FT MASSAC 2019
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $1,157,744 | ||
| 2 | E. T. Simonds Construction Company | $1,553,470 | +34.2% | |
| 3 | Samron Midwest Contracting, Inc. | $2,072,990 | +79.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 E. T. Simonds C… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X2110104 | TOPSOIL F & P 4 SPL | 537 | SQ YD | $13.31 | $15.90 | $16.00 | |
| 2 | X2300023 | TIMBER RAILING | 257 | FOOT | $388.20 | $388.03 | $425.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $29,786.00 | $28,160.00 | $18,000.00 | |
| 4 | Z0046304 | P UNDR FOR STRUCT 4 | 136 | FOOT | $22.41 | $19.93 | $25.00 | |
| 5 | 20100210 | TREE REMOV OVER 15 | 202 | UNIT | $27.93 | $88.06 | $100.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 177 | CU YD | $15.91 | $26.92 | $75.00 | |
| 7 | 20300100 | CHANNEL EXCAVATION | 848 | CU YD | $12.43 | $20.90 | $30.00 | |
| 8 | 20400800 | FURNISHED EXCAVATION | 105 | CU YD | $37.41 | $36.56 | $100.00 | |
| 9 | 28000305 | TEMP DITCH CHECKS | 9 | FOOT | $44.08 | $43.93 | $60.00 | |
| 10 | 28000400 | PERIMETER EROS BAR | 404 | FOOT | $4.77 | $6.10 | $6.00 | |
| 11 | 28100109 | STONE RIPRAP CL A5 | 794 | SQ YD | $37.67 | $67.49 | $60.00 | |
| 12 | 28200200 | FILTER FABRIC | 794 | SQ YD | $1.33 | $2.48 | $1.50 | |
| 13 | 35100700 | AGG BASE CSE A 8 | 658 | SQ YD | $17.18 | $21.79 | $15.00 | |
| 14 | 40600275 | BIT MATLS PR CT | 1,481 | POUND | $0.00 | $0.00 | $1.40 | |
| 15 | 40600290 | BIT MATLS TACK CT | 297 | POUND | $0.00 | $0.00 | $1.60 | |
| 16 | 40602978 | HMA BC IL-9.5 N50 | 64 | TON | $166.90 | $176.31 | $175.00 | |
| 17 | 40604000 | HMA SC IL-9.5FG C N50 | 64 | TON | $166.90 | $176.31 | $175.00 | |
| 18 | 42001300 | PROTECTIVE COAT | 452 | SQ YD | $2.68 | $1.26 | $6.00 | |
| 19 | 48100300 | AGGREGATE SHLDS A 4 | 108 | SQ YD | $25.25 | $29.97 | $65.00 | |
| 20 | 50100100 | REM EXIST STRUCT | 1 | EACH | $54,293.10 | $38,177.30 | $75,000.00 | |
| 21 | 50200100 | STRUCTURE EXCAVATION | 29 | CU YD | $23.56 | $21.78 | $35.00 | |
| 22 | 50200300 | COFFERDAM EXCAVATION | 104 | CU YD | $30.12 | $141.16 | $115.00 | |
| 23 | 50201101 | COFFERDAM TYP 1 LOC 1 | 1 | EACH | $19,907.70 | $126,886.46 | $225,000.00 | |
| 24 | 50201102 | COFFERDAM TYP 1 LOC 2 | 1 | EACH | $19,907.70 | $126,886.46 | $225,000.00 | |
| 25 | 50300225 | CONC STRUCT | 148 | CU YD | $933.23 | $1,384.53 | $1,100.00 | |
| 26 | 50300255 | CONC SUP-STR | 127 | CU YD | $1,140.71 | $1,354.86 | $1,650.00 | |
| 27 | 50300260 | BR DECK GROOVING | 371 | SQ YD | $17.69 | $17.86 | $23.00 | |
| 28 | 50400805 | F & E P P CON I-BM 36 | 626 | FOOT | $277.99 | $306.67 | $350.00 | |
| 29 | 50800205 | REINF BARS, EPOXY CTD | 45,540 | POUND | $1.44 | $1.62 | $1.50 | |
| 30 | 51201800 | FUR STL PILE HP14X73 | 1,700 | FOOT | $92.44 | $85.27 | $80.00 | |
| 31 | 51202305 | DRIVING PILES | 1,700 | FOOT | $1.00 | $1.00 | $1.00 | |
| 32 | 51203800 | TEST PILE ST HP14X73 | 4 | EACH | $9,088.57 | $7,995.81 | $5,000.00 | |
| 33 | 51204650 | PILE SHOES | 26 | EACH | $115.05 | $154.00 | $125.00 | |
| 34 | 51500100 | NAME PLATES | 1 | EACH | $501.35 | $536.30 | $450.00 | |
| 35 | 58600101 | GRANULAR BACKFILL STR | 104 | CU YD | $35.33 | $73.27 | $90.00 | |
| 36 | 59100100 | GEOCOMPOSITE WALL DR | 36 | SQ YD | $36.21 | $16.46 | $40.00 | |
| 37 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $3,127.00 | $5,142.50 | $3,300.00 | |
| 38 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,339.00 | $2,970.00 | $3,500.00 | |
| 39 | 63200310 | GUARDRAIL REMOV | 64 | FOOT | $17.75 | $7.40 | $33.00 | |
| 40 | 67100100 | MOBILIZATION | 1 | L SUM | $65,532.65 | $88,197.99 | $355,000.00 | |
| 41 | 78001110 | PAINT PVT MK LINE 4 | 436 | FOOT | $4.34 | $4.50 | $12.00 |