((06-6,7)(6&50)-8)SFY,CBL
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | COLLINS & HERMANN, INC. Low bidder | $763,936 | ||
| 2 | Access Control Company, Inc. | $802,984 | +5.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 COLLINS & HERMA… | #2 Access Control … |
|---|---|---|---|---|---|---|---|
| 1 | X0325231 | CABLE GUARD MARKER | 771 | EACH | $3.80 | $4.00 | |
| 2 | X0325667 | WD CTRL MWNG STRP SP | 20,486 | SQ YD | $16.25 | $15.00 | |
| 3 | X0326880 | MESSAGE BOARD VEH DRV | 240 | HOUR | $50.78 | $1.00 | |
| 4 | X0326907 | PORT VHMNT CH MSS SGN | 2 | CAL MO | $3,164.06 | $100.00 | |
| 5 | X7010600 | TC-PROT 701406 SPL | 1 | L SUM | $48,560.89 | $82,000.00 | |
| 6 | X7015005 | CHANGEABLE MESSAGE SN | 75 | CAL DA | $63.28 | $1.00 | |
| 7 | 64401100 | HT CBL MEDIAN BARRIER | 30,730 | FOOT | $9.85 | $11.50 | |
| 8 | 64401300 | HT CBL MED BAR TERM | 10 | EACH | $2,926.13 | $4,000.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $19,035.00 | $14,000.00 | |
| 10 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $3,607.03 | $2,200.00 | |
| 11 | 72501100 | TERMINAL MARKER - PM | 10 | EACH | $169.28 | $50.00 |