(14R-17R)PP
- Let date
- Friday, June 13, 2025
- Contract
- 66R52 · job page
- District
- District 3
- County
- Iroquois
- Highway
- Limits
- Class B pavement patching and other related construction work on Il Route 1 at the intersection of IL Route 1 and US Route 24 near Watseka and ending at the Vermilion County Line.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $680,867 | ||
| 2 | Kinney Contractors, Inc. | $871,775 | +28.0% | |
| 3 | Beniach Construction Co., Inc. | $901,947 | +32.5% | |
| 4 | SNC Construction, Inc. | $1,106,847 | +62.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… | #3 Beniach Constru… | #4 SNC Constructio… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7200061 | TEMP INFO SIGNING | 42 | SQ FT | $0.0100 | $25.00 | $68.00 | $56.01 | |
| 2 | Z0017099 | DOWEL BAR ASSEMBLY | 2 | EACH | $300.00 | $300.00 | $675.00 | $1,920.19 | |
| 3 | 44200050 | WELDED WIRE REINF | 140 | SQ YD | $5.00 | $17.00 | $15.00 | $24.59 | |
| 4 | 44201053 | CL B PATCH T4 17 | 1,429 | SQ YD | $405.00 | $345.00 | $511.00 | $544.09 | |
| 5 | 44201055 | CL B PATCH T2 17 | 93 | SQ YD | $405.00 | $350.00 | $617.00 | $474.33 | |
| 6 | 44201057 | CL B PATCH T3 17 | 47 | SQ YD | $405.00 | $347.00 | $581.00 | $627.79 | |
| 7 | 44201298 | DOWEL BARS 1 1/4 | 3,660 | EACH | $0.0100 | $24.00 | $14.00 | $23.72 | |
| 8 | 44213200 | SAW CUTS | 8,522 | FOOT | $0.0100 | $3.00 | $0.0100 | $5.01 | |
| 9 | 44213204 | TIE BARS 3/4 | 19 | EACH | $0.0100 | $25.00 | $11.00 | $103.87 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $33,000.00 | $50,000.00 | $25,000.00 | $69,404.41 | |
| 11 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $11,000.00 | $162,000.00 | $4,200.00 | $45,200.23 |