2022 TRAFFIC LT
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | John Burns Construction Company Low bidder | $3,452,919 | ||
| 2 | Hecker and Company, Inc. | $4,085,852 | +18.3% | |
| 3 | H & H Electric Co. | $4,146,513 | +20.1% | |
| 4 | Meade Inc. | $4,158,330 | +20.4% | |
| 5 | Electric Conduit Construction | $4,426,715 | +28.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 John Burns Cons… | #2 Hecker and Comp… | #3 H & H Electric … | #4 Meade Inc. | #5 Electric Condui… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X1400190 | REM HM LUMNRS SALVAGE | 163 | EACH | $45.00 | $332.00 | $127.92 | $47.63 | $458.47 | |
| 2 | X1400402 | L CT B 480V200D RS FO | 2 | EACH | $55,000.00 | $57,800.00 | $52,447.10 | $54,947.16 | $50,773.67 | |
| 3 | X2511630 | EROS CONT BLANKET SPL | 12,951 | SQ YD | $0.1000 | $1.90 | $1.25 | $1.93 | $1.68 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $100,000.00 | $138,000.00 | $0.0100 | $132,000.00 | $1,050.00 | |
| 5 | X8420111 | REM UNDERPASS LU NS | 38 | EACH | $200.00 | $682.00 | $2,141.87 | $433.04 | $1,053.28 | |
| 6 | X8420510 | REM TOWER FDN | 50 | EACH | $1,000.00 | $1,350.00 | $1,550.62 | $3,413.56 | $832.31 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $39,600.00 | $34,929.59 | $25,190.00 | $29,925.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 155 | SQ FT | $16.00 | $55.00 | $31.22 | $27.50 | $26.25 | |
| 9 | Z0033020 | LUM SFTY CABLE ASMBLY | 189 | EACH | $100.00 | $19.00 | $252.78 | $50.40 | $165.64 | |
| 10 | Z0033028 | MAINT LIGHTING SYS | 15 | CAL MO | $1,000.00 | $5,390.00 | $0.0100 | $1,732.16 | $1,500.00 | |
| 11 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 370 | CU YD | $1.00 | $1.00 | $0.0100 | $11.00 | $40.37 | |
| 14 | 20400800 | FURNISHED EXCAVATION | 185 | CU YD | $1.00 | $1.00 | $24.97 | $11.00 | $21.12 | |
| 15 | 21101505 | TOPSOIL EXC & PLAC | 2,159 | CU YD | $1.00 | $1.00 | $0.0100 | $11.00 | $27.70 | |
| 16 | 21101625 | TOPSOIL F & P 6 | 1,000 | SQ YD | $1.00 | $16.00 | $11.24 | $16.50 | $7.35 | |
| 17 | 25000210 | SEEDING CL 2A | 3 | ACRE | $1,000.00 | $2,890.00 | $3,870.66 | $2,970.00 | $3,305.40 | |
| 18 | 25000400 | NITROGEN FERT NUTR | 241 | POUND | $3.00 | $3.20 | $3.75 | $3.30 | $3.15 | |
| 19 | 25000500 | PHOSPHORUS FERT NUTR | 241 | POUND | $3.00 | $3.20 | $3.75 | $3.30 | $3.15 | |
| 20 | 25000600 | POTASSIUM FERT NUTR | 241 | POUND | $3.00 | $3.20 | $3.75 | $3.30 | $3.15 | |
| 21 | 28000250 | TEMP EROS CONTR SEED | 1,500 | POUND | $0.1000 | $5.50 | $3.75 | $5.83 | $5.25 | |
| 22 | 28000305 | TEMP DITCH CHECKS | 500 | FOOT | $2.00 | $13.00 | $6.24 | $13.48 | $4.10 | |
| 23 | 28000400 | PERIMETER EROS BAR | 9,148 | FOOT | $1.00 | $3.05 | $2.50 | $3.14 | $2.10 | |
| 24 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,000.00 | $6,210.00 | $6,118.14 | $3,685.00 | $3,570.00 | |
| 25 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $100.00 | $538.00 | $624.30 | $1,320.00 | $3,045.00 | |
| 26 | 66901006 | REG SUB MON | 175 | CAL DA | $1.00 | $689.00 | $799.10 | $1,320.00 | $1,039.50 | |
| 27 | 67000400 | ENGR FIELD OFFICE A | 15 | CAL MO | $2,000.00 | $5,220.00 | $2,746.92 | $11,000.00 | $2,001.10 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $205,800.00 | $245,000.00 | $415,935.18 | $249,000.00 | $329,563.50 | |
| 29 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $100.00 | $4,600.00 | $0.0100 | $550.00 | $1,050.00 | |
| 30 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $100.00 | $9,080.00 | $0.0100 | $110.00 | $1,050.00 | |
| 31 | 80400100 | ELECT SERV INSTALL | 2 | EACH | $7,000.00 | $3,280.00 | $2,118.90 | $3,089.80 | $4,043.29 | |
| 32 | 80400200 | ELECT UTIL SERV CONN | 1 | L SUM | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | $20,000.00 | |
| 33 | 81028240 | UNDRGRD C GALVS 4 | 75 | FOOT | $102.00 | $75.00 | $49.85 | $165.06 | $100.48 | |
| 34 | 81028390 | UNDRGRD C PVC 4 | 1,915 | FOOT | $62.00 | $54.50 | $31.82 | $41.91 | $56.04 | |
| 35 | 81100320 | CON AT ST 1 PVC GS | 1,454 | FOOT | $68.00 | $58.00 | $35.85 | $49.41 | $81.68 | |
| 36 | 81100805 | CON AT ST 3 PVC GALVS | 100 | FOOT | $174.00 | $106.00 | $103.96 | $136.72 | $143.84 | |
| 37 | 81300220 | JUN BX SS AS 6X6X4 | 26 | EACH | $790.00 | $1,160.00 | $1,175.11 | $908.70 | $2,356.11 | |
| 38 | 81300530 | JUN BX SS AS 12X10X6 | 13 | EACH | $1,896.00 | $1,610.00 | $2,300.08 | $1,582.49 | $2,596.42 | |
| 39 | 81300830 | JUN BX SS AS 18X18X8 | 7 | EACH | $3,072.00 | $3,010.00 | $3,681.88 | $2,384.92 | $3,136.10 | |
| 40 | 81603081 | UD 3#2#4GXLPUSE 1.5 P | 48,570 | FOOT | $14.00 | $17.41 | $15.54 | $17.57 | $17.50 | |
| 41 | 81702110 | EC C XLP USE 1C 10 | 4,577 | FOOT | $2.00 | $3.65 | $3.96 | $3.59 | $9.23 | |
| 42 | 81702220 | EC C XLP USE 1C 350 | 381 | FOOT | $13.00 | $27.00 | $17.10 | $23.63 | $27.04 | |
| 43 | 82110008 | LUM LED RDWY H | 189 | EACH | $761.00 | $825.00 | $621.30 | $510.68 | $663.91 | |
| 44 | 82110027 | LUM LED UP SUS E | 26 | EACH | $2,108.00 | $2,840.00 | $3,714.08 | $3,691.95 | $5,850.18 | |
| 45 | 83050810 | LT P A 47.5MH 15MA | 189 | EACH | $4,700.00 | $5,260.00 | $5,081.77 | $4,276.58 | $5,467.32 | |
| 46 | 83600365 | LP F M 15BC 10" X 8' | 189 | EACH | $2,550.00 | $1,550.00 | $1,659.88 | $1,599.54 | $1,904.19 | |
| 47 | 83800205 | BKWY DEV TR B 15BC | 189 | EACH | $515.00 | $611.00 | $564.93 | $567.27 | $657.33 | |
| 48 | 84200605 | REM LT TWR NO SAL | 50 | EACH | $3,000.00 | $3,010.00 | $9,090.78 | $5,777.80 | $5,105.57 | |
| 49 | 84500110 | REMOV LIGHTING CONTR | 2 | EACH | $500.00 | $1,030.00 | $383.75 | $1,732.16 | $1,334.15 | |
| 50 | 84500120 | REMOV ELECT SERV INST | 2 | EACH | $500.00 | $1,280.00 | $383.75 | $1,732.16 | $1,334.15 | |
| 51 | 84500130 | REMOV LTG CONTR FDN | 2 | EACH | $500.00 | $1,750.00 | $388.96 | $2,598.24 | $2,865.55 |