(B,150)RS-3
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | P. H. Broughton & Sons, Inc. Low bidder | $2,490,973 | ||
| 2 | Truman L. Flatt & Sons Co., Inc. | $2,501,179 | +0.4% | |
| 3 | Illinois Valley Paving, a div of UCM, Inc. | $2,789,146 | +12.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 P. H. Broughton… | #2 Truman L. Flatt… | #3 Illinois Valley… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4406260 | PART DEP REM T2 6 | 29 | SQ YD | $83.03 | $52.70 | $66.95 | |
| 2 | X4406460 | PART DEP REM T3 6 | 53 | SQ YD | $83.03 | $52.55 | $66.95 | |
| 3 | X4421000 | PARTIAL DEPTH PATCH | 28 | TON | $319.04 | $241.20 | $415.42 | |
| 4 | X5010523 | REM CONC END SEC | 1 | EACH | $616.93 | $586.50 | $603.75 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,729.30 | $14,280.00 | $10,121.85 | |
| 6 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 7 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 8 | 20100110 | TREE REMOV 6-15 | 105 | UNIT | $118.02 | $102.00 | $105.00 | |
| 9 | 20100210 | TREE REMOV OVER 15 | 99 | UNIT | $118.02 | $102.00 | $105.00 | |
| 10 | 21400100 | GRADING & SHAP DITCH | 1,973 | FOOT | $16.09 | $15.30 | $15.75 | |
| 11 | 25000200 | SEEDING CL 2 | 0.5 | ACRE | $3,755.26 | $3,570.00 | $3,675.00 | |
| 12 | 25000400 | NITROGEN FERT NUTR | 49 | POUND | $3.22 | $3.06 | $3.15 | |
| 13 | 25000500 | PHOSPHORUS FERT NUTR | 49 | POUND | $3.22 | $3.06 | $3.15 | |
| 14 | 25000600 | POTASSIUM FERT NUTR | 49 | POUND | $3.22 | $3.06 | $3.15 | |
| 15 | 25000700 | AGR GROUND LIMESTONE | 1 | TON | $214.59 | $204.00 | $210.00 | |
| 16 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $3,755.26 | $3,570.00 | $3,675.00 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 54 | POUND | $7.51 | $7.14 | $7.35 | |
| 18 | 28000305 | TEMP DITCH CHECKS | 176 | FOOT | $13.95 | $27.03 | $27.83 | |
| 19 | 28000500 | INLET & PIPE PROTECT | 8 | EACH | $209.22 | $367.20 | $378.00 | |
| 20 | 28100207 | STONE RIPRAP CL A4 | 388 | TON | $386.25 | $188.70 | $194.25 | |
| 21 | 28200200 | FILTER FABRIC | 875 | SQ YD | $2.41 | $2.30 | $2.36 | |
| 22 | 31101000 | SUB GRAN MAT B | 17 | TON | $53.65 | $56.92 | $87.01 | |
| 23 | 40200800 | AGG SURF COURSE TY B | 10 | TON | $53.65 | $51.00 | $52.50 | |
| 24 | 40600290 | BIT MATLS TACK CT | 61,244 | POUND | $0.5600 | $0.6800 | $1.12 | |
| 25 | 40600370 | LONG JOINT SEALANT | 33,704 | FOOT | $2.74 | $2.51 | $2.56 | |
| 26 | 40600405 | MATL TRANSFER DEVICE | 8,129 | TON | $3.49 | $3.25 | $3.76 | |
| 27 | 40600982 | HMA SURF REM BUTT JT | 1,083 | SQ YD | $22.42 | $22.96 | $24.28 | |
| 28 | 40600990 | TEMPORARY RAMP | 254 | SQ YD | $10.30 | $16.58 | $7.34 | |
| 29 | 40602965 | HMA BC IL-9.5FG N50 | 5,776 | TON | $108.56 | $109.19 | $119.34 | |
| 30 | 40604050 | HMA SC IL-9.5 C N50 | 7,014 | TON | $103.55 | $107.06 | $119.11 | |
| 31 | 40604164 | P HMA SC IL-9.5 D N90 | 1,115 | TON | $140.57 | $148.22 | $162.89 | |
| 32 | 40800029 | BIT MATLS TACK CT | 480 | POUND | $1.00 | $0.6900 | $0.8500 | |
| 33 | 40800050 | INCIDENTAL HMA SURF | 127 | TON | $277.89 | $325.56 | $342.77 | |
| 34 | 42000060 | WELDED WIRE REINF | 89 | SQ YD | $37.55 | $20.94 | $29.80 | |
| 35 | 44000153 | HMA SURF REM 1 | 37,255 | SQ YD | $1.45 | $1.79 | $2.20 | |
| 36 | 44000155 | HMA SURF REM 1 1/2 | 44,756 | SQ YD | $1.45 | $2.12 | $2.20 | |
| 37 | 44000157 | HMA SURF REM 2 | 11,351 | SQ YD | $1.45 | $4.51 | $4.85 | |
| 38 | 44000160 | HMA SURF REM 2 3/4 | 1,421 | SQ YD | $1.45 | $5.69 | $6.61 | |
| 39 | 44201025 | CL B PATCH T4 14 | 89 | SQ YD | $348.70 | $254.34 | $479.70 | |
| 40 | 44201299 | DOWEL BARS 1 1/2 | 60 | EACH | $32.19 | $53.16 | $36.60 | |
| 41 | 44213200 | SAW CUTS | 82 | FOOT | $10.73 | $10.29 | $42.25 | |
| 42 | 48102100 | AGG WEDGE SHLD TYPE B | 1,060 | TON | $47.21 | $44.88 | $44.07 | |
| 43 | 48203100 | HMA SHOULDERS | 163 | TON | $103.55 | $163.71 | $176.63 | |
| 44 | 54213669 | PRC FLAR END SEC 24 | 1 | EACH | $2,682.32 | $2,550.00 | $2,625.00 | |
| 45 | 60905305 | BOX CUL TO BE CLEANED | 46 | FOOT | $134.12 | $127.50 | $131.25 | |
| 46 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,081.76 | $2,456.72 | $3,495.03 | |
| 47 | 67100100 | MOBILIZATION | 1 | L SUM | $47,328.21 | $38,832.42 | $60,594.93 | |
| 48 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,471.94 | $909.02 | $0.0100 | |
| 49 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $13,948.08 | $13,827.90 | $24,231.62 | |
| 50 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $107.29 | $1,513.13 | $0.0100 | |
| 51 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $107.29 | $6,010.90 | $2,191.83 | |
| 52 | 70107025 | CHANGEABLE MESSAGE SN | 21 | CAL DA | $128.75 | $85.49 | $225.23 | |
| 53 | 70300100 | SHORT TERM PAVT MKING | 9,887 | FOOT | $1.61 | $0.4200 | $1.22 | |
| 54 | 70300150 | SHRT TRM PAVT MK REM | 3,296 | SQ FT | $1.76 | $2.80 | $0.0100 | |
| 55 | 78009000 | MOD URETH PM LTR-SYM | 255 | SQ FT | $5.36 | $12.24 | $12.60 | |
| 56 | 78009005 | MOD URETH PM LINE 5 | 83,202 | FOOT | $0.8600 | $0.5500 | $0.5700 | |
| 57 | 78009006 | MOD URETH PM LINE 6 | 1,075 | FOOT | $1.07 | $0.6000 | $0.6200 | |
| 58 | 78009008 | MOD URETH PM LINE 8 | 548 | FOOT | $3.22 | $4.08 | $4.20 | |
| 59 | 78009012 | MOD URETH PM LINE 12 | 1,320 | FOOT | $2.15 | $8.16 | $8.40 | |
| 60 | 78009024 | MOD URETH PM LINE 24 | 190 | FOOT | $5.36 | $12.24 | $12.60 | |
| 61 | 78100100 | RAISED REFL PAVT MKR | 500 | EACH | $45.40 | $43.16 | $44.43 | |
| 62 | 78200020 | CURB REFLECTORS | 47 | EACH | $5.36 | $5.10 | $5.25 | |
| 63 | 78300200 | RAISED REF PVT MK REM | 500 | EACH | $9.79 | $17.75 | $11.63 |