(06-2,06-3)SFY,CBL
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Access Control Company, Inc. Low bidder | $700,595 | ||
| 2 | Lovewell Fencing, Inc. | $744,292 | +6.2% | |
| 3 | COLLINS & HERMANN, INC. | $817,046 | +16.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Access Control … | #2 Lovewell Fencin… | #3 COLLINS & HERMA… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0325231 | CABLE GUARD MARKER | 806 | EACH | $3.00 | $3.00 | $3.80 | |
| 2 | X0325667 | WD CTRL MWNG STRP SP | 21,437 | SQ YD | $14.20 | $15.00 | $15.23 | |
| 3 | X7015005 | CHANGEABLE MESSAGE SN | 180 | CAL DA | $1.00 | $30.00 | $63.28 | |
| 4 | 64401100 | HT CBL MEDIAN BARRIER | 32,155 | FOOT | $9.75 | $9.80 | $10.72 | |
| 5 | 64401300 | HT CBL MED BAR TERM | 10 | EACH | $3,650.00 | $4,000.00 | $3,678.32 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $14,000.00 | $29,800.00 | $19,103.97 | |
| 7 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $27,000.00 | $26,000.00 | $71,816.22 | |
| 8 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $1,580.00 | $1,500.00 | $2,009.18 | |
| 9 | 72501100 | TERMINAL MARKER - PM | 10 | EACH | $100.00 | $250.00 | $169.28 |