Bid tab 64T32

Let Jun 13, 2025 · District 2 · Henry

‹ Jun 2025 results

D2 CJS 2025-03

Let date
Friday, June 13, 2025
Contract
64T32 · job page
District
District 2
County
Henry
Highway
Limits
1.82 miles of crack joint sealing on IL 81 from Galva-Atkinson Rd to WestSt in Kewanee and from US 150 to 0.4 miles west of I-74.
Classification
·
Project number

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Denler, Inc. Low bidder $160,257
2 Complete Asphalt Service Co. $175,896 +9.8%
3 Countryman, Inc. $186,174 +16.2%
4 Freehill Asphalt, Inc. $210,461 +31.3%
5 SKC Construction, Inc. $226,366 +41.3%

Bid tab: unit prices 8 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Denler, Inc.#2 Complete Asphal…#3 Countryman, Inc.#4 Freehill Asphal…#5 SKC Constructio…
145100100 CRACK ROUTING (PAVT)146,620FOOT $0.0100 $0.0100 $0.1500 $0.0200 $0.0200
245100200 CRACK FILLING64,549POUND $0.6100 $1.25 $1.50 $1.25 $1.89
367100100 MOBILIZATION1L SUM $10,000.00 $10,000.00 $5,000.00 $10,750.00 $15,000.00
470100460 TRAF CONT-PROT 7013061L SUM $25,000.00 $10,000.00 $6,300.00 $40,000.00 $6,500.00
570102620 TR CONT & PROT 7015011L SUM $100.00 $1,000.00 $6,300.00 $100.00 $1.00
678001110 PAINT PVT MK LINE 4361,792FOOT $0.2000 $0.1400 $0.1200 $0.1800 $0.1900
778009006 MOD URETH PM LINE 682FOOT $10.89 $10.47 $3.00 $9.90 $10.20
878009024 MOD URETH PM LINE 24508FOOT $21.78 $41.80 $12.00 $19.80 $20.39