Bid tab 66H70

Let Apr 27, 2018 · District 3 · Bureau Sign up free

‹ Apr 2018 results

(06-2,06-3)SFY,CBL

Let date
Friday, April 27, 2018
Contract
66H70 · job page
District
District 3
County
Bureau
Highway
Limits
Intall 6.1 miles of high tensin cable median barrier on I-80 from 0.42 mile west of 600 E Street to the 1200 E Street overpass.

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Access Control Company, Inc. Low bidder $700,595
2 Lovewell Fencing, Inc. $744,292 +6.2%
3 COLLINS & HERMANN, INC. $817,046 +16.6%

Bid tab: unit prices 9 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Access Control …#2 Lovewell Fencin…#3 COLLINS & HERMA…
1X0325231 CABLE GUARD MARKER806EACH $3.00 $3.00 $3.80
2X0325667 WD CTRL MWNG STRP SP21,437SQ YD $14.20 $15.00 $15.23
3X7015005 CHANGEABLE MESSAGE SN180CAL DA $1.00 $30.00 $63.28
464401100 HT CBL MEDIAN BARRIER32,155FOOT $9.75 $9.80 $10.72
564401300 HT CBL MED BAR TERM10EACH $3,650.00 $4,000.00 $3,678.32
667100100 MOBILIZATION1L SUM $14,000.00 $29,800.00 $19,103.97
770100800 TRAF CONT-PROT 7014011L SUM $27,000.00 $26,000.00 $71,816.22
870100825 TRAF CONT-PROT 7014561L SUM $1,580.00 $1,500.00 $2,009.18
972501100 TERMINAL MARKER - PM10EACH $100.00 $250.00 $169.28