(12-B-1)BR 23
- Let date
- Friday, January 17, 2025
- Contract
- 62W32 · job page
- District
- District 1
- County
- Lake
- Highway
- Limits
- The improvement consists of the installing scour countermeasures such as riprap erosion control and landscaping. The project is located approximately 0.1 miles west of the Tri-State Tollway (I-94) and 1,100 ft east of Illinois Route 21 at SN 049-0046 and SN 049-0047 along Illinois Route 120 in the Village of Gurnee in Lake County.
- Classification
- The installing scour countermeasures such as riprap erosion control and landscaping ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martam Construction Incorporated Low bidder | $617,286 | ||
| 2 | MYS, Incorporated | $679,668 | +10.1% | |
| 3 | Copenhaver Construction, Inc. | $752,547 | +21.9% | |
| 4 | Alliance Contractors, Inc. | $1,070,807 | +73.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martam Construc… | #2 MYS, Incorporat… | #3 Copenhaver Cons… | #4 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | K0029620 | WEED CONT BROADLF WC | 1 | GALLON | $2,650.00 | $3,918.20 | $200.00 | $2,000.00 | |
| 2 | X2511630 | EROS CONT BLANKET SPL | 2,250 | SQ YD | $2.80 | $2.03 | $6.00 | $2.50 | |
| 3 | X6640108 | FENCE REM & REINSTALL | 100 | FOOT | $92.00 | $8.62 | $50.00 | $118.03 | |
| 4 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $30.00 | $68.52 | $30.00 | $18.00 | |
| 5 | 20101000 | TEMPORARY FENCE | 400 | FOOT | $8.00 | $6.29 | $10.00 | $5.00 | |
| 6 | 25100115 | MULCH METHOD 2 | 0.5 | ACRE | $7,000.00 | $4,625.33 | $4,000.00 | $6,000.00 | |
| 7 | 28000250 | TEMP EROS CONTR SEED | 42 | POUND | $11.00 | $9.31 | $0.0100 | $10.00 | |
| 8 | 28000400 | PERIMETER EROS BAR | 18,500 | FOOT | $2.80 | $0.2900 | $0.0100 | $2.50 | |
| 9 | 28100109 | STONE RIPRAP CL A5 | 640 | SQ YD | $135.00 | $173.96 | $240.00 | $655.00 | |
| 10 | 28200200 | FILTER FABRIC | 346 | SQ YD | $5.00 | $5.83 | $5.00 | $1.00 | |
| 11 | 50200300 | COFFERDAM EXCAVATION | 728 | CU YD | $78.00 | $187.66 | $49.00 | $100.00 | |
| 12 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $136,000.00 | $137,320.77 | $140,000.00 | $150,000.00 | |
| 13 | 50201122 | COFFERDAM TYP 2 LOC 2 | 1 | EACH | $136,000.00 | $137,320.77 | $140,000.00 | $150,000.00 | |
| 14 | 66900200 | NON SPL WASTE DISPOSL | 200 | CU YD | $125.00 | $95.22 | $110.00 | $52.00 | |
| 15 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,500.00 | $1,722.65 | $3,000.00 | $1,400.00 | |
| 16 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $4,600.00 | $3,957.46 | $4,000.00 | $3,000.00 | |
| 17 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,200.00 | $581.98 | $2,000.00 | $1,400.00 | |
| 18 | 66901006 | REG SUB MON | 7 | CAL DA | $1,200.00 | $814.77 | $700.00 | $725.00 | |
| 19 | 67100100 | MOBILIZATION | 1 | L SUM | $36,000.00 | $60,477.44 | $70,000.00 | $173,676.00 | |
| 20 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $33,500.00 | $19,176.82 | $146,000.00 | $5,038.00 | |
| 21 | 70100420 | TRAF CONT-PROT 701411 | 1 | EACH | $10,000.00 | $19,176.82 | $200.00 | $5,038.00 |