(84-3-2)DR
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $80,363 | ||
| 2 | William Charles Construction Company, LLC | $101,200 | +25.9% | |
| 3 | Sangamo Construction Company | $103,232 | +28.5% | |
| 4 | Freesen, a div of UCM, Inc. | $111,937 | +39.3% | |
| 5 | Phoenix Corporation of the Quad Cities | $116,336 | +44.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 William Charles… | #3 Sangamo Constru… | #4 Freesen, a div … | #5 Phoenix Corpora… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 28100105 | STONE RIPRAP CL A3 | 34 | SQ YD | $132.00 | $175.00 | $178.32 | $161.88 | $164.00 | |
| 2 | 28200200 | FILTER FABRIC | 34 | SQ YD | $13.00 | $25.00 | $6.37 | $14.92 | $22.00 | |
| 3 | 50105220 | PIPE CULVERT REMOV | 198 | FOOT | $42.00 | $35.00 | $44.55 | $33.04 | $32.00 | |
| 4 | 50800105 | REINFORCEMENT BARS | 100 | POUND | $18.50 | $25.00 | $17.15 | $9.38 | $16.00 | |
| 5 | 54002020 | EXPAN BOLTS 3/4 | 12 | EACH | $125.00 | $150.00 | $109.70 | $124.27 | $128.00 | |
| 6 | 54210189 | PIPE ELBOW 24 | 6 | EACH | $1,250.00 | $925.00 | $512.22 | $1,152.66 | $4,100.00 | |
| 7 | 54248510 | CONCRETE COLLAR | 1.2 | CU YD | $2,275.00 | $7,000.00 | $2,491.78 | $6,272.91 | $4,000.00 | |
| 8 | 60100985 | PIPE DRAINS 24 | 198 | FOOT | $106.50 | $140.00 | $154.48 | $257.05 | $80.00 | |
| 9 | 61000050 | CONC THRUST BLOCKS | 3 | EACH | $950.00 | $3,500.00 | $911.45 | $2,894.52 | $2,500.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $6,000.00 | $6,090.71 | $6,784.28 | $14,000.00 | |
| 11 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $19,600.00 | $25,000.00 | $39,625.10 | $16,147.47 | $33,800.00 |