FAP 0021 22 BJ
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Martam Construction Incorporated Low bidder | $1,888,608 | ||
| 2 | Areatha Construction Co., Inc. | $2,171,979 | +15.0% | |
| 3 | Lorig Construction Company | $2,324,818 | +23.1% | |
| 4 | Rausch Infrastructure, LLC | $2,547,704 | +34.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Martam Construc… | #2 Areatha Constru… | #3 Lorig Construct… | #4 Rausch Infrastr… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0322215 | CLN BRDG SCUPS/DNSPTS | 12 | EACH | $500.00 | $141.35 | $400.00 | $500.00 | |
| 2 | X4400503 | CC&G RMVL REPL > 10FT | 3,200 | FOOT | $49.00 | $65.00 | $77.00 | $79.00 | |
| 3 | X5537800 | SS CLEANED 12 | 500 | FOOT | $5.00 | $5.00 | $4.00 | $5.00 | |
| 4 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $2,800.00 | $2,500.00 | $2,700.00 | $5,000.00 | |
| 5 | X7010005 | MAINT TRAFF ILL TLWY | 1 | L SUM | $32,500.00 | $36,700.00 | $2,000.00 | $35,000.00 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $180,500.00 | $38,500.00 | $350,000.00 | $40,000.00 | |
| 7 | X7010238 | CHANGE MESSAGE SN SPL | 6 | CAL MO | $1,100.00 | $900.00 | $1,000.00 | $950.00 | |
| 8 | X7830050 | RRPM REFLECTOR REMOVL | 131 | EACH | $20.00 | $6.00 | $6.00 | $9.00 | |
| 9 | X7830052 | RRPM REFLECTOR REPLAC | 131 | EACH | $30.00 | $12.00 | $12.00 | $15.00 | |
| 10 | X8891009 | VID VEH DET SYS SN AP | 1 | EACH | $25,000.00 | $23,012.60 | $17,000.00 | $27,000.00 | |
| 11 | Z0006014 | BR DK LTX C OLY 2 1/2 | 3,341 | SQ YD | $112.00 | $120.30 | $109.00 | $125.00 | |
| 12 | Z0010605 | CLEAN DRAINAGE SYSTEM | 1 | L SUM | $600.00 | $1,714.30 | $500.00 | $600.00 | |
| 13 | Z0012130 | BR DECK SCAR 3/4 | 2,734 | SQ YD | $40.00 | $53.90 | $55.00 | $45.00 | |
| 14 | Z0012138 | BR DECK SCAR 1 3/4 | 607 | SQ YD | $40.00 | $57.10 | $63.00 | $65.00 | |
| 15 | Z0018051 | DRAINAGE SCUPPERS ADJ | 12 | EACH | $900.00 | $712.40 | $1,550.00 | $900.00 | |
| 16 | Z0030850 | TEMP INFO SIGNING | 57 | SQ FT | $22.00 | $12.00 | $14.00 | $24.00 | |
| 17 | Z0073510 | TEMP TR SIGNAL TIMING | 10 | EACH | $660.00 | $900.00 | $750.00 | $700.00 | |
| 18 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 19 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 20 | 40600985 | PCC SURF REM BUTT JT | 633.5 | SQ YD | $16.00 | $35.00 | $22.00 | $35.00 | |
| 21 | 42001300 | PROTECTIVE COAT | 1,067 | SQ YD | $1.00 | $0.0500 | $2.00 | $3.50 | |
| 22 | 44200050 | WELDED WIRE REINF | 1,831 | SQ YD | $8.00 | $12.00 | $22.00 | $16.50 | |
| 23 | 44200982 | CL B PATCH T2 11 | 560 | SQ YD | $135.00 | $175.00 | $185.00 | $223.00 | |
| 24 | 44200986 | CL B PATCH T3 11 | 1,688 | SQ YD | $128.00 | $165.00 | $175.00 | $208.00 | |
| 25 | 44200988 | CL B PATCH T4 11 | 143 | SQ YD | $125.00 | $165.00 | $175.00 | $208.00 | |
| 26 | 44201299 | DOWEL BARS 1 1/2 | 1,860 | EACH | $24.00 | $24.00 | $25.00 | $26.00 | |
| 27 | 50102400 | CONC REM | 40.9 | CU YD | $1,600.00 | $1,661.70 | $2,300.00 | $2,000.00 | |
| 28 | 50157300 | PROTECTIVE SHIELD | 1,746 | SQ YD | $1.00 | $71.10 | $1.00 | $90.00 | |
| 29 | 50300255 | CONC SUP-STR | 44.7 | CU YD | $2,450.00 | $2,479.15 | $1,400.00 | $4,000.00 | |
| 30 | 50300260 | BR DECK GROOVING | 3,321 | SQ YD | $6.00 | $5.35 | $5.50 | $7.70 | |
| 31 | 50300300 | PROTECTIVE COAT | 3,466 | SQ YD | $1.00 | $2.05 | $1.75 | $3.85 | |
| 32 | 50800205 | REINF BARS, EPOXY CTD | 6,080 | POUND | $2.50 | $3.00 | $4.00 | $3.00 | |
| 33 | 50800515 | BAR SPLICERS | 40 | EACH | $63.00 | $61.75 | $85.00 | $210.00 | |
| 34 | 52000110 | PREF JT STRIP SEAL | 344 | FOOT | $245.00 | $337.55 | $285.00 | $288.00 | |
| 35 | 66900200 | NON SPL WASTE DISPOSL | 10 | CU YD | $115.00 | $115.00 | $125.00 | $116.00 | |
| 36 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,900.00 | $1,100.00 | $1,300.00 | $2,133.00 | |
| 37 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,600.00 | $4,400.00 | $4,300.00 | $2,844.00 | |
| 38 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,200.00 | $500.00 | $500.00 | $2,370.00 | |
| 39 | 66901006 | REG SUB MON | 1 | CAL DA | $1,100.00 | $700.00 | $2,000.00 | $1,185.00 | |
| 40 | 67100100 | MOBILIZATION | 1 | L SUM | $110,000.00 | $136,100.00 | $125,000.00 | $152,000.00 | |
| 41 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $440.00 | $200.00 | $200.00 | $590.00 | |
| 42 | 70300150 | SHRT TRM PAVT MK REM | 2,447 | SQ FT | $0.5000 | $0.4000 | $0.4000 | $2.00 | |
| 43 | 70307120 | TEMP PVT MK L4 T4 TAPE | 7,341 | FOOT | $1.50 | $1.20 | $1.20 | $1.50 | |
| 44 | 70400100 | TEMP CONC BARRIER | 912.5 | FOOT | $18.00 | $26.10 | $25.00 | $45.00 | |
| 45 | 70400200 | REL TEMP CONC BARRIER | 826 | FOOT | $6.00 | $6.75 | $5.00 | $18.00 | |
| 46 | 70600255 | IMP ATTN TEMP FRN TL2 | 2 | EACH | $4,200.00 | $4,000.00 | $4,000.00 | $4,750.00 | |
| 47 | 70600322 | IMP ATTN REL FRN TL2 | 2 | EACH | $2,500.00 | $2,000.00 | $2,000.00 | $2,370.00 | |
| 48 | 78009000 | MOD URETH PM LTR-SYM | 185 | SQ FT | $11.00 | $6.00 | $6.00 | $5.75 | |
| 49 | 78009004 | MOD URETH PM LINE 4 | 7,520 | FOOT | $1.20 | $1.10 | $1.10 | $1.00 | |
| 50 | 78009006 | MOD URETH PM LINE 6 | 1,029 | FOOT | $2.20 | $1.20 | $1.20 | $2.15 | |
| 51 | 78009008 | MOD URETH PM LINE 8 | 1,584 | FOOT | $2.70 | $1.80 | $1.80 | $3.00 | |
| 52 | 78009012 | MOD URETH PM LINE 12 | 177 | FOOT | $6.00 | $3.00 | $3.00 | $4.15 | |
| 53 | 78009024 | MOD URETH PM LINE 24 | 133 | FOOT | $12.00 | $6.00 | $7.00 | $5.70 | |
| 54 | 78100100 | RAISED REFL PAVT MKR | 39 | EACH | $160.00 | $650.00 | $650.00 | $200.00 | |
| 55 | 78300200 | RAISED REF PVT MK REM | 39 | EACH | $35.00 | $23.00 | $20.00 | $118.00 | |
| 56 | 78300202 | PVT MKG REM WTR BLAST | 124 | SQ FT | $30.00 | $23.00 | $24.00 | $36.00 | |
| 57 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $6,600.00 | $6,057.00 | $5,000.00 | $7,500.00 | |
| 58 | 89502200 | MOD EX CONTR | 1 | EACH | $11,000.00 | $10,262.60 | $3,000.00 | $18,000.00 |