D2 DMS 2019-1
- Let date
- Friday, June 14, 2019
- Contract
- 64K76 · job page
- District
- District 2
- County
- Henry, Rock Island
- Highway
- Limits
- Remove and replace 3 overhead dynamic message signs, structure components, and supports at various locations.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | John Burns Construction Company Low bidder | $1,090,515 | ||
| 2 | Western Remac, Inc. | $1,136,243 | +4.2% | |
| 3 | General Constructors Inc. of the Quad Cities | $1,157,609 | +6.2% | |
| 4 | COLLINS & HERMANN, INC. | $1,318,198 | +20.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 John Burns Cons… | #2 Western Remac, … | #3 General Constru… | #4 COLLINS & HERMA… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0325482 | REM EXIST ITS EQUIPMT | 3 | EACH | $6,975.00 | $1,682.00 | $2,400.00 | $9,092.94 | |
| 2 | X0325485 | TR MTD LED DYN MSG SN | 3 | EACH | $116,600.00 | $80,032.00 | $70,000.00 | $83,787.44 | |
| 3 | X0326263 | EQUIPMENT CABINET | 3 | EACH | $11,900.00 | $11,024.00 | $8,500.00 | $9,541.44 | |
| 4 | 48100300 | AGGREGATE SHLDS A 4 | 94 | SQ YD | $44.00 | $60.90 | $45.00 | $62.74 | |
| 5 | 63000001 | SPBGR TY A 6FT POSTS | 625 | FOOT | $25.00 | $30.00 | $25.00 | $27.50 | |
| 6 | 63000007 | SPBGR TY B 6FT POSTS | 250 | FOOT | $35.00 | $51.10 | $33.00 | $43.81 | |
| 7 | 63000017 | SPBGR TY D 6FT POSTS | 50 | FOOT | $40.00 | $69.00 | $60.00 | $51.78 | |
| 8 | 63100045 | TRAF BAR TERM T2 | 2 | EACH | $1,800.00 | $2,204.00 | $1,500.00 | $1,582.28 | |
| 9 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,100.00 | $4,000.00 | $3,200.00 | $3,544.57 | |
| 10 | 63200310 | GUARDRAIL REMOV | 646 | FOOT | $8.00 | $6.00 | $5.00 | $7.56 | |
| 11 | 63301990 | REM RE-E T B TERM T1 | 3 | EACH | $1,300.00 | $4,228.00 | $2,900.00 | $1,375.10 | |
| 12 | 63302000 | REM RE-E T B TERM T2 | 3 | EACH | $2,200.00 | $1,984.00 | $1,200.00 | $731.53 | |
| 13 | 64300260 | IMP ATTEN FRD NAR TL3 | 2 | EACH | $18,000.00 | $27,840.00 | $22,000.00 | $49,820.70 | |
| 14 | 64301090 | ATTENUATOR BASE | 2 | SQ YD | $3,800.00 | $2,500.00 | $850.00 | $6,273.75 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $64,500.00 | $70,515.40 | $100,000.00 | $59,413.91 | |
| 16 | 70100205 | TRAF CONT-PROT 701401 | 3 | EACH | $250.00 | $9,750.00 | $8,100.00 | $18,104.25 | |
| 17 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $35,000.00 | $78,664.00 | $41,400.00 | $18,104.25 | |
| 18 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $750.00 | $6,600.00 | $5,000.00 | $104.56 | |
| 19 | 72501000 | TERMINAL MARKER - DA | 2 | EACH | $25.00 | $100.00 | $40.00 | $25.31 | |
| 20 | 73300300 | OVHD SIN STR-SPAN T3A | 300 | FOOT | $749.20 | $838.00 | $1,250.00 | $923.55 | |
| 21 | 73301810 | OSS WALKWAY TY A | 60 | FOOT | $275.00 | $324.00 | $1,000.00 | $363.07 | |
| 22 | 73400200 | DRILL SHAFT CONC FDN | 87.2 | CU YD | $1,630.00 | $2,051.30 | $1,225.00 | $3,606.06 | |
| 23 | 73600100 | REMOV OH SIN STR-SPAN | 3 | EACH | $6,800.00 | $3,647.00 | $22,500.00 | $11,056.50 | |
| 24 | 73700300 | REM CONC FDN-OVHD | 6 | EACH | $2,850.00 | $5,409.00 | $1,600.00 | $3,052.69 | |
| 25 | 78200005 | GRDRAIL REF TYPE A | 16 | EACH | $12.00 | $11.50 | $10.00 | $10.63 | |
| 26 | 80500100 | SERV INSTALL TY A | 3 | EACH | $7,475.00 | $7,500.00 | $2,100.00 | $3,928.41 | |
| 27 | 81028350 | UNDRGRD C PVC 2 | 183 | FOOT | $53.00 | $16.00 | $12.00 | $78.42 | |
| 28 | 81702500 | EC C XLP USE 4C 6 | 473 | FOOT | $18.00 | $10.00 | $8.00 | $7.32 | |
| 29 | 87800200 | CONC FDN TY D | 9 | FOOT | $1,615.00 | $900.00 | $750.00 | $784.22 | |
| 30 | 89500120 | REM EX SERV INSTALL | 3 | EACH | $2,400.00 | $1,650.00 | $1,428.00 | $2,354.75 |