$8.62Avg low bid / SQ YD
$10.58Avg of all bids
—Avg engineer's estimate
9Jobs · 12,606 SQ YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 2 | 335 | $32.85 | $40.96 |
| 2023 | 2 | 596 | $38.96 | $51.46 |
| 2022 | 1 | 4,102 | $8.50 | $13.00 |
| 2021 | 1 | 6,500 | $4.00 | $7.39 |
| 2020 | 2 | 979 | $9.65 | $12.33 |
| 2019 | 1 | 94 | $44.00 | $53.16 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 2, 2024 | 62K73 | CookDistrict 1 | 314 SQ YD | $33.00 | Lorig Construction Company |
| Jun 14, 2024 | 76P46 | MadisonDistrict 8 | 21 SQ YD | $30.60 | Keeley & Sons, Inc. |
| Jun 16, 2023 | 95893 | MaconDistrict 7 | 489 SQ YD | $35.45 | William Charles Construction Company, LLC and White Construction, LLC JV |
| Jan 20, 2023 | 62K74 | CookDistrict 1 | 107 SQ YD | $55.00 | Dunnet Bay Construction Company & Martam Construction JV |
| Nov 18, 2022 | 76K25 | RandolphDistrict 8 | 4,102 SQ YD | $8.50 | Samron Midwest Contracting, Inc. |
| Mar 5, 2021 | 62L23 | DupageDistrict 1 | 6,500 SQ YD | $4.00 | K-Five Construction Corporation |
| Apr 24, 2020 | 46908 | MassacDistrict 9 | 108 SQ YD | $25.25 | Sierra Bravo Contractors, LLC |
| Jan 17, 2020 | 64L72 | WinnebagoDistrict 2 | 871 SQ YD | $7.71 | William Charles Construction Company, LLC |
| Jun 14, 2019 | 64K76 | Henry, Rock IslandDistrict 2 | 94 SQ YD | $44.00 | John Burns Construction Company |