(90-14;106;107;108;109;110)CJS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Complete Asphalt Service Co. Low bidder | $197,480 | ||
| 2 | Denler, Inc. | $226,950 | +14.9% | |
| 3 | Kinney Contractors, Inc. | $358,400 | +81.5% | |
| 4 | SKC Construction, Inc. | $419,950 | +112.7% | |
| 5 | Fahrner Asphalt Sealers, LLC | $611,450 | +209.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Complete Asphal… | #2 Denler, Inc. | #3 Kinney Contract… | #4 SKC Constructio… | #5 Fahrner Asphalt… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4510100 | CRACK ROUTING/FILLING | 145,000 | POUND | $1.28 | $1.19 | $1.90 | $1.97 | $3.87 | |
| 2 | 67100100 | MOBILIZATION | 1 | L SUM | $11,500.00 | $12,000.00 | $64,000.00 | $18,000.00 | $37,000.00 | |
| 3 | 70100420 | TRAF CONT-PROT 701411 | 28 | EACH | $10.00 | $300.00 | $300.00 | $225.00 | $300.00 | |
| 4 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $100.00 | $34,000.00 | $10,500.00 | $110,000.00 | $4,900.00 |