(86-9HB2)BDR,BRR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freesen, a div of UCM, Inc. Low bidder | $544,972 | ||
| 2 | Otto Baum Company, Inc. | $597,700 | +9.7% | |
| 3 | County Contractors, Inc. | $745,920 | +36.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freesen, a div … | #2 Otto Baum Compa… | #3 County Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0325748 | ACRYLIC COATING | 243 | SQ YD | $44.39 | $15.81 | $10.00 | |
| 2 | X0325749 | FIBER WRAP | 486 | SQ FT | $62.83 | $50.65 | $75.00 | |
| 3 | X5060704 | CLN & PT EXP RE-BAR | 15.4 | SQ FT | $486.85 | $248.53 | $335.00 | |
| 4 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $2,269.56 | $1,277.51 | $3,450.00 | |
| 5 | Z0001800 | APPR SLAB REPAIR (PD) | 5 | SQ YD | $1,236.73 | $898.02 | $750.00 | |
| 6 | Z0004556 | HMA SURFACE RM (DECK) | 759 | SQ YD | $12.40 | $6.06 | $7.25 | |
| 7 | Z0012130 | BR DECK SCAR 3/4 | 759 | SQ YD | $47.43 | $81.97 | $175.00 | |
| 8 | Z0012164 | BR DK MIC C OVL 2 1/2 | 759 | SQ YD | $128.33 | $134.49 | $205.50 | |
| 9 | Z0012754 | STR REP CON DP = < 5 | 142 | SQ FT | $375.30 | $260.35 | $210.00 | |
| 10 | Z0016002 | DECK SLAB REP (FD-T2) | 5 | SQ YD | $1,520.00 | $1,530.38 | $1,650.00 | |
| 11 | Z0041895 | POLYMER CONCRETE | 3.4 | CU FT | $1,481.26 | $1,985.31 | $1,900.00 | |
| 12 | Z0043800 | P P CONC I-BM REPAIR | 56 | SQ FT | $402.69 | $445.35 | $625.00 | |
| 13 | 40600982 | HMA SURF REM BUTT JT | 68 | SQ YD | $46.70 | $106.89 | $115.00 | |
| 14 | 40800029 | BIT MATLS TACK CT | 31 | POUND | $11.05 | $11.76 | $53.00 | |
| 15 | 40800050 | INCIDENTAL HMA SURF | 10 | TON | $1,630.32 | $1,735.61 | $1,690.00 | |
| 16 | 50102400 | CONC REM | 5.1 | CU YD | $6,335.17 | $2,680.38 | $6,250.00 | |
| 17 | 50157300 | PROTECTIVE SHIELD | 267 | SQ YD | $154.70 | $200.42 | $100.00 | |
| 18 | 50300225 | CONC STRUCT | 5.8 | CU YD | $4,604.62 | $3,262.03 | $5,000.00 | |
| 19 | 50300255 | CONC SUP-STR | 3.5 | CU YD | $3,468.73 | $4,385.91 | $6,275.00 | |
| 20 | 50300260 | BR DECK GROOVING | 702 | SQ YD | $10.31 | $14.57 | $13.00 | |
| 21 | 50300300 | PROTECTIVE COAT | 767 | SQ YD | $4.99 | $8.92 | $6.00 | |
| 22 | 50800205 | REINF BARS, EPOXY CTD | 1,140 | POUND | $6.91 | $5.70 | $6.50 | |
| 23 | 52000110 | PREF JT STRIP SEAL | 58 | FOOT | $298.21 | $286.05 | $385.00 | |
| 24 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,815.83 | $1,421.82 | $3,000.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $24,604.24 | $104,934.28 | $40,000.00 | |
| 26 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $36,290.66 | $30,225.77 | $80,000.00 | |
| 27 | 70107025 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $136.50 | $138.40 | $116.00 |