138RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $1,798,693 | ||
| 2 | Valley Construction Co. | $2,071,828 | +15.2% | |
| 3 | Brandt Construction Co. | $2,797,048 | +55.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 Valley Construc… | #3 Brandt Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7820007 | GRDRAIL REFL TY C SPL | 24 | EACH | $45.00 | $50.00 | $105.00 | |
| 2 | Z0028415 | GEOTECHNICAL REINF | 226 | SQ YD | $4.90 | $4.25 | $5.50 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 9,959 | TON | $2.65 | $0.0100 | $3.00 | |
| 4 | 30300001 | AGG SUBGRADE IMPROVE | 38 | CU YD | $50.00 | $257.00 | $215.00 | |
| 5 | 40600290 | BIT MATLS TACK CT | 31,045 | POUND | $0.8500 | $1.00 | $0.5000 | |
| 6 | 40600370 | LONG JOINT SEALANT | 17,639 | FOOT | $2.75 | $3.00 | $2.90 | |
| 7 | 40600990 | TEMPORARY RAMP | 397 | SQ YD | $15.00 | $21.00 | $45.00 | |
| 8 | 40601005 | HMA REPL OVER PATCH | 2,028 | TON | $90.00 | $163.00 | $175.00 | |
| 9 | 40603080 | HMA BC IL-19.0 N50 | 6,224 | TON | $90.00 | $96.00 | $110.00 | |
| 10 | 40604050 | HMA SC IL-9.5 C N50 | 3,809 | TON | $100.00 | $99.00 | $110.00 | |
| 11 | 40800050 | INCIDENTAL HMA SURF | 256 | TON | $160.00 | $325.00 | $265.00 | |
| 12 | 44000164 | HMA SURF REM 3 3/4 | 45,186 | SQ YD | $3.50 | $4.00 | $8.00 | |
| 13 | 44002232 | HMA RM OV PATCH 8 | 4,527 | SQ YD | $10.00 | $13.50 | $70.00 | |
| 14 | 44201737 | CL D PATCH T1 8 | 57 | SQ YD | $225.00 | $225.00 | $400.00 | |
| 15 | 44201741 | CL D PATCH T2 8 | 57 | SQ YD | $225.00 | $195.00 | $400.00 | |
| 16 | 44201745 | CL D PATCH T3 8 | 57 | SQ YD | $185.00 | $160.00 | $400.00 | |
| 17 | 44201747 | CL D PATCH T4 8 | 57 | SQ YD | $165.00 | $140.00 | $400.00 | |
| 18 | 48102100 | AGG WEDGE SHLD TYPE B | 1,638 | TON | $31.25 | $33.25 | $42.00 | |
| 19 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $2,000.00 | $2,500.00 | $3,500.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $100,000.00 | $115,000.00 | $165,000.00 | |
| 21 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1,000.00 | $1,000.00 | $1,120.00 | |
| 22 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $25,000.00 | $8,400.00 | $9,400.00 | |
| 23 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1,000.00 | $1,000.00 | $1,120.00 | |
| 24 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $50.00 | $50.00 | $55.00 | |
| 25 | 70300100 | SHORT TERM PAVT MKING | 7,434 | FOOT | $0.8500 | $1.43 | $2.40 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 2,478 | SQ FT | $1.00 | $1.85 | $5.25 | |
| 27 | 72000100 | SIGN PANEL T1 | 175 | SQ FT | $26.00 | $32.00 | $29.00 | |
| 28 | 72000200 | SIGN PANEL T2 | 58 | SQ FT | $35.00 | $37.00 | $39.00 | |
| 29 | 72400310 | REMOV SIGN PANEL T1 | 111 | SQ FT | $10.00 | $12.00 | $11.00 | |
| 30 | 72400320 | REMOV SIGN PANEL T2 | 68 | SQ FT | $12.00 | $14.00 | $13.50 | |
| 31 | 72400710 | RELOC SIGN PANEL T1 | 22 | SQ FT | $15.00 | $75.00 | $16.00 | |
| 32 | 72400720 | RELOC SIGN PANEL T2 | 11 | SQ FT | $20.00 | $85.00 | $22.00 | |
| 33 | 72800100 | TELES STL SIN SUPPORT | 219 | FOOT | $18.00 | $30.00 | $20.00 | |
| 34 | 73000100 | WOOD SIN SUPPORT | 165 | FOOT | $30.00 | $35.00 | $35.00 | |
| 35 | 78000200 | THPL PVT MK LINE 4 | 52,308 | FOOT | $0.7100 | $0.8000 | $0.7700 | |
| 36 | 78011025 | GRV RCSD PVT MRKG 5 | 52,308 | FOOT | $0.3500 | $0.4000 | $0.3900 | |
| 37 | 78100100 | RAISED REFL PAVT MKR | 2 | EACH | $1,994.00 | $1,000.00 | $900.00 | |
| 38 | 78300200 | RAISED REF PVT MK REM | 2 | EACH | $18.10 | $18.50 | $110.00 |