(10-7,10-7B-1)BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | ICC Group Inc. Low bidder | $2,968,000 | ||
| 2 | Stark Excavating, Inc. | $3,530,438 | +19.0% | |
| 3 | White Construction LLC | $3,758,631 | +26.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ICC Group Inc. | #2 Stark Excavatin… | #3 White Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0325748 | ACRYLIC COATING | 389 | SQ YD | $18.00 | $72.00 | $18.00 | |
| 2 | X0325749 | FIBER WRAP | 3,494 | SQ FT | $30.00 | $43.00 | $30.00 | |
| 3 | X0327640 | REAL-TIME TR CONT CBU | 10 | CAL MO | $1,000.00 | $1,500.00 | $1,000.00 | |
| 4 | X0327641 | REAL-TIME TR CONT SU | 160 | CAL MO | $360.00 | $400.00 | $360.00 | |
| 5 | X0328006 | REAL-TIME TR CON W SGN | 80 | CAL MO | $550.00 | $700.00 | $550.00 | |
| 6 | X2700001 | TEMP RUMBLE STRIPS SP | 16 | EACH | $2,128.00 | $1,400.00 | $2,128.00 | |
| 7 | X5030250 | BR DECK GROOVING LONG | 3,356 | SQ YD | $6.28 | $8.50 | $5.65 | |
| 8 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $3,850.00 | $3,000.00 | $3,850.00 | |
| 9 | Z0001899 | JACK & REM EX BEARING | 99 | EACH | $4,500.00 | $2,575.00 | $2,700.00 | |
| 10 | Z0003802 | REM EXIST BEARINGS | 29 | EACH | $600.00 | $1,250.00 | $1,800.00 | |
| 11 | Z0006014 | BR DK LTX C OLY 2 1/2 | 3,566 | SQ YD | $100.00 | $155.00 | $237.00 | |
| 12 | Z0012130 | BR DECK SCAR 3/4 | 3,566 | SQ YD | $40.00 | $41.00 | $48.00 | |
| 13 | Z0012754 | STR REP CON DP = < 5 | 370 | SQ FT | $125.00 | $185.00 | $118.00 | |
| 14 | Z0029090 | DIAMOND GRIND BR SEC | 3,202 | SQ YD | $12.36 | $18.00 | $12.41 | |
| 15 | Z0043800 | P P CONC I-BM REPAIR | 832 | SQ FT | $118.00 | $235.00 | $118.00 | |
| 16 | Z0073200 | TEMP SHORING & CRIB | 33 | EACH | $2,000.00 | $3,650.00 | $1,400.00 | |
| 17 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 18 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 19 | 40600290 | BIT MATLS TACK CT | 140 | POUND | $21.00 | $22.00 | $21.00 | |
| 20 | 40600982 | HMA SURF REM BUTT JT | 2,776 | SQ YD | $6.75 | $10.00 | $7.50 | |
| 21 | 40604174 | P HMA SC IL-9.5 E N90 | 144 | TON | $419.25 | $435.00 | $419.25 | |
| 22 | 48203100 | HMA SHOULDERS | 90 | TON | $504.75 | $525.00 | $504.75 | |
| 23 | 50102400 | CONC REM | 48.2 | CU YD | $1,700.00 | $3,275.00 | $3,800.00 | |
| 24 | 50300255 | CONC SUP-STR | 57.4 | CU YD | $1,900.00 | $5,795.00 | $3,900.00 | |
| 25 | 50300300 | PROTECTIVE COAT | 3,745 | SQ YD | $2.50 | $0.6000 | $5.50 | |
| 26 | 50500405 | F & E STRUCT STEEL | 19,640 | POUND | $15.00 | $9.75 | $13.00 | |
| 27 | 50800205 | REINF BARS, EPOXY CTD | 9,570 | POUND | $3.00 | $3.00 | $3.50 | |
| 28 | 50800515 | BAR SPLICERS | 120 | EACH | $75.00 | $57.00 | $65.00 | |
| 29 | 52000110 | PREF JT STRIP SEAL | 701 | FOOT | $175.00 | $190.00 | $250.00 | |
| 30 | 52100010 | ELAST BEARING ASSY T1 | 96 | EACH | $2,000.00 | $1,525.00 | $3,000.00 | |
| 31 | 52100520 | ANCHOR BOLTS 1 | 480 | EACH | $100.00 | $100.00 | $190.00 | |
| 32 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,000.00 | $2,100.00 | $2,300.00 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $156,906.60 | $210,000.00 | $220,294.45 | |
| 34 | 70100207 | TRAF CONT-PROT 701402 | 2 | EACH | $50,000.00 | $80,000.00 | $47,150.00 | |
| 35 | 70100420 | TRAF CONT-PROT 701411 | 2 | EACH | $1,275.00 | $2,000.00 | $1,275.00 | |
| 36 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $25,000.00 | $1,000.00 | $19,600.00 | |
| 37 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $250.00 | $150.00 | $250.00 | |
| 38 | 70400100 | TEMP CONC BARRIER | 2,450 | FOOT | $33.00 | $35.00 | $33.00 | |
| 39 | 70400200 | REL TEMP CONC BARRIER | 2,450 | FOOT | $5.00 | $5.00 | $5.00 | |
| 40 | 70600250 | IMP ATTN TEMP NRD TL3 | 4 | EACH | $5,045.00 | $5,200.00 | $5,045.00 | |
| 41 | 70600350 | IMP ATTN REL NRD TL3 | 4 | EACH | $1,525.00 | $1,000.00 | $1,525.00 |