72[6RS;(6-1)RS-1]
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $10,996,119 | ||
| 2 | R. A. Cullinan and Son, a div of UCM, Inc. | $11,150,809 | +1.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 R. A. Cullinan … |
|---|---|---|---|---|---|---|---|
| 1 | XZ013798 | CONSTR STA LAYOUT | 1 | L SUM | $15,000.00 | $6,388.85 | |
| 2 | X2600002 | RECOVERABLE DELINEATR | 233 | EACH | $65.00 | $155.00 | |
| 3 | X4400196 | HMA SURF REM SPL | 7,411 | SQ YD | $16.50 | $33.99 | |
| 4 | X4420559 | CL A PATCH T4 10 SPL | 1,026.5 | SQ YD | $255.00 | $255.00 | |
| 5 | X6350204 | LINEAR DELIN PANELS 4 | 156 | EACH | $40.00 | $40.00 | |
| 6 | X6370101 | CONC BAR WALL R&R L1 | 1 | L SUM | $17,250.00 | $14,718.20 | |
| 7 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $77,000.00 | $104,868.60 | |
| 8 | Z0001002 | GDRL AGG EROS CONT | 2,418 | TON | $115.00 | $110.34 | |
| 9 | Z0018700 | DRAINAGE STR REMOVED | 14 | EACH | $2,300.00 | $1,914.62 | |
| 10 | Z0020805 | EROSION CONT CURB REM | 7,168.7 | FOOT | $10.00 | $5.01 | |
| 11 | Z0076600 | TRAINEES | 5,000 | HOUR | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 5,000 | HOUR | $15.00 | $15.00 | |
| 13 | 20200500 | EARTH EXC WID | 55.4 | CU YD | $125.00 | $104.74 | |
| 14 | 25000750 | MOWING | 40 | ACRE | $120.00 | $120.00 | |
| 15 | 31100100 | SUB GRAN MAT A | 95.2 | TON | $87.50 | $110.38 | |
| 16 | 35501301 | HMA BASE CSE 4 1/4 | 54,954 | SQ YD | $29.50 | $28.61 | |
| 17 | 35501324 | HMA BASE CSE 10 | 952.1 | SQ YD | $70.00 | $104.90 | |
| 18 | 40600295 | P BIT MATLS TACK CT | 208,905 | POUND | $0.9000 | $1.08 | |
| 19 | 40600405 | MATL TRANSFER DEVICE | 31,292 | TON | $4.65 | $3.07 | |
| 20 | 40600982 | HMA SURF REM BUTT JT | 1,158.1 | SQ YD | $33.50 | $15.37 | |
| 21 | 40600985 | PCC SURF REM BUTT JT | 875 | SQ YD | $41.50 | $22.37 | |
| 22 | 40600990 | TEMPORARY RAMP | 1,344.4 | SQ YD | $15.00 | $5.85 | |
| 23 | 40603208 | P HMA BC IL-9.5 N70 | 8,927 | TON | $130.00 | $138.35 | |
| 24 | 40604010 | HMA SC IL-9.5FG D N50 | 6,594 | TON | $120.00 | $160.22 | |
| 25 | 40605034 | P SC SMA 12.5 E N80 | 10,202 | TON | $155.00 | $183.33 | |
| 26 | 40800050 | INCIDENTAL HMA SURF | 142.4 | TON | $250.00 | $285.00 | |
| 27 | 44000152 | HMA SURF REM 3/4 | 1,577 | SQ YD | $5.00 | $8.48 | |
| 28 | 44000164 | HMA SURF REM 3 3/4 | 3,518.3 | SQ YD | $6.10 | $7.88 | |
| 29 | 44000166 | HMA SURF REM 4 1/4 | 52,685 | SQ YD | $7.45 | $5.83 | |
| 30 | 44004250 | PAVED SHLD REMOVAL | 785.5 | SQ YD | $22.00 | $21.62 | |
| 31 | 44200553 | CL A PATCH T2 10 | 88 | SQ YD | $300.00 | $300.00 | |
| 32 | 44200557 | CL A PATCH T3 10 | 80 | SQ YD | $300.00 | $300.00 | |
| 33 | 44200559 | CL A PATCH T4 10 | 3,096.9 | SQ YD | $250.00 | $250.00 | |
| 34 | 44200583 | CL A PATCH T4 12 | 186.67 | SQ YD | $260.00 | $260.00 | |
| 35 | 44213000 | PATCH REINFORCEMENT | 4,478.1 | SQ YD | $95.00 | $95.00 | |
| 36 | 44213200 | SAW CUTS | 5,735.6 | FOOT | $2.00 | $2.00 | |
| 37 | 44213204 | TIE BARS 3/4 | 1,638 | EACH | $5.00 | $5.00 | |
| 38 | 48101200 | AGGREGATE SHLDS B | 1,706 | TON | $37.75 | $66.44 | |
| 39 | 48203100 | HMA SHOULDERS | 5,769 | TON | $120.00 | $141.17 | |
| 40 | 50300225 | CONC STRUCT | 14 | CU YD | $1,196.85 | $1,875.00 | |
| 41 | 50800205 | REINF BARS, EPOXY CTD | 1,110 | POUND | $4.72 | $6.50 | |
| 42 | 63000001 | SPBGR TY A 6FT POSTS | 11,925 | FOOT | $33.00 | $33.00 | |
| 43 | 63000030 | SPGR ATT TO CULVERT | 68.75 | FOOT | $275.00 | $275.00 | |
| 44 | 63100045 | TRAF BAR TERM T2 | 13 | EACH | $2,200.00 | $2,200.00 | |
| 45 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $4,425.00 | $4,425.00 | |
| 46 | 63100167 | TR BAR TRM T1 SPL TAN | 13 | EACH | $3,700.00 | $3,700.00 | |
| 47 | 63200310 | GUARDRAIL REMOV | 12,360 | FOOT | $6.25 | $6.25 | |
| 48 | 64200108 | SHOULDER RUM STRIP 8 | 51,331 | FOOT | $0.3500 | $0.2500 | |
| 49 | 64300260 | IMP ATTEN FRD NAR TL3 | 1 | EACH | $23,975.00 | $23,975.00 | |
| 50 | 67100100 | MOBILIZATION | 1 | L SUM | $625,000.00 | $32,350.00 | |
| 51 | 70107025 | CHANGEABLE MESSAGE SN | 720 | CAL DA | $25.00 | $75.00 | |
| 52 | 70300100 | SHORT TERM PAVT MKING | 5,415 | FOOT | $2.00 | $2.37 | |
| 53 | 70300150 | SHRT TRM PAVT MK REM | 1,805 | SQ FT | $2.50 | $9.18 | |
| 54 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 73,845 | FOOT | $0.0100 | $0.2500 | |
| 55 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 549.24 | FOOT | $0.0100 | $0.3500 | |
| 56 | 72501000 | TERMINAL MARKER - DA | 28 | EACH | $42.00 | $42.00 | |
| 57 | 78004630 | PREF PL PM TD STD L 6 | 73,845 | FOOT | $5.80 | $4.55 | |
| 58 | 78004640 | PREF PL PM TD STD L 8 | 549.24 | FOOT | $12.50 | $19.00 | |
| 59 | 78011035 | GRV RCSD PVT MRKG 7 | 73,845 | FOOT | $0.6000 | $0.4500 | |
| 60 | 78011045 | GRV RCSD PVT MRKG 9 | 549.24 | FOOT | $1.00 | $0.6500 | |
| 61 | 78100100 | RAISED REFL PAVT MKR | 323 | EACH | $53.00 | $47.00 | |
| 62 | 78300200 | RAISED REF PVT MK REM | 323 | EACH | $14.00 | $31.53 |