D4 ITS REPLACE 2021
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | H & H Electric Co. Low bidder | $258,043 | ||
| 2 | Laser Electric, Inc. | $266,950 | +3.5% | |
| 3 | Capitol Construction Group, LLC d/b/a Egizii Electric | $277,459 | +7.5% | |
| 4 | Oberlander Electric Co. | $300,028 | +16.3% | |
| 5 | Gerstner Electric, Inc. | $346,185 | +34.2% | |
| 6 | Bodine Electric of Decatur | $367,512 | +42.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 H & H Electric … | #2 Laser Electric,… | #3 Capitol Constru… | #4 Oberlander Elec… | #5 Gerstner Electr… | #6 Bodine Electric… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326812 | CAT 5 ETHERNET CABLE | 180 | FOOT | $1.50 | $2.05 | $2.00 | $2.10 | $3.50 | $4.79 | |
| 2 | X1400179 | CCTV DOME CAMERA HD | 87 | EACH | $2,842.60 | $2,768.63 | $3,114.13 | $3,095.00 | $3,765.00 | $4,024.35 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $1,646.10 | $12,032.32 | $4,600.00 | $18,885.00 | $3,000.00 | $2,510.56 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $8,820.50 | $13,677.40 | $1,569.60 | $11,500.00 | $15,000.00 | $14,020.57 |