(10-4-1HB-1)BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $894,984 | ||
| 2 | Big O Services, LLC | $967,203 | +8.1% | |
| 3 | Sangamo Construction Company | $1,052,219 | +17.6% | |
| 4 | William Charles Construction Company, LLC | $1,286,627 | +43.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 Big O Services,… | #3 Sangamo Constru… | #4 William Charles… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $10,000.00 | $12,000.00 | $56,029.82 | $26,951.00 | |
| 2 | Z0001899 | JACK & REM EX BEARING | 8 | EACH | $3,500.00 | $5,500.00 | $7,030.40 | $7,500.00 | |
| 3 | Z0001903 | STRUCT STEEL REMOV | 2,330 | POUND | $4.00 | $3.50 | $4.33 | $4.80 | |
| 4 | Z0001905 | STRUCT STEEL REPAIR | 3,130 | POUND | $29.50 | $35.00 | $24.26 | $25.00 | |
| 5 | Z0012111 | BRD FLYASH/SLAG 2 1/2 | 716 | SQ YD | $130.00 | $158.00 | $193.04 | $190.00 | |
| 6 | Z0012130 | BR DECK SCAR 3/4 | 716 | SQ YD | $65.00 | $63.00 | $57.81 | $90.00 | |
| 7 | Z0012754 | STR REP CON DP = < 5 | 97 | SQ FT | $245.00 | $400.00 | $415.47 | $405.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,500.00 | $8,000.00 | $10,373.03 | $15,000.00 | |
| 9 | Z0016002 | DECK SLAB REP (FD-T2) | 57 | SQ YD | $1,375.00 | $950.00 | $2,294.55 | $2,250.00 | |
| 10 | Z0041895 | POLYMER CONCRETE | 4 | CU FT | $1,795.00 | $1,300.00 | $1,292.01 | $1,600.00 | |
| 11 | 40600290 | BIT MATLS TACK CT | 95 | POUND | $9.50 | $13.00 | $9.55 | $26.00 | |
| 12 | 40600982 | HMA SURF REM BUTT JT | 210 | SQ YD | $32.00 | $38.00 | $15.64 | $68.50 | |
| 13 | 40604050 | HMA SC IL-9.5 C N50 | 21 | TON | $935.00 | $1,110.00 | $954.99 | $1,435.00 | |
| 14 | 50102400 | CONC REM | 24.9 | CU YD | $3,875.00 | $4,300.00 | $4,547.58 | $3,800.00 | |
| 15 | 50157300 | PROTECTIVE SHIELD | 251 | SQ YD | $100.00 | $120.00 | $1.00 | $138.00 | |
| 16 | 50300100 | FLOOR DRAINS | 8 | EACH | $725.00 | $1,100.00 | $616.67 | $1,542.11 | |
| 17 | 50300225 | CONC STRUCT | 15.2 | CU YD | $4,750.00 | $6,200.00 | $5,107.03 | $5,000.00 | |
| 18 | 50300255 | CONC SUP-STR | 13.3 | CU YD | $4,275.00 | $2,200.00 | $3,850.04 | $5,200.00 | |
| 19 | 50300260 | BR DECK GROOVING | 691 | SQ YD | $9.25 | $10.00 | $12.38 | $13.00 | |
| 20 | 50300300 | PROTECTIVE COAT | 762.4 | SQ YD | $4.00 | $5.00 | $3.69 | $8.00 | |
| 21 | 50500405 | F & E STRUCT STEEL | 3,810 | POUND | $7.50 | $7.50 | $10.38 | $15.00 | |
| 22 | 50800205 | REINF BARS, EPOXY CTD | 4,470 | POUND | $4.50 | $4.00 | $3.76 | $5.00 | |
| 23 | 52000110 | PREF JT STRIP SEAL | 62 | FOOT | $285.00 | $260.00 | $278.08 | $350.00 | |
| 24 | 52100010 | ELAST BEARING ASSY T1 | 8 | EACH | $1,850.00 | $1,800.00 | $1,954.33 | $2,500.00 | |
| 25 | 52100520 | ANCHOR BOLTS 1 | 16 | EACH | $180.00 | $200.00 | $181.70 | $300.00 | |
| 26 | 67000500 | ENGR FIELD OFFICE B | 5 | CAL MO | $1,500.00 | $2,800.00 | $2,920.48 | $3,200.00 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $53,500.00 | $39,000.00 | $62,080.92 | $75,000.00 | |
| 28 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $21,725.00 | $46,000.00 | $1.00 | $100,000.00 | |
| 29 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $105.00 | $125.00 | $106.11 | $100.00 | |
| 30 | 70400100 | TEMP CONC BARRIER | 620 | FOOT | $47.00 | $35.00 | $43.48 | $70.00 | |
| 31 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $5,450.00 | $6,000.00 | $3,033.61 | $4,400.00 |