(121,122)RS-3
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $4,931,854 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… |
|---|---|---|---|---|---|---|
| 1 | X0100025 | FLOWABLE FILL | 1 | CU YD | $2,500.00 | |
| 2 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $10,000.00 | |
| 3 | X0326649 | LINEAR DELIN PANELS 6 | 8 | EACH | $64.00 | |
| 4 | X0327809 | LINEAR DELIN PANELS 4 | 43 | EACH | $58.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 7,485 | SQ YD | $6.75 | |
| 6 | X5010523 | REM CONC END SEC | 6 | EACH | $500.00 | |
| 7 | X5537800 | SS CLEANED 12 | 52 | FOOT | $20.00 | |
| 8 | Z0010615 | CLEAN EX INLETS | 2 | EACH | $350.00 | |
| 9 | Z0029300 | GROUT REPAIR | 5 | FOOT | $105.00 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $50.00 | |
| 11 | Z0034105 | MATL TRANSFER DEVICE | 24,997 | TON | $15.00 | |
| 12 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $0.0100 | |
| 13 | 20200100 | EARTH EXCAVATION | 5 | CU YD | $85.00 | |
| 14 | 20300100 | CHANNEL EXCAVATION | 105 | CU YD | $95.00 | |
| 15 | 20400800 | FURNISHED EXCAVATION | 125 | CU YD | $0.0100 | |
| 16 | 20800150 | TRENCH BACKFILL | 45 | CU YD | $75.00 | |
| 17 | 21400100 | GRADING & SHAP DITCH | 1,115 | FOOT | $18.00 | |
| 18 | 25000210 | SEEDING CL 2A | 0.75 | ACRE | $2,500.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 68 | POUND | $3.20 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 68 | POUND | $3.20 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 68 | POUND | $3.20 | |
| 22 | 25100630 | EROSION CONTR BLANKET | 3,332 | SQ YD | $2.50 | |
| 23 | 28100105 | STONE RIPRAP CL A3 | 172 | SQ YD | $135.00 | |
| 24 | 28100107 | STONE RIPRAP CL A4 | 4 | SQ YD | $330.00 | |
| 25 | 28200200 | FILTER FABRIC | 176 | SQ YD | $5.50 | |
| 26 | 40200800 | AGG SURF CSE B | 5 | TON | $85.00 | |
| 27 | 40600290 | BIT MATLS TACK CT | 83,513 | POUND | $1.00 | |
| 28 | 40600370 | LONG JOINT SEALANT | 50,383 | FOOT | $2.95 | |
| 29 | 40600400 | MIX CR JTS FLANGEWYS | 37.1 | TON | $0.0100 | |
| 30 | 40600900 | HMA BC HM N50 | 61.3 | TON | $0.0100 | |
| 31 | 40600982 | HMA SURF REM BUTT JT | 362 | SQ YD | $0.0100 | |
| 32 | 40600990 | TEMPORARY RAMP | 706 | SQ YD | $0.0100 | |
| 33 | 40603080 | HMA BC IL-19.0 N50 | 14,834 | TON | $94.00 | |
| 34 | 40604050 | HMA SC IL-9.5 C N50 | 10,163 | TON | $98.00 | |
| 35 | 40800050 | INCIDENTAL HMA SURF | 700 | TON | $235.00 | |
| 36 | 42000060 | WELDED WIRE REINF | 663 | SQ YD | $55.00 | |
| 37 | 42400100 | PC CONC SIDEWALK 4 | 512 | SQ FT | $22.00 | |
| 38 | 42400800 | DETECTABLE WARNINGS | 100 | SQ FT | $53.00 | |
| 39 | 44000100 | PAVEMENT REM | 55 | SQ YD | $125.00 | |
| 40 | 44000164 | HMA SURF REM 3 3/4 | 117,737 | SQ YD | $5.65 | |
| 41 | 44000600 | SIDEWALK REM | 299 | SQ FT | $16.00 | |
| 42 | 44200976 | CL B PATCH T4 10 | 627 | SQ YD | $325.00 | |
| 43 | 44200998 | CL B PATCH T3 12 | 69 | SQ YD | $385.00 | |
| 44 | 44201299 | DOWEL BARS 1 1/2 | 597 | EACH | $32.50 | |
| 45 | 44213200 | SAW CUTS | 985 | FOOT | $10.00 | |
| 46 | 44213204 | TIE BARS 3/4 | 597 | EACH | $22.50 | |
| 47 | 48102100 | AGG WEDGE SHLD TYPE B | 1,499 | TON | $37.00 | |
| 48 | 50105220 | PIPE CULVERT REMOV | 126 | FOOT | $75.00 | |
| 49 | 542A5473 | P CUL CL A 1 EQRS 18 | 160 | FOOT | $135.00 | |
| 50 | 54213663 | PRC FLAR END SEC 18 | 8 | EACH | $1,450.00 | |
| 51 | 54390160 | INSERT CUL LIN 21 | 42 | FOOT | $550.00 | |
| 52 | 60605000 | COMB CC&G TB6.24 | 238 | FOOT | $100.00 | |
| 53 | 60905305 | BOX CUL TO BE CLEANED | 396 | FOOT | $105.00 | |
| 54 | 60920018 | PIPE CULV CLEANED 18 | 174 | FOOT | $100.00 | |
| 55 | 63500105 | DELINEATORS | 26 | EACH | $66.00 | |
| 56 | 66900200 | NON SPL WASTE DISPOSL | 300 | CU YD | $125.00 | |
| 57 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,750.00 | |
| 58 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,650.00 | |
| 59 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,500.00 | |
| 60 | 66901006 | REG SUB MON | 4 | CAL DA | $1,450.00 | |
| 61 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $2,000.00 | |
| 62 | 67100100 | MOBILIZATION | 1 | L SUM | $240,000.00 | |
| 63 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1.00 | |
| 64 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $35,000.00 | |
| 65 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | |
| 66 | 70300100 | SHORT TERM PAVT MKING | 4,032 | FOOT | $0.0100 | |
| 67 | 70300150 | SHRT TRM PAVT MK REM | 1,341 | SQ FT | $0.0100 | |
| 68 | 78000100 | THPL PVT MK LTR & SYM | 62 | SQ FT | $8.75 | |
| 69 | 78000200 | THPL PVT MK LINE 4 | 4,238 | FOOT | $1.50 | |
| 70 | 78000400 | THPL PVT MK LINE 6 | 40 | FOOT | $2.15 | |
| 71 | 78000500 | THPL PVT MK LINE 8 | 397 | FOOT | $2.85 | |
| 72 | 78000600 | THPL PVT MK LINE 12 | 538 | FOOT | $4.40 | |
| 73 | 78001110 | PAINT PVT MK LINE 4 | 182,662 | FOOT | $0.1500 | |
| 74 | 78001130 | PAINT PVT MK LINE 6 | 17,142 | FOOT | $0.2000 | |
| 75 | 78003181 | PREF PL PM TB STAN L24 | 80 | FOOT | $50.00 | |
| 76 | 78011000 | GRV RCSD PM LTR & SYM | 62 | SQ FT | $11.00 | |
| 77 | 78011025 | GRV RCSD PVT MRKG 5 | 4,238 | FOOT | $1.55 | |
| 78 | 78011035 | GRV RCSD PVT MRKG 7 | 40 | FOOT | $2.30 | |
| 79 | 78011045 | GRV RCSD PVT MRKG 9 | 397 | FOOT | $3.15 | |
| 80 | 78011065 | GRV RCSD PVT MRKG 13 | 538 | FOOT | $4.80 | |
| 81 | 78011125 | GRV RCSD PVT MRKG 25 | 80 | FOOT | $10.50 | |
| 82 | 78100100 | RAISED REFL PAVT MKR | 611 | EACH | $37.50 | |
| 83 | 78200020 | CURB REFLECTORS | 13 | EACH | $15.75 | |
| 84 | 78300200 | RAISED REF PVT MK REM | 611 | EACH | $0.0100 |