | |
| 57 | 78011045 | GRV RCSD PVT MRKG 9 | 3,067 | FOOT | $2.59 | $3.01 | $2.94 | |
| 58 | 78011065 | GRV RCSD PVT MRKG 13 | 1,341 | FOOT | $4.66 | $4.56 | $4.46 | |
| 59 | 78011125 | GRV RCSD PVT MRKG 25 | 739 | FOOT | $9.32 | $9.13 | $8.93 | |
| 60 | 78100100 | RAISED REFL PAVT MKR | 980 | EACH | $39.81 | $56.90 | $55.65 | |
| 61 | 78300200 | RAISED REF PVT MK REM | 980 | EACH | $7.96 | $9.11 | $23.06 | |
| 62 | 81028350 | UNDRGRD C PVC 2 | 239 | FOOT | $40.99 | $42.51 | $41.58 | |
| 63 | 85706000 | INTERSEC MONITOR UNIT | 1 | EACH | $2,285.28 | $2,370.42 | $2,318.40 | |
| 64 | 87900200 | DRILL EX HANDHOLE | 4 | EACH | $894.24 | $927.56 | $907.20 |