CJS,MICROSURF JT REPAIR 2019-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | SKC Construction, Inc. Low bidder | $298,715 | ||
| 2 | Freehill Asphalt, Inc. | $412,189 | +38.0% | |
| 3 | Complete Asphalt Service Co. | $416,538 | +39.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 SKC Constructio… | #2 Freehill Asphal… | #3 Complete Asphal… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 1,956 | SQ FT | $2.25 | $3.00 | $2.10 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 210 | SQ FT | $25.00 | $20.00 | $30.00 | |
| 3 | 40400001 | FIBR MOD ASP CRK SEAL | 15,565 | FOOT | $1.12 | $0.6000 | $1.21 | |
| 4 | 40400121 | MICRO-SURF SNGL MD | 3,459 | SQ YD | $8.90 | $10.76 | $15.59 | |
| 5 | 40600290 | BIT MATLS TACK CT | 779 | POUND | $0.0100 | $0.0100 | $0.0200 | |
| 6 | 40600400 | MIX CR JTS FLANGEWYS | 1 | TON | $350.00 | $0.0100 | $1,000.00 | |
| 7 | 45100100 | CRACK ROUTING (PAVT) | 271,590 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 8 | 45100200 | CRACK FILLING | 95,087 | POUND | $1.67 | $2.73 | $2.58 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $12,000.00 | $21,840.00 | $24,500.00 | |
| 10 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $100.00 | $6,000.00 | $100.00 | |
| 11 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $32,000.00 | $15,200.00 | $100.00 | |
| 12 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $100.00 | $100.00 | $100.00 | |
| 13 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $100.00 | $100.00 | $100.00 | |
| 14 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $100.00 | $6,000.00 | $100.00 | |
| 15 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $100.00 | $100.00 | $100.00 | |
| 16 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $100.00 | $100.00 | |
| 17 | 70107025 | CHANGEABLE MESSAGE SN | 60 | CAL DA | $65.00 | $40.00 | $80.00 | |
| 18 | 70300100 | SHORT TERM PAVT MKING | 3,129 | FOOT | $0.7200 | $1.25 | $2.72 | |
| 19 | 70300150 | SHRT TRM PAVT MK REM | 1,043 | SQ FT | $2.75 | $5.22 | $8.15 | |
| 20 | 78001110 | PAINT PVT MK LINE 4 | 84,357 | FOOT | $0.1100 | $0.1000 | $0.1100 | |
| 21 | 78001130 | PAINT PVT MK LINE 6 | 19,171 | FOOT | $0.1600 | $0.1500 | $0.1600 | |
| 22 | 78001140 | PAINT PVT MK LINE 8 | 4,841 | FOOT | $0.2100 | $0.2000 | $0.2100 | |
| 23 | 78100100 | RAISED REFL PAVT MKR | 195 | EACH | $41.50 | $41.50 | $43.58 | |
| 24 | 78300200 | RAISED REF PVT MK REM | 195 | EACH | $20.00 | $59.92 | $79.19 |