(46-3)I-3
- Let date
- Friday, June 12, 2020
- Contract
- 66K44 · job page
- District
- District 3
- County
- Kankakee
- Highway
- Limits
- This contract is for 2 permanent crossovers in Kankakee. The North crossover is located approximately 1500' N of SN 046-0010/11 over Grinnell Rd, the South crossover is located 2300' S of SN 046-0008/0009 over railroad tracks.
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kankakee Valley Construction Company, Inc. Low bidder | $1,630,706 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kankakee Valley… |
|---|---|---|---|---|---|---|
| 1 | X0326208 | ALTERNATE RTE SIGNING | 1 | L SUM | $6,850.00 | |
| 2 | X0326677 | REM HT CBL MEDIAN BAR | 1,801 | FOOT | $7.55 | |
| 3 | X0326687 | REM HTC MED BAR TERM | 1 | EACH | $2,000.00 | |
| 4 | X0326880 | MESSAGE BOARD VEH DRV | 250 | HOUR | $103.00 | |
| 5 | X0326907 | PORT VHMNT CH MSS SGN | 2 | CAL MO | $3,200.00 | |
| 6 | X0327980 | PAVMT MRKG REM WTR BL | 7,467 | SQ FT | $1.25 | |
| 7 | X0328003 | REAL-TIME TR CTRL SYS | 50 | WEEK | $610.25 | |
| 8 | X0328004 | REAL-TIME TR CTRL SU | 150 | WEEK | $316.25 | |
| 9 | X5420615 | PIPE CULV CLEANED 15 | 74 | FOOT | $75.00 | |
| 10 | X5420618 | PIPE CULV CLEANED 18 | 117 | FOOT | $75.00 | |
| 11 | X7010239 | CHANGEABLE MSG SN SPL | 100 | CAL WK | $172.50 | |
| 12 | X7010805 | TR C-PROT 701401 SPL | 1 | L SUM | $95,000.00 | |
| 13 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $15,000.00 | |
| 14 | Z0040530 | PIPE UNDERDRAIN REMOV | 3,430 | FOOT | $2.50 | |
| 15 | Z0065773 | SLTD DR 21 W/VAR SLOT | 195 | FOOT | $525.00 | |
| 16 | Z0065775 | SLOT DR 24" W/VAR SL | 195 | FOOT | $515.00 | |
| 17 | 20100110 | TREE REMOV 6-15 | 3,347 | UNIT | $7.50 | |
| 18 | 20100210 | TREE REMOV OVER 15 | 859 | UNIT | $9.00 | |
| 19 | 20200100 | EARTH EXCAVATION | 1,220 | CU YD | $48.00 | |
| 20 | 20400800 | FURNISHED EXCAVATION | 340 | CU YD | $51.00 | |
| 21 | 21001000 | GEOTECH FAB F/GR STAB | 4,723 | SQ YD | $1.20 | |
| 22 | 21400100 | GRADING & SHAP DITCH | 284 | FOOT | $30.00 | |
| 23 | 25000210 | SEEDING CL 2A | 7.25 | ACRE | $1,425.00 | |
| 24 | 25000400 | NITROGEN FERT NUTR | 653 | POUND | $1.00 | |
| 25 | 25000500 | PHOSPHORUS FERT NUTR | 653 | POUND | $1.00 | |
| 26 | 25000600 | POTASSIUM FERT NUTR | 653 | POUND | $1.00 | |
| 27 | 25100125 | MULCH METHOD 3 | 7.25 | ACRE | $1,425.00 | |
| 28 | 25100630 | EROSION CONTR BLANKET | 3,216 | SQ YD | $1.20 | |
| 29 | 28000250 | TEMP EROS CONTR SEED | 790 | POUND | $4.00 | |
| 30 | 28000305 | TEMP DITCH CHECKS | 384 | FOOT | $10.00 | |
| 31 | 28000400 | PERIMETER EROS BAR | 4,450 | FOOT | $3.00 | |
| 32 | 31100910 | SUB GRAN MAT A 12 | 4,723 | SQ YD | $21.00 | |
| 33 | 42000521 | PCC PVT 11 JOINTED | 4,587 | SQ YD | $94.00 | |
| 34 | 42001300 | PROTECTIVE COAT | 4,884 | SQ YD | $1.30 | |
| 35 | 44004250 | PAVED SHLD REMOVAL | 1,684 | SQ YD | $31.00 | |
| 36 | 44213204 | TIE BARS 3/4 | 1,598 | EACH | $30.00 | |
| 37 | 48101500 | AGGREGATE SHLDS B 6 | 546 | SQ YD | $18.00 | |
| 38 | 542D0226 | P CUL CL D 1 21 | 361 | FOOT | $60.00 | |
| 39 | 542D0229 | P CUL CL D 1 24 | 440 | FOOT | $70.00 | |
| 40 | 54260521 | SLOP MET ES 21", 1:6 | 2 | EACH | $1,750.00 | |
| 41 | 54260524 | SLOP MET ES 24", 1:6 | 2 | EACH | $2,750.00 | |
| 42 | 60100060 | CONC HDWL FOR P DRAIN | 8 | EACH | $921.80 | |
| 43 | 60108100 | PIPE UNDERDRAIN 4 SP | 96 | FOOT | $63.00 | |
| 44 | 60108501 | PIPE UNDERDR T 3 | 3,385 | FOOT | $8.20 | |
| 45 | 60616800 | PAVED DITCH TB-15 | 445 | FOOT | $137.00 | |
| 46 | 63500105 | DELINEATORS | 8 | EACH | $50.00 | |
| 47 | 64401300 | HT CBL MED BAR TERM | 3 | EACH | $3,841.50 | |
| 48 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,200.00 | |
| 49 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $1,850.00 | |
| 50 | 66901006 | REG SUB MON | 3 | CAL DA | $1,000.00 | |
| 51 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,000.00 | |
| 52 | 67100100 | MOBILIZATION | 1 | L SUM | $83,000.00 | |
| 53 | 70100420 | TRAF CONT-PROT 701411 | 2 | EACH | $2,000.00 | |
| 54 | 70107025 | CHANGEABLE MESSAGE SN | 300 | CAL DA | $35.00 | |
| 55 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $0.0100 | |
| 56 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $4,250.00 | |
| 57 | 72501000 | TERMINAL MARKER - DA | 3 | EACH | $50.00 | |
| 58 | 78009004 | MOD URETH PM LINE 4 | 16,290 | FOOT | $0.5500 | |
| 59 | 78009006 | MOD URETH PM LINE 6 | 4,073 | FOOT | $0.8200 | |
| 60 | 78100100 | RAISED REFL PAVT MKR | 408 | EACH | $1.00 | |
| 61 | 78300200 | RAISED REF PVT MK REM | 408 | EACH | $0.0100 |