2023 OB YARD PARKING
- Let date
- Friday, April 26, 2024
- Contract
- 62V97 · job page
- District
- District 1
- County
- Dupage
- Highway
- Limits
- This improvement is located at the IDOT Oakbrook Maintenance yard at 17W125 Butterfield Road, Villa Park, IL. Scope of work includes pavement removal, Catch Basins PCC reconstruction, placement of subbase granular material, HMA asphalt pavement, PCC pavement, and thermoplastic pavement marking.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $780,422 | ||
| 2 | Schroeder Asphalt Services, Inc. | $782,486 | +0.3% | |
| 3 | R. W. Dunteman Company | $795,888 | +2.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 Schroeder Aspha… | #3 R. W. Dunteman … |
|---|---|---|---|---|---|---|---|---|
| 1 | X5537800 | SS CLEANED 12 | 400 | FOOT | $3.85 | $6.00 | $3.85 | |
| 2 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $3,300.00 | $3,500.00 | $1,650.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,000.00 | $8,000.00 | $6,000.00 | |
| 4 | Z0018400 | DRAINAGE STR ADJ | 5 | EACH | $395.00 | $950.00 | $900.00 | |
| 5 | Z0018500 | DRAINAGE STR CLEANED | 6 | EACH | $385.00 | $1,000.00 | $385.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 1,822 | CU YD | $59.00 | $42.00 | $61.75 | |
| 7 | 20201200 | REM & DISP UNS MATL | 182 | CU YD | $118.00 | $45.00 | $32.15 | |
| 8 | 21001000 | GEOTECH FAB F/GR STAB | 547 | SQ YD | $2.40 | $2.00 | $5.60 | |
| 9 | 30300001 | AGG SUBGRADE IMPROVE | 547 | CU YD | $0.0100 | $53.00 | $6.65 | |
| 10 | 31101400 | SUB GRAN MAT B 6 | 10,935 | SQ YD | $9.94 | $9.15 | $2.85 | |
| 11 | 40600275 | BIT MATLS PR CT | 24,603 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 12 | 40600290 | BIT MATLS TACK CT | 3,612 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 13 | 40603085 | HMA BC IL-19.0 N70 | 1,837 | TON | $82.10 | $87.00 | $98.85 | |
| 14 | 40604062 | HMA SC IL-9.5 D N70 | 1,134 | TON | $100.00 | $94.00 | $102.65 | |
| 15 | 42000300 | PCC PVT 8 | 540 | SQ YD | $99.50 | $150.00 | $96.65 | |
| 16 | 42001300 | PROTECTIVE COAT | 540 | SQ YD | $3.00 | $3.00 | $2.70 | |
| 17 | 44000100 | PAVEMENT REM | 10,935 | SQ YD | $6.00 | $5.00 | $14.10 | |
| 18 | 44000155 | HMA SURF REM 1 1/2 | 2,560 | SQ YD | $2.50 | $4.00 | $2.50 | |
| 19 | 44201765 | CL D PATCH T2 10 | 50 | SQ YD | $30.00 | $110.00 | $91.40 | |
| 20 | 44201769 | CL D PATCH T3 10 | 50 | SQ YD | $30.00 | $110.00 | $91.40 | |
| 21 | 66900200 | NON SPL WASTE DISPOSL | 430 | CU YD | $87.00 | $100.00 | $21.60 | |
| 22 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,585.00 | $2,200.00 | $1,720.00 | |
| 23 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,400.00 | $2,600.00 | $2,400.00 | |
| 24 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $2,500.00 | $1,390.00 | |
| 25 | 66901006 | REG SUB MON | 3 | CAL DA | $700.00 | $1,050.00 | $650.00 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $47,659.98 | $21,000.00 | $55,117.50 | |
| 27 | 78000200 | THPL PVT MK LINE 4 | 600 | FOOT | $4.16 | $8.00 | $20.00 |