D5 STADIUM PARKING
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | McCarthy Improvement Company Low bidder | $1,111,995 | ||
| 2 | Feutz Contractors, Inc. | $1,188,828 | +6.9% | |
| 3 | Kieffer Bros. Construction Co., Inc. | $1,439,754 | +29.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 McCarthy Improv… | #2 Feutz Contracto… | #3 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $20,000.00 | $8,800.00 | $48,495.00 | |
| 2 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 985 | CU YD | $43.00 | $55.00 | $44.00 | |
| 4 | 20800150 | TRENCH BACKFILL | 194 | CU YD | $75.00 | $48.00 | $77.00 | |
| 5 | 31100300 | SUB GRAN MAT A 4 | 5,582 | SQ YD | $12.00 | $12.25 | $14.00 | |
| 6 | 42000060 | WELDED WIRE REINF | 992 | SQ YD | $14.00 | $19.00 | $17.00 | |
| 7 | 42000501 | PCC PVT 10 JOINTED | 4,590 | SQ YD | $105.00 | $113.00 | $134.50 | |
| 8 | 42000540 | PCC PVT 12 | 992 | SQ YD | $130.00 | $132.00 | $162.87 | |
| 9 | 44000100 | PAVEMENT REM | 5,582 | SQ YD | $20.00 | $23.75 | $52.15 | |
| 10 | 50102400 | CONC REM | 0.2 | CU YD | $15,000.00 | $6,000.00 | $2,186.25 | |
| 11 | 550B0050 | STORM SEW CL B 1 12 | 78 | FOOT | $70.00 | $91.00 | $60.18 | |
| 12 | 550B0070 | STORM SEW CL B 1 15 | 119 | FOOT | $78.00 | $110.00 | $72.27 | |
| 13 | 55100200 | STORM SEWER REM 6 | 360 | FOOT | $18.00 | $18.00 | $11.13 | |
| 14 | 55100300 | STORM SEWER REM 8 | 480 | FOOT | $12.00 | $18.00 | $13.78 | |
| 15 | 55100500 | STORM SEWER REM 12 | 30 | FOOT | $15.00 | $18.00 | $34.45 | |
| 16 | 55100600 | STORM SEWER REM 14 | 60 | FOOT | $14.00 | $18.00 | $45.58 | |
| 17 | 55100900 | STORM SEWER REM 18 | 71 | FOOT | $6.00 | $22.00 | $45.58 | |
| 18 | 56109210 | WATER VALVES ADJUST | 2 | EACH | $250.00 | $1,300.00 | $225.25 | |
| 19 | 59300100 | CONTR LOW-STRENG MATL | 100 | CU YD | $180.00 | $200.00 | $284.08 | |
| 20 | 60100915 | PIPE DRAINS 6 | 445 | FOOT | $80.00 | $65.00 | $23.11 | |
| 21 | 60100925 | PIPE DRAINS 8 | 368 | FOOT | $65.00 | $69.00 | $33.66 | |
| 22 | 60218300 | MAN TA 4 DIA T1F OL | 1 | EACH | $4,800.00 | $5,800.00 | $5,572.96 | |
| 23 | 60218400 | MAN TA 4 DIA T1F CL | 1 | EACH | $4,800.00 | $5,800.00 | $5,572.96 | |
| 24 | 60234200 | INLETS TA T1F OL | 2 | EACH | $2,800.00 | $2,800.00 | $1,527.84 | |
| 25 | 60240210 | INLETS TB T1F OL | 1 | EACH | $3,500.00 | $4,100.00 | $2,291.57 | |
| 26 | 60240215 | INLETS TB T1F CL | 2 | EACH | $3,500.00 | $4,000.00 | $2,291.57 | |
| 27 | 60500060 | REMOV INLETS | 3 | EACH | $750.00 | $1,190.00 | $477.00 | |
| 28 | 67000500 | ENGR FIELD OFFICE B | 6 | CAL MO | $3,000.00 | $3,800.00 | $2,157.10 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $65,000.00 | $63,850.00 | $38,319.00 | |
| 30 | 78001110 | PAINT PVT MK LINE 4 | 425 | FOOT | $7.00 | $7.00 | $7.58 | |
| 31 | 78001130 | PAINT PVT MK LINE 6 | 50 | FOOT | $10.50 | $10.50 | $11.37 |