(9-15D)RS-2
- Let date
- Friday, April 29, 2022
- Contract
- 64N37 · job page
- District
- District 2
- County
- Rock Island
- Highway
- Limits
- 1.54 miles cold milling and HMA resurfacing and ADA on IL 192 from 0.3 miles West of 140th St W in Edgington to 123rd St W.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Brandt Construction Co. Low bidder | $1,308,309 | ||
| 2 | Valley Construction Co. | $1,349,429 | +3.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Brandt Construc… | #2 Valley Construc… |
|---|---|---|---|---|---|---|---|
| 1 | X0324380 | REMOVE & REPLACE LID | 10 | EACH | $8,000.00 | $3,000.00 | |
| 2 | X4201650 | PAVEMENT FABRIC SPL | 1,196 | SQ YD | $10.00 | $24.75 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,500.00 | $5,800.00 | |
| 4 | Z0028415 | GEOTECHNICAL REINF | 46 | SQ YD | $23.00 | $5.25 | |
| 5 | Z0034105 | MATL TRANSFER DEVICE | 2,907 | TON | $8.00 | $0.0100 | |
| 6 | 20200100 | EARTH EXCAVATION | 15 | CU YD | $50.00 | $150.00 | |
| 7 | 21101615 | TOPSOIL F & P 4 | 40 | SQ YD | $25.00 | $15.75 | |
| 8 | 25200110 | SODDING SALT TOLERANT | 40 | SQ YD | $90.00 | $50.00 | |
| 9 | 25200200 | SUPPLE WATERING | 1 | UNIT | $2,250.00 | $1,000.00 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 3 | POUND | $25.00 | $5.25 | |
| 11 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $225.00 | $275.00 | |
| 12 | 30300001 | AGG SUBGRADE IMPROVE | 8 | CU YD | $330.00 | $52.50 | |
| 13 | 35101400 | AGG BASE CSE B | 10 | TON | $85.00 | $290.00 | |
| 14 | 40600290 | BIT MATLS TACK CT | 17,897 | POUND | $1.00 | $1.00 | |
| 15 | 40600370 | LONG JOINT SEALANT | 39,772 | FOOT | $2.50 | $2.00 | |
| 16 | 40600990 | TEMPORARY RAMP | 654 | SQ YD | $40.00 | $20.00 | |
| 17 | 40602965 | HMA BC IL-9.5FG N50 | 1,306 | TON | $110.00 | $125.00 | |
| 18 | 40604050 | HMA SC IL-9.5 C N50 | 2,907 | TON | $105.00 | $135.00 | |
| 19 | 40800050 | INCIDENTAL HMA SURF | 710 | TON | $185.00 | $235.00 | |
| 20 | 42400200 | PC CONC SIDEWALK 5 | 647 | SQ FT | $18.00 | $23.00 | |
| 21 | 42400800 | DETECTABLE WARNINGS | 20 | SQ FT | $35.00 | $125.00 | |
| 22 | 44000100 | PAVEMENT REM | 38 | SQ YD | $125.00 | $61.00 | |
| 23 | 44000155 | HMA SURF REM 1 1/2 | 15,543 | SQ YD | $3.35 | $3.50 | |
| 24 | 44000157 | HMA SURF REM 2 | 10,834 | SQ YD | $4.35 | $5.00 | |
| 25 | 44000158 | HMA SURF REM 2 1/4 | 3,919 | SQ YD | $5.35 | $6.30 | |
| 26 | 44000500 | COMB CURB GUTTER REM | 76 | FOOT | $75.00 | $14.80 | |
| 27 | 44000600 | SIDEWALK REM | 353 | SQ FT | $8.00 | $6.55 | |
| 28 | 44201445 | CL C PATCH T2 18 | 7 | SQ YD | $750.00 | $415.00 | |
| 29 | 44201447 | CL C PATCH T3 18 | 98 | SQ YD | $450.00 | $390.00 | |
| 30 | 44201449 | CL C PATCH T4 18 | 126 | SQ YD | $450.00 | $385.00 | |
| 31 | 48102100 | AGG WEDGE SHLD TYPE B | 452 | TON | $35.50 | $48.00 | |
| 32 | 56109210 | WATER VALVES ADJUST | 2 | EACH | $1,000.00 | $500.00 | |
| 33 | 60255500 | MAN ADJUST | 2 | EACH | $1,500.00 | $2,300.00 | |
| 34 | 60605000 | COMB CC&G TB6.24 | 75 | FOOT | $110.00 | $37.50 | |
| 35 | 66900200 | NON SPL WASTE DISPOSL | 6 | CU YD | $800.00 | $250.00 | |
| 36 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,550.00 | $4,200.00 | |
| 37 | 66901006 | REG SUB MON | 2 | CAL DA | $1,700.00 | $895.00 | |
| 38 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,000.00 | $2,780.00 | |
| 39 | 67100100 | MOBILIZATION | 1 | L SUM | $75,000.00 | $69,101.03 | |
| 40 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $550.00 | $4,750.00 | |
| 41 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $550.00 | $525.00 | |
| 42 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $550.00 | $525.00 | |
| 43 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $4,200.00 | $4,000.00 | |
| 44 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $100.00 | |
| 45 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $550.00 | $525.00 | |
| 46 | 70103815 | TR CONT SURVEILLANCE | 5 | CAL DA | $1,350.00 | $100.00 | |
| 47 | 70300100 | SHORT TERM PAVT MKING | 5,936 | FOOT | $1.35 | $0.5500 | |
| 48 | 70300150 | SHRT TRM PAVT MK REM | 459 | SQ FT | $2.10 | $2.00 | |
| 49 | 78000100 | THPL PVT MK LTR & SYM | 94 | SQ FT | $5.50 | $7.35 | |
| 50 | 78000200 | THPL PVT MK LINE 4 | 19,657 | FOOT | $0.9000 | $0.8500 | |
| 51 | 78000400 | THPL PVT MK LINE 6 | 149 | FOOT | $1.35 | $1.70 | |
| 52 | 78000500 | THPL PVT MK LINE 8 | 344 | FOOT | $1.80 | $1.70 | |
| 53 | 78000600 | THPL PVT MK LINE 12 | 611 | FOOT | $2.70 | $2.65 | |
| 54 | 78000650 | THPL PVT MK LINE 24 | 180 | FOOT | $5.50 | $7.35 | |
| 55 | 78011000 | GRV RCSD PM LTR & SYM | 305 | SQ FT | $4.70 | $6.30 | |
| 56 | 78011025 | GRV RCSD PVT MRKG 5 | 19,657 | FOOT | $0.7800 | $0.7500 | |
| 57 | 78011035 | GRV RCSD PVT MRKG 7 | 149 | FOOT | $1.20 | $1.30 | |
| 58 | 78011045 | GRV RCSD PVT MRKG 9 | 344 | FOOT | $1.60 | $1.75 | |
| 59 | 78011065 | GRV RCSD PVT MRKG 13 | 611 | FOOT | $2.35 | $3.15 | |
| 60 | 78011125 | GRV RCSD PVT MRKG 25 | 180 | FOOT | $4.50 | $7.35 | |
| 61 | 78100100 | RAISED REFL PAVT MKR | 19 | EACH | $145.00 | $375.00 | |
| 62 | 78300200 | RAISED REF PVT MK REM | 75 | EACH | $55.00 | $50.00 | |
| 63 | 78300202 | PAVMT MRKG REM WTR BL | 392 | SQ FT | $10.50 | $10.00 |