(94-16HB)BR
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | White Construction LLC Low bidder | $5,194,500 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 White Construct… |
|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 1,772 | SQ FT | $2.25 | |
| 2 | X1700035 | CLASS SI CONC | 2 | CU YD | $1,325.00 | |
| 3 | X4404400 | PAVT REMOVAL SPL | 472 | SQ YD | $75.00 | |
| 4 | X6050065 | REMOV INLETS SPL | 2 | EACH | $760.00 | |
| 5 | X7011801 | TRAF CONT-PROT BLR 22 | 1 | L SUM | $3,650.00 | |
| 6 | X7830070 | GRV RCSD PVT MRKG 5 | 4,800 | FOOT | $1.10 | |
| 7 | X7830074 | GRV RCSD PVT MRKG 7 | 600 | FOOT | $8.80 | |
| 8 | Z0001002 | GDRL AGG EROS CONT | 370 | TON | $70.00 | |
| 9 | Z0004552 | APPROACH SLAB REM | 534 | SQ YD | $65.00 | |
| 10 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $24,366.44 | |
| 11 | Z0034105 | MATL TRANSFER DEVICE | 489 | TON | $12.10 | |
| 12 | Z0041500 | PLUG EX CULVERTS | 4 | EACH | $445.00 | |
| 13 | Z0046304 | P UNDR FOR STRUCT 4 | 390 | FOOT | $35.00 | |
| 14 | Z0073400 | TEMP SUPPORT SYSTEM | 4 | EACH | $10,500.00 | |
| 15 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | |
| 17 | 21101615 | TOPSOIL F & P 4 | 1,250 | SQ YD | $8.50 | |
| 18 | 25000210 | SEEDING CL 2A | 0.26 | ACRE | $7,605.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 23.4 | POUND | $2.00 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 23.4 | POUND | $2.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 23.4 | POUND | $2.00 | |
| 22 | 25000750 | MOWING | 1 | ACRE | $1,300.00 | |
| 23 | 25100635 | HD EROS CONTR BLANKET | 1,250 | SQ YD | $1.60 | |
| 24 | 28000250 | TEMP EROS CONTR SEED | 23.4 | POUND | $3.75 | |
| 25 | 28000400 | PERIMETER EROS BAR | 450 | FOOT | $7.00 | |
| 26 | 35300300 | PCC BSE CSE 8 | 2,572 | SQ YD | $80.00 | |
| 27 | 40200100 | AGG SURF CSE A | 85 | TON | $110.00 | |
| 28 | 40600295 | P BIT MATLS TACK CT | 11,523 | POUND | $3.47 | |
| 29 | 40600985 | PCC SURF REM BUTT JT | 800 | SQ YD | $63.24 | |
| 30 | 40600990 | TEMPORARY RAMP | 267 | SQ YD | $55.00 | |
| 31 | 40603208 | P HMA BC IL-9.5 N70 | 517 | TON | $244.83 | |
| 32 | 40604162 | P HMA SC IL-9.5 D N70 | 489 | TON | $259.59 | |
| 33 | 42000080 | PVT CON PCC BR APP SL | 12 | SQ YD | $350.00 | |
| 34 | 44000182 | HMA SURF REM 8 | 2,572 | SQ YD | $8.00 | |
| 35 | 44213204 | TIE BARS 3/4 | 485 | EACH | $33.00 | |
| 36 | 48101200 | AGGREGATE SHLDS B | 73 | TON | $60.00 | |
| 37 | 48203012 | HMA SHOULDERS 3 3/4 | 3,325 | SQ YD | $61.83 | |
| 38 | 50100100 | REM EXIST STRUCT | 2 | EACH | $200,000.00 | |
| 39 | 50200100 | STRUCTURE EXCAVATION | 1,887 | CU YD | $50.00 | |
| 40 | 50300225 | CONC STRUCT | 725.7 | CU YD | $900.00 | |
| 41 | 50300255 | CONC SUP-STR | 473.9 | CU YD | $1,100.00 | |
| 42 | 50300260 | BR DECK GROOVING | 1,698 | SQ YD | $7.50 | |
| 43 | 50300300 | PROTECTIVE COAT | 2,200 | SQ YD | $1.50 | |
| 44 | 50301350 | CONC SUPSTR APP SLAB | 241.3 | CU YD | $425.00 | |
| 45 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $450,000.00 | |
| 46 | 50500505 | STUD SHEAR CONNECTORS | 7,992 | EACH | $3.85 | |
| 47 | 50800205 | REINF BARS, EPOXY CTD | 302,200 | POUND | $1.40 | |
| 48 | 50800515 | BAR SPLICERS | 1,857 | EACH | $45.00 | |
| 49 | 51100100 | SLOPE WALL 4 | 2,007 | SQ YD | $125.00 | |
| 50 | 51201500 | FUR STL PILE HP10X57 | 691 | FOOT | $90.00 | |
| 51 | 51202305 | DRIVING PILES | 691 | FOOT | $0.0100 | |
| 52 | 51203500 | TEST PILE ST HP10X57 | 2 | EACH | $7,000.00 | |
| 53 | 51500100 | NAME PLATES | 2 | EACH | $760.00 | |
| 54 | 52100010 | ELAST BEARING ASSY T1 | 24 | EACH | $1,375.00 | |
| 55 | 52100520 | ANCHOR BOLTS 1 | 96 | EACH | $115.00 | |
| 56 | 52200010 | TEMP SHT PILING | 803 | SQ FT | $45.00 | |
| 57 | 52200020 | TEMP SOIL RETEN SYSTM | 7,231 | SQ FT | $47.50 | |
| 58 | 58600101 | GRANULAR BACKFILL STR | 308 | CU YD | $77.00 | |
| 59 | 58700300 | CONCRETE SEALER | 1,402 | SQ FT | $2.60 | |
| 60 | 59100100 | GEOCOMPOSITE WALL DR | 177 | SQ YD | $40.00 | |
| 61 | 60600605 | CONC CURB TB | 60 | FOOT | $55.00 | |
| 62 | 63000001 | SPBGR TY A 6FT POSTS | 550 | FOOT | $29.00 | |
| 63 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $3,100.00 | |
| 64 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $2,950.00 | |
| 65 | 63200310 | GUARDRAIL REMOV | 1,192 | FOOT | $5.00 | |
| 66 | 64200116 | SHOULDER RUM STRIP 16 | 3,741 | FOOT | $1.60 | |
| 67 | 67000400 | ENGR FIELD OFFICE A | 14 | CAL MO | $1,925.00 | |
| 68 | 67100100 | MOBILIZATION | 1 | L SUM | $311,669.98 | |
| 69 | 70100207 | TRAF CONT-PROT 701402 | 2 | EACH | $24,000.00 | |
| 70 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $22,000.00 | |
| 71 | 70300100 | SHORT TERM PAVT MKING | 800 | FOOT | $3.00 | |
| 72 | 70300150 | SHRT TRM PAVT MK REM | 240 | SQ FT | $5.40 | |
| 73 | 70300220 | TEMP PVT MK LINE 4 | 15,149 | FOOT | $1.10 | |
| 74 | 70400100 | TEMP CONC BARRIER | 915 | FOOT | $50.00 | |
| 75 | 70400200 | REL TEMP CONC BARRIER | 810 | FOOT | $6.50 | |
| 76 | 70600251 | IMP ATTN TEMP NRN TL3 | 2 | EACH | $5,500.00 | |
| 77 | 70600352 | IMP ATTN REL NRN TL3 | 2 | EACH | $1,000.00 | |
| 78 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | |
| 79 | 78009004 | MOD URETH PM LINE 4 | 4,800 | FOOT | $1.25 | |
| 80 | 78009006 | MOD URETH PM LINE 6 | 600 | FOOT | $10.00 | |
| 81 | 78100100 | RAISED REFL PAVT MKR | 30 | EACH | $180.00 | |
| 82 | 78200005 | GRDRAIL REF TYPE A | 14 | EACH | $8.00 | |
| 83 | 78300200 | RAISED REF PVT MK REM | 30 | EACH | $40.00 |