(104VB-BR)BRR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $138,518 | ||
| 2 | Halverson Construction Co., Inc. | $156,850 | +13.2% | |
| 3 | Stark Excavating, Inc. | $201,300 | +45.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Halverson Const… | #3 Stark Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0012754 | STR REP CON DP = < 5 | 407 | SQ FT | $188.00 | $291.00 | $300.00 | |
| 2 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $13,000.00 | $20,000.00 | $8,100.00 | |
| 3 | Z0073200 | TEMP SHORING & CRIB | 6 | EACH | $7,500.00 | $1,500.00 | $8,000.00 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $4,000.00 | $9,411.00 | $20,400.00 | |
| 5 | 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $1.00 | $1.00 | $200.00 | |
| 6 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $2,500.00 |