119B(BR)BJR,P
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $371,800 | ||
| 2 | Stark Excavating, Inc. | $416,545 | +12.0% | |
| 3 | Path Construction Company, Inc. | $461,023 | +24.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Stark Excavatin… | #3 Path Constructi… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326394 | FLOOR DRAINS CLEANED | 134 | EACH | $42.93 | $130.00 | $100.00 | |
| 2 | Z0016200 | DECK SLAB REP (PART) | 53 | SQ YD | $689.96 | $678.00 | $575.00 | |
| 3 | 20200500 | EARTH EXC WID | 111 | CU YD | $69.00 | $146.00 | $100.00 | |
| 4 | 40600290 | BIT MATLS TACK CT | 999 | POUND | $1.33 | $1.25 | $0.0100 | |
| 5 | 44000100 | PAVEMENT REM | 207 | SQ YD | $69.11 | $40.00 | $62.00 | |
| 6 | 48203029 | HMA SHOULDERS 8 | 722 | SQ YD | $112.00 | $77.00 | $123.00 | |
| 7 | 50102400 | CONC REM | 8.6 | CU YD | $4,207.29 | $5,500.00 | $3,200.00 | |
| 8 | 50300255 | CONC SUP-STR | 8.6 | CU YD | $4,100.00 | $5,500.00 | $3,200.00 | |
| 9 | 50300300 | PROTECTIVE COAT | 26 | SQ YD | $77.78 | $20.00 | $42.00 | |
| 10 | 50800205 | REINF BARS, EPOXY CTD | 1,200 | POUND | $4.24 | $5.00 | $4.00 | |
| 11 | 50800515 | BAR SPLICERS | 12 | EACH | $360.51 | $103.00 | $145.00 | |
| 12 | 52000110 | PREF JT STRIP SEAL | 90 | FOOT | $216.89 | $255.00 | $315.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $22,266.70 | $24,000.00 | $24,000.00 | |
| 14 | 70100405 | TRAF CONT-PROT 701321 | 1 | EACH | $16,000.00 | $20,100.00 | $91,000.00 | |
| 15 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $3,800.00 | $1,655.00 | $1,000.00 | |
| 16 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $21,056.81 | $25,000.00 | $34,000.00 | |
| 17 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $531.74 | $1,500.00 | $800.00 | |
| 18 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $79.76 | $125.00 | $80.00 | |
| 19 | 70400100 | TEMP CONC BARRIER | 762.5 | FOOT | $23.53 | $41.00 | $45.00 | |
| 20 | 70400200 | REL TEMP CONC BARRIER | 762.5 | FOOT | $8.54 | $9.00 | $5.50 | |
| 21 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $2,250.00 | $5,000.00 | $4,200.00 | |
| 22 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $366.73 | $650.00 | $600.00 | |
| 23 | 78001110 | PAINT PVT MK LINE 4 | 6,096 | FOOT | $2.65 | $2.50 | $0.6000 | |
| 24 | 78300202 | PAVMT MRKG REM WTR BL | 2,032 | SQ FT | $4.20 | $4.25 | $2.25 |