$183.84Avg low bid / TON
$176.88Avg of all bids
—Avg engineer's estimate
11Jobs · 92,068.5 TON
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 3 | 4,184 | $182.95 | $174.85 |
| 2025 | 6 | 85,883 | $182.99 | $175.61 |
| 2024 | 2 | 2,001.5 | $222.20 | $218.42 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 76R36 | St. ClairDistrict 8 | 439 TON | $190.00 | The Kilian Corporation |
| Feb 27, 2026 | 70F77 | McleanDistrict 5 | 274 TON | $285.00 | Stark Excavating, Inc. |
| Jan 16, 2026 | 76U95 | St.clairDistrict 8 | 3,471 TON | $174.00 | The Kilian Corporation |
| Apr 25, 2025 | 76J62 | St.clairDistrict 8 | 14,126 TON | $159.13 | Christ Bros. Asphalt, Inc. |
| Apr 25, 2025 | 76U26 | MadisonDistrict 8 | 17,660 TON | $190.29 | Charles E. Mahoney Co. |
| Mar 7, 2025 | 70D55 | McleanDistrict 5 | 3,001 TON | $220.00 | Rowe Construction, a div of UCM, Inc. |
| Jan 17, 2025 | 70A55 | VermilionDistrict 5 | 3,074 TON | $219.60 | Open Road Paving Company LLC |
| Jan 17, 2025 | 72D00 | Montgomery, MacoupinDistrict 6 | 41,681 TON | $183.80 | Illinois Valley Paving, a div of UCM, Inc. |
| Jan 17, 2025 | 78884 | Franklin, JeffersonDistrict 9 | 6,341 TON | $175.18 | E. T. Simonds Construction Company |
| Dec 13, 2024 | 76U07 | MadisonDistrict 8 | 160.5 TON | $362.10 | Keeley & Sons, Inc. |
| Dec 13, 2024 | 70D76 | ChampaignDistrict 5 | 1,841 TON | $210.00 | Stark Excavating, Inc. |