D4 CRACK & JOINT SEALING 2025
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Denler, Inc. Low bidder | $858,085 | ||
| 2 | SKC Construction, Inc. | $996,662 | +16.1% | |
| 3 | Complete Asphalt Service Co. | $1,053,665 | +22.8% | |
| 4 | ROADSAFE TRAFFIC SYSTEMS, INC. | $1,400,000 | +63.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Denler, Inc. | #2 SKC Constructio… | #3 Complete Asphal… | #4 ROADSAFE TRAFFI… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X4510100 | CRACK ROUTING/FILLING | 181,096 | POUND | $1.27 | $2.28 | $2.42 | $2.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $45,000.00 | $100,000.00 | $37,400.00 | $200,000.00 | |
| 3 | X7800800 | HS THPL PM LTR & SYM | 509.6 | SQ FT | $10.00 | $6.69 | $7.15 | $12.00 | |
| 4 | X7800815 | HS THPL PM LN 4 | 292,077 | FOOT | $0.3000 | $0.3600 | $0.3900 | $0.6000 | |
| 5 | X7800835 | HS THPL PM LN 6 | 84,411 | FOOT | $0.4600 | $0.6100 | $0.6600 | $1.00 | |
| 6 | X7800845 | HS THPL PM LN 8 | 28,733 | FOOT | $0.6100 | $0.9700 | $1.05 | $3.00 | |
| 7 | X7800855 | HS THPL PM LN 12 | 1,525 | FOOT | $4.95 | $3.03 | $3.25 | $6.00 | |
| 8 | X7800870 | HS THPL PM LN 24 | 598 | FOOT | $10.00 | $6.43 | $6.88 | $12.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $45,000.00 | $35,000.00 | $63,000.00 | $76,553.60 | |
| 10 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $35,000.00 | $8,000.00 | $37,400.00 | $25,000.00 | |
| 11 | 70107025 | CHANGEABLE MESSAGE SN | 124 | CAL DA | $100.00 | $155.00 | $165.00 | $250.00 | |
| 12 | 78009004 | MOD URETH PM LINE 4 | 226,684 | FOOT | $0.8800 | $0.6600 | $0.7200 | $0.7500 | |
| 13 | 78009006 | MOD URETH PM LINE 6 | 94,656 | FOOT | $1.32 | $0.7700 | $0.8300 | $1.50 | |
| 14 | 78009008 | MOD URETH PM LINE 8 | 2,080 | FOOT | $1.76 | $1.28 | $1.38 | $12.00 |