25SLP
- Let date
- Friday, June 14, 2024
- Contract
- 64R35 · job page
- District
- District 2
- County
- Jo Daviess
- Highway
- Limits
- Culvert end section and erosion repair 0.4 mile east of Galena Ridge Dr. on US 20.
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Fischer Excavating, Inc. Low bidder | $286,287 | ||
| 2 | Law Excavating, Inc. | $381,383 | +33.2% | |
| 3 | Phoenix Corporation of the Quad Cities | $417,881 | +46.0% | |
| 4 | Miller Trucking & Excavating Company | $474,640 | +65.8% | |
| 5 | Louie's Trenching Service, Inc. | $504,495 | +76.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Fischer Excavat… | #2 Law Excavating,… | #3 Phoenix Corpora… | #4 Miller Trucking… | #5 Louie's Trenchi… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0328017 | STRM MIT BANK CRED | 615.5 | EACH | $80.00 | $10.00 | $80.00 | $90.00 | $90.00 | |
| 2 | X2810110 | STONE RIPRAP CL A5 SP | 56 | SQ YD | $100.00 | $150.00 | $116.00 | $160.00 | $250.00 | |
| 3 | X5427602 | REMOV EX FLAR END SEC | 1 | EACH | $500.00 | $500.00 | $1,150.00 | $2,500.00 | $500.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,600.00 | $5,000.00 | $13,000.00 | $7,500.00 | $7,000.00 | |
| 5 | 20100110 | TREE REMOV 6-15 | 387 | UNIT | $33.00 | $36.00 | $58.50 | $40.00 | $50.00 | |
| 6 | 20100210 | TREE REMOV OVER 15 | 307 | UNIT | $55.00 | $36.00 | $73.50 | $55.00 | $60.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 2,485 | CU YD | $20.00 | $19.00 | $27.00 | $35.00 | $35.00 | |
| 8 | 20800150 | TRENCH BACKFILL | 147 | CU YD | $34.00 | $40.00 | $80.00 | $40.00 | $85.00 | |
| 9 | 21101615 | TOPSOIL F & P 4 | 2,420 | SQ YD | $3.65 | $4.00 | $4.50 | $15.00 | $18.00 | |
| 10 | 25000310 | SEEDING CL 4 | 0.5 | ACRE | $6,000.00 | $10,000.00 | $4,200.00 | $7,500.00 | $20,000.00 | |
| 11 | 25100630 | EROSION CONTR BLANKET | 2,420 | SQ YD | $2.50 | $3.20 | $3.75 | $4.00 | $5.00 | |
| 12 | 28000250 | TEMP EROS CONTR SEED | 150 | POUND | $0.0100 | $2.00 | $2.00 | $1.00 | $15.00 | |
| 13 | 28000305 | TEMP DITCH CHECKS | 40 | FOOT | $15.00 | $25.00 | $41.00 | $10.00 | $30.00 | |
| 14 | 28000400 | PERIMETER EROS BAR | 20 | FOOT | $5.00 | $20.00 | $11.00 | $10.00 | $20.00 | |
| 15 | 28100109 | STONE RIPRAP CL A5 | 355 | SQ YD | $80.00 | $75.00 | $125.00 | $105.00 | $125.00 | |
| 16 | 28200200 | FILTER FABRIC | 355 | SQ YD | $4.00 | $3.00 | $4.00 | $4.00 | $5.00 | |
| 17 | 50105220 | PIPE CULVERT REMOV | 20 | FOOT | $32.00 | $15.00 | $60.00 | $250.00 | $50.00 | |
| 18 | 52200020 | TEMP SOIL RETEN SYSTM | 815 | SQ FT | $0.0100 | $1.00 | $50.00 | $60.00 | $110.00 | |
| 19 | 542A2755 | P CUL CL A 4 30 | 72 | FOOT | $200.00 | $110.00 | $303.00 | $420.00 | $175.00 | |
| 20 | 54261430 | CONC ES 542001 30 1:4 | 1 | EACH | $7,500.00 | $6,500.00 | $11,100.00 | $7,500.00 | $12,000.00 | |
| 21 | 60221100 | MAN TA 5 DIA T1F CL | 1 | EACH | $42,500.00 | $30,000.00 | $15,000.00 | $30,000.00 | $15,000.00 | |
| 22 | 60500040 | REMOV MANHOLES | 1 | EACH | $1,100.00 | $1,000.00 | $3,500.00 | $6,000.00 | $4,000.00 | |
| 23 | 66600105 | FUR ERECT ROW MARKERS | 7 | EACH | $500.00 | $200.00 | $400.00 | $750.00 | $600.00 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $17,000.00 | $165,000.00 | $47,750.00 | $45,000.00 | $33,000.00 | |
| 25 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2,940.00 | $18,500.00 | $10,000.00 | $8,000.00 | $3,250.00 |