35RS-5;36RS-4;139RS-7
- Let date
- Friday, April 25, 2025
- Contract
- 68J21 · job page
- District
- District 4
- County
- Warren
- Highway
- Limits
- PPP designed overlay on US 67 from north of 40th Ave and south end of BUS 67; SMART overlay on Roseville Bypass and north end of BUS 67, including IL 116 from 0.2 mile west to 0.2 mile east of US 67 west of Roseville. Approximately 6.65 miles gross length.
- Classification
- ·
- Project number
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gunther Construction, a div of UCM, Inc. Low bidder | $12,640,388 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gunther Constru… |
|---|---|---|---|---|---|---|
| 1 | XZ013798 | CONSTR STA LAYOUT | 1 | L SUM | $8,950.39 | |
| 2 | X4400196 | HMA SURF REM SPL | 8,624 | SQ YD | $21.74 | |
| 3 | X4401198 | HMA SURF REM VAR DP | 267 | SQ YD | $39.21 | |
| 4 | X4402805 | ISLAND REMOVAL | 1,366 | SQ FT | $17.18 | |
| 5 | X4421000 | PARTIAL DEPTH PATCH | 281 | TON | $367.76 | |
| 6 | X4421002 | PART DEPTH PATCH SPL | 1,251 | SQ YD | $57.41 | |
| 7 | X6061055 | CONCRETE ISLAND SPL | 1,366 | SQ FT | $45.21 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $42,365.60 | |
| 9 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | |
| 10 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | |
| 11 | 25000750 | MOWING | 102 | ACRE | $110.00 | |
| 12 | 40600295 | P BIT MATLS TACK CT | 169,665 | POUND | $2.98 | |
| 13 | 40600405 | MATL TRANSFER DEVICE | 39,638 | TON | $4.60 | |
| 14 | 40600982 | HMA SURF REM BUTT JT | 721 | SQ YD | $46.18 | |
| 15 | 40600990 | TEMPORARY RAMP | 552 | SQ YD | $19.07 | |
| 16 | 40603200 | P HMA BC IL-4.75 N50 | 2,062 | TON | $197.17 | |
| 17 | 40604150 | P HMA SC IL-9.5 C N50 | 15,097 | TON | $194.14 | |
| 18 | 40604152 | P HMA SC IL-9.5 C N70 | 20,178 | TON | $170.40 | |
| 19 | 40800050 | INCIDENTAL HMA SURF | 73 | TON | $466.33 | |
| 20 | 44000155 | HMA SURF REM 1 1/2 | 19,636 | SQ YD | $4.32 | |
| 21 | 44000157 | HMA SURF REM 2 | 283,625 | SQ YD | $5.25 | |
| 22 | 44000159 | HMA SURF REM 2 1/2 | 8,235 | SQ YD | $11.21 | |
| 23 | 44000163 | HMA SURF REM 3 1/2 | 8,745 | SQ YD | $11.80 | |
| 24 | 44003510 | MEDIAN REMOVAL (PD) | 721 | SQ FT | $25.84 | |
| 25 | 48102100 | AGG WEDGE SHLD TYPE B | 519 | TON | $142.07 | |
| 26 | 48203100 | HMA SHOULDERS | 2,231 | TON | $211.55 | |
| 27 | 64200108 | SHOULDER RUM STRIP 8 | 502 | FOOT | $20.01 | |
| 28 | 64200116 | SHOULDER RUM STRIP 16 | 133,861 | FOOT | $0.3200 | |
| 29 | 66700205 | PERM SURV MKRS T1 | 9 | EACH | $1,256.67 | |
| 30 | 67100100 | MOBILIZATION | 1 | L SUM | $635,969.33 | |
| 31 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $34,511.36 | |
| 32 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $67,797.20 | |
| 33 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $141,486.68 | |
| 34 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $137.50 | |
| 35 | 70300100 | SHORT TERM PAVT MKING | 2,653 | FOOT | $5.26 | |
| 36 | 70300150 | SHRT TRM PAVT MK REM | 898 | SQ FT | $15.20 | |
| 37 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 1,016 | SQ FT | $1.38 | |
| 38 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 8,326 | FOOT | $0.2200 | |
| 39 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 146,349 | FOOT | $0.3300 | |
| 40 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 11,090 | FOOT | $0.4400 | |
| 41 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 804 | FOOT | $1.10 | |
| 42 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 280 | FOOT | $4.40 | |
| 43 | 72000100 | SIGN PANEL T1 | 18.75 | SQ FT | $110.00 | |
| 44 | 72400600 | RELOC SIN PAN ASSY TB | 1 | EACH | $1,650.00 | |
| 45 | 78004600 | PREF PL PM TD STD LTR/SYM | 1,016 | SQ FT | $43.78 | |
| 46 | 78004620 | PREF PL PM TD STD L4 | 8,326 | FOOT | $4.03 | |
| 47 | 78004630 | PREF PL PM TD STD L 6 | 146,332 | FOOT | $5.47 | |
| 48 | 78004640 | PREF PL PM TD STD L 8 | 11,090 | FOOT | $8.67 | |
| 49 | 78004660 | PREF PL PM TD STD L12 | 804 | FOOT | $14.47 | |
| 50 | 78004720 | PREF PL PM TD STD L24 | 280 | FOOT | $25.07 | |
| 51 | 78011000 | GRV RCSD PM LTR & SYM | 1,425 | SQ FT | $7.96 | |
| 52 | 78011025 | GRV RCSD PVT MRKG 5 | 8,326 | FOOT | $0.5900 | |
| 53 | 78011035 | GRV RCSD PVT MRKG 7 | 146,332 | FOOT | $0.6900 | |
| 54 | 78011045 | GRV RCSD PVT MRKG 9 | 11,090 | FOOT | $1.18 | |
| 55 | 78011065 | GRV RCSD PVT MRKG 13 | 804 | FOOT | $3.99 | |
| 56 | 78011125 | GRV RCSD PVT MRKG 25 | 280 | FOOT | $6.88 | |
| 57 | 78100100 | RAISED REFL PAVT MKR | 720 | EACH | $41.04 | |
| 58 | 78100200 | TEMP RAIS REF PVT MKR | 720 | EACH | $25.30 | |
| 59 | 78300200 | RAISED REF PVT MK REM | 720 | EACH | $19.80 |