D2 CJS 2025-04
- Let date
- Friday, June 13, 2025
- Contract
- 64T33 · job page
- District
- District 2
- County
- Whiteside
- Highway
- Limits
- 2.85 miles of crack joint sealing on IL 84 from US 30 to south of 12th Ave in Albany and on US 30 from IandM Feeder Canal 0.3 miles east of ILL 40 in Rock Falls to Lee County Line.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Denler, Inc. Low bidder | $195,171 | ||
| 2 | Freehill Asphalt, Inc. | $265,323 | +35.9% | |
| 3 | Countryman, Inc. | $286,234 | +46.7% | |
| 4 | SKC Construction, Inc. | $312,593 | +60.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Denler, Inc. | #2 Freehill Asphal… | #3 Countryman, Inc. | #4 SKC Constructio… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $4,000.00 | $4,300.00 | $5,000.00 | $6,000.00 | |
| 2 | 45100100 | CRACK ROUTING (PAVT) | 207,576 | FOOT | $0.0100 | $0.0100 | $0.1500 | $0.0200 | |
| 3 | 45100200 | CRACK FILLING | 91,406 | POUND | $0.6500 | $1.32 | $1.51 | $2.12 | |
| 4 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $750.00 | $2,500.00 | $4,000.00 | $3,000.00 | |
| 5 | 67100100 | MOBILIZATION | 1 | L SUM | $15,000.00 | $15,000.00 | $5,000.00 | $20,000.00 | |
| 6 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $32,000.00 | $45,000.00 | $6,300.00 | $7,000.00 | |
| 7 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $100.00 | $100.00 | $6,300.00 | $1.00 | |
| 8 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $100.00 | $6,300.00 | $1.00 | |
| 9 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $150.00 | $125.00 | $600.00 | $110.00 | |
| 10 | 78001110 | PAINT PVT MK LINE 4 | 207,928 | FOOT | $0.2100 | $0.1900 | $0.1300 | $0.2000 | |
| 11 | 78009000 | MOD URETH PM LTR-SYM | 468 | SQ FT | $10.99 | $9.99 | $12.00 | $10.29 | |
| 12 | 78009004 | MOD URETH PM LINE 4 | 4,160 | FOOT | $1.82 | $1.65 | $2.00 | $1.70 | |
| 13 | 78009008 | MOD URETH PM LINE 8 | 3,103 | FOOT | $3.63 | $3.30 | $4.00 | $3.40 | |
| 14 | 78009012 | MOD URETH PM LINE 12 | 1,092 | FOOT | $5.48 | $4.98 | $6.00 | $5.13 | |
| 15 | 78009024 | MOD URETH PM LINE 24 | 287 | FOOT | $10.99 | $9.99 | $12.00 | $10.29 |