FAP 0377 22 BJ
- Let date
- Friday, September 22, 2023
- Contract
- 62T25 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- The proposed improvement consists of bridge deck overlay and joint repairs of IL 58 (Dempster Street) at I-94 (Edens Expressway) in the Village of Morton Grove and the Village of Skokie, Cook County. Total gross length= 1539 FT and net length= 361 FT.
- Classification
- Bridge deck overlay and joint repairs of IL 58 (Dempster Street) at I-94 (Edens Expressway) in the Village of
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lorig Construction Company Low bidder | $1,452,432 | ||
| 2 | Areatha Construction Co., Inc. | $1,487,382 | +2.4% | |
| 3 | Martam Construction Incorporated | $1,487,968 | +2.4% | |
| 4 | Rausch Infrastructure, LLC | $1,728,728 | +19.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lorig Construct… | #2 Areatha Constru… | #3 Martam Construc… | #4 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | K0029618 | WEED CONT BROADLF TRF | 1 | GALLON | $3,200.00 | $3,200.00 | $3,600.00 | $3,920.00 | |
| 2 | X0326766 | CLEAN RESEAL RLF JNT | 160 | FOOT | $75.00 | $62.95 | $65.00 | $36.30 | |
| 3 | X5030250 | BR DECK GROOVING LONG | 2,074 | SQ YD | $7.00 | $7.65 | $8.00 | $9.30 | |
| 4 | X6700407 | ENGR FLD OFF A D1 | 12 | CAL MO | $3,300.00 | $2,500.00 | $3,200.00 | $4,900.00 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $125,000.00 | $25,000.00 | $154,000.00 | $57,000.00 | |
| 6 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $100,000.00 | $62,900.00 | $76,000.00 | $42,000.00 | |
| 7 | X7013820 | TR CONT SURVEIL EXPWY | 65 | CAL DA | $150.00 | $500.00 | $350.00 | $183.00 | |
| 8 | X7830050 | RAISD REF PM REFL REM | 74 | EACH | $35.00 | $20.00 | $10.00 | $12.25 | |
| 9 | Z0001700 | APPROACH SL REP (FD) | 23 | SQ YD | $1,000.00 | $1,227.00 | $850.00 | $990.00 | |
| 10 | Z0001800 | APPROACH SL REP (PD) | 27 | SQ YD | $700.00 | $610.70 | $450.00 | $845.00 | |
| 11 | Z0001903 | STRUCT STEEL REMOV | 30 | POUND | $125.00 | $20.10 | $85.00 | $52.00 | |
| 12 | Z0006016 | BR DK LTX C OLY 2 3/4 | 2,180 | SQ YD | $128.00 | $148.85 | $122.00 | $150.00 | |
| 13 | Z0012130 | BR DECK SCAR 3/4 | 2,180 | SQ YD | $55.00 | $72.25 | $42.00 | $51.50 | |
| 14 | Z0012750 | CONC MEDIAN REPAIR | 44 | SQ FT | $90.00 | $166.35 | $165.00 | $143.00 | |
| 15 | Z0012754 | STR REP CON DP = < 5 | 346 | SQ FT | $250.00 | $172.65 | $190.00 | $254.00 | |
| 16 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $2,500.00 | $6,000.00 | $12,250.00 | |
| 17 | Z0016001 | DECK SLAB REP (FD-T1) | 3 | SQ YD | $2,000.00 | $900.00 | $3,600.00 | $1,530.00 | |
| 18 | Z0016002 | DECK SLAB REP (FD-T2) | 5 | SQ YD | $2,000.00 | $900.00 | $3,200.00 | $1,530.00 | |
| 19 | Z0018051 | DRAINAGE SCUPPERS ADJ | 8 | EACH | $1,000.00 | $538.20 | $900.00 | $1,130.00 | |
| 20 | Z0029090 | DIAMOND GRIND BR SEC | 1,987 | SQ YD | $8.00 | $12.95 | $11.50 | $13.00 | |
| 21 | Z0030850 | TEMP INFO SIGNING | 252 | SQ FT | $20.00 | $18.00 | $15.00 | $22.00 | |
| 22 | Z0064600 | SELECTIVE CLEARING | 0.25 | ACRE | $16,000.00 | $16,000.00 | $20,000.00 | $19,600.00 | |
| 23 | Z0073200 | TEMP SHORING & CRIB | 3 | EACH | $1,000.00 | $7,500.00 | $10,000.00 | $15,000.00 | |
| 24 | Z0073510 | TEMP TR SIGNAL TIMING | 4 | EACH | $500.00 | $1,500.00 | $2,500.00 | $1,470.00 | |
| 25 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 26 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 27 | 20200100 | EARTH EXCAVATION | 15 | CU YD | $80.00 | $94.50 | $88.00 | $115.00 | |
| 28 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $8,000.00 | $8,000.00 | $10,000.00 | $9,800.00 | |
| 29 | 25000400 | NITROGEN FERT NUTR | 30 | POUND | $3.00 | $3.00 | $4.00 | $3.70 | |
| 30 | 25000500 | PHOSPHORUS FERT NUTR | 30 | POUND | $3.00 | $3.00 | $4.00 | $3.70 | |
| 31 | 25000600 | POTASSIUM FERT NUTR | 30 | POUND | $3.00 | $3.00 | $4.00 | $3.70 | |
| 32 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $6,000.00 | $6,000.00 | $8,000.00 | $7,350.00 | |
| 33 | 28000400 | PERIMETER EROS BAR | 100 | FOOT | $9.00 | $9.00 | $12.00 | $11.00 | |
| 34 | 40600290 | BIT MATLS TACK CT | 439 | POUND | $0.0100 | $0.0100 | $0.1000 | $0.0100 | |
| 35 | 40600982 | HMA SURF REM BUTT JT | 592 | SQ YD | $28.00 | $28.00 | $32.00 | $34.30 | |
| 36 | 40604172 | P HMA SC IL-9.5 E N70 | 119 | TON | $275.00 | $265.00 | $290.00 | $325.00 | |
| 37 | 42400200 | PC CONC SIDEWALK 5 | 129 | SQ FT | $17.00 | $49.55 | $15.00 | $31.85 | |
| 38 | 44000500 | COMB CURB GUTTER REM | 30 | FOOT | $27.00 | $27.50 | $12.00 | $49.00 | |
| 39 | 44000600 | SIDEWALK REM | 129 | SQ FT | $8.00 | $13.85 | $5.00 | $24.50 | |
| 40 | 50102400 | CONC REM | 27.9 | CU YD | $2,300.00 | $1,500.00 | $1,600.00 | $1,576.00 | |
| 41 | 50157300 | PROTECTIVE SHIELD | 1,432 | SQ YD | $1.00 | $35.00 | $45.00 | $147.00 | |
| 42 | 50300255 | CONC SUP-STR | 30.3 | CU YD | $3,200.00 | $2,662.35 | $2,400.00 | $2,490.00 | |
| 43 | 50300300 | PROTECTIVE COAT | 2,234 | SQ YD | $1.00 | $2.80 | $1.00 | $4.55 | |
| 44 | 50500405 | F & E STRUCT STEEL | 29 | POUND | $200.00 | $28.50 | $226.00 | $65.00 | |
| 45 | 50800205 | REINF BARS, EPOXY CTD | 3,720 | POUND | $3.75 | $4.00 | $3.00 | $3.90 | |
| 46 | 50800515 | BAR SPLICERS | 48 | EACH | $80.00 | $51.15 | $85.00 | $122.00 | |
| 47 | 52000110 | PREF JT STRIP SEAL | 194 | FOOT | $245.00 | $324.25 | $225.00 | $250.00 | |
| 48 | 52100520 | ANCHOR BOLTS 1 | 4 | EACH | $375.00 | $386.25 | $120.00 | $415.00 | |
| 49 | 58700300 | CONCRETE SEALER | 7,526 | SQ FT | $3.00 | $1.35 | $1.00 | $2.00 | |
| 50 | 60605000 | COMB CC&G TB6.24 | 30 | FOOT | $95.00 | $253.45 | $69.00 | $184.00 | |
| 51 | 66900200 | NON SPL WASTE DISPOSL | 15 | CU YD | $85.00 | $104.20 | $122.00 | $155.00 | |
| 52 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,500.00 | $1,600.00 | $1,800.00 | $1,960.00 | |
| 53 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,500.00 | $3,400.00 | $3,700.00 | $4,171.66 | |
| 54 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,500.00 | $500.00 | $600.00 | $612.00 | |
| 55 | 66901006 | REG SUB MON | 5 | CAL DA | $900.00 | $675.00 | $750.00 | $827.00 | |
| 56 | 67100100 | MOBILIZATION | 1 | L SUM | $75,000.00 | $89,154.00 | $88,000.00 | $100,000.00 | |
| 57 | 70107025 | CHANGEABLE MESSAGE SN | 210 | CAL DA | $26.00 | $30.00 | $30.00 | $32.00 | |
| 58 | 70300100 | SHORT TERM PAVT MKING | 967 | FOOT | $2.00 | $1.50 | $1.00 | $2.50 | |
| 59 | 70300150 | SHRT TRM PAVT MK REM | 4,187 | SQ FT | $0.4000 | $2.00 | $0.4000 | $0.5000 | |
| 60 | 70307120 | TEMP PVT MK L4 T4 TAPE | 7,357 | FOOT | $1.20 | $1.40 | $1.30 | $1.50 | |
| 61 | 70307125 | TEMP PVT MK L5 T4 TAPE | 463 | FOOT | $3.10 | $1.75 | $1.70 | $3.80 | |
| 62 | 70307130 | TEMP PVT MK L6 T4 TAPE | 579 | FOOT | $2.00 | $2.10 | $1.90 | $2.50 | |
| 63 | 70307140 | TEMP PVT MK L8 T4 TAPE | 1,005 | FOOT | $2.40 | $2.80 | $2.70 | $3.00 | |
| 64 | 70307160 | TEMP PVT MK L12 T4 TAPE | 259 | FOOT | $4.00 | $4.15 | $4.00 | $5.00 | |
| 65 | 70400100 | TEMP CONC BARRIER | 1,437.5 | FOOT | $28.00 | $44.45 | $32.00 | $45.00 | |
| 66 | 70400125 | PIN TEMP CONC BARRIER | 104 | EACH | $20.00 | $29.70 | $15.00 | $50.00 | |
| 67 | 70400200 | REL TEMP CONC BARRIER | 1,300 | FOOT | $5.00 | $13.50 | $8.00 | $20.00 | |
| 68 | 70600255 | IMP ATTN TEMP FRN TL2 | 2 | EACH | $4,200.00 | $5,410.00 | $5,800.00 | $5,145.00 | |
| 69 | 70600260 | IMP ATTN TEMP FRN TL3 | 2 | EACH | $4,500.00 | $6,880.00 | $7,400.00 | $5,512.00 | |
| 70 | 70600322 | IMP ATTN REL FRN TL2 | 2 | EACH | $2,300.00 | $2,462.00 | $2,800.00 | $2,817.00 | |
| 71 | 70600332 | IMP ATTN REL FRN TL3 | 1 | EACH | $2,500.00 | $2,870.00 | $3,200.00 | $3,062.00 | |
| 72 | 78000200 | THPL PVT MK LINE 4 | 3,775 | FOOT | $1.35 | $1.35 | $1.10 | $1.65 | |
| 73 | 78000500 | THPL PVT MK LINE 8 | 1,892 | FOOT | $2.55 | $2.55 | $2.20 | $3.00 | |
| 74 | 78000600 | THPL PVT MK LINE 12 | 265 | FOOT | $5.05 | $5.05 | $3.30 | $6.20 | |
| 75 | 78004625 | PREF PL PM TD STD L 5 | 306 | FOOT | $5.00 | $5.00 | $10.00 | $6.10 | |
| 76 | 78004635 | PREF PL PM TD STD L 7 | 130 | FOOT | $26.00 | $26.00 | $15.00 | $32.00 | |
| 77 | 78004640 | PREF PL PM TD STD L 8 | 154 | FOOT | $9.00 | $9.00 | $16.00 | $11.00 | |
| 78 | 78009004 | MOD URETH PM LINE 4 | 1,047 | FOOT | $2.25 | $2.25 | $3.60 | $2.75 | |
| 79 | 78009008 | MOD URETH PM LINE 8 | 519 | FOOT | $2.95 | $2.95 | $7.00 | $3.60 | |
| 80 | 78011030 | GRV RCSD PVT MRKG 6 | 306 | FOOT | $0.6500 | $0.6500 | $3.60 | $1.00 | |
| 81 | 78011040 | GRV RCSD PVT MRKG 8 | 130 | FOOT | $1.15 | $1.15 | $6.00 | $1.50 | |
| 82 | 78011045 | GRV RCSD PVT MRKG 9 | 154 | FOOT | $1.25 | $1.25 | $7.00 | $2.00 | |
| 83 | 78100100 | RAISED REFL PAVT MKR | 8 | EACH | $375.00 | $375.00 | $500.00 | $460.00 | |
| 84 | 78100300 | REPLACEMENT REFLECTOR | 74 | EACH | $35.00 | $35.00 | $20.00 | $43.00 | |
| 85 | 78200011 | BARR WALL REF TYPE C | 46 | EACH | $8.00 | $15.00 | $30.00 | $10.00 | |
| 86 | 78300200 | RAISED REF PVT MK REM | 8 | EACH | $40.00 | $25.00 | $30.00 | $245.00 | |
| 87 | 78300202 | PAVMT MRKG REM WTR BL | 3,353 | SQ FT | $1.50 | $2.25 | $2.00 | $2.00 |