2021-081-RS
- Let date
- Friday, January 21, 2022
- Contract
- 62P18 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- Designed Overlay project on IL 43 (Harlem Ave.) at 26th Street and continues northerly direction for (4.49 mile) to south of IL 64 North Ave located in the City of Berwyn and the Villages of Forest Park, North Riverside, Oak Park, River Forest, and Riverside.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Arrow Road Construction Co. Low bidder | $5,762,151 | ||
| 2 | K-Five Construction Corporation | $6,082,740 | +5.6% | |
| 3 | R. W. Dunteman Company | $6,437,507 | +11.7% | |
| 4 | Plote Construction, Inc. | $6,781,110 | +17.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Arrow Road Cons… | #2 K-Five Construc… | #3 R. W. Dunteman … | #4 Plote Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $3,000.00 | $2,250.00 | $3,970.00 | $4,000.00 | |
| 2 | X0327149 | RELO BENCH | 1 | EACH | $2,500.00 | $2,500.00 | $699.51 | $500.00 | |
| 3 | X0327611 | REM & REIN BRIC PAVER | 24 | SQ FT | $50.00 | $50.00 | $25.00 | $25.00 | |
| 4 | X4400501 | COMB C&G REMOV REPL < = 10FT | 610 | FOOT | $50.00 | $50.00 | $46.00 | $55.00 | |
| 5 | X6030310 | FR & LIDS ADJUST SPL | 292 | EACH | $725.00 | $750.00 | $750.00 | $750.00 | |
| 6 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $8,500.00 | $1.00 | $2,500.00 | $7,500.00 | |
| 7 | Z0004562 | COMB C C&G REM & REPL | 8,320 | FOOT | $37.00 | $39.00 | $36.25 | $40.00 | |
| 8 | Z0018500 | DRAINAGE STR CLEANED | 278 | EACH | $310.00 | $310.00 | $450.00 | $310.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $18.00 | $22.00 | $22.00 | $14.00 | |
| 10 | Z0038123 | PCC SUR REM 2 1/2 | 884 | SQ YD | $17.00 | $5.00 | $5.96 | $9.00 | |
| 11 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 12 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 13 | 20200100 | EARTH EXCAVATION | 20 | CU YD | $65.00 | $60.00 | $75.00 | $70.00 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 473 | SQ YD | $3.00 | $3.00 | $10.00 | $8.00 | |
| 15 | 25200110 | SODDING SALT TOLERANT | 473 | SQ YD | $19.00 | $19.00 | $15.00 | $9.00 | |
| 16 | 25200200 | SUPPLE WATERING | 50 | UNIT | $25.00 | $25.00 | $0.0100 | $10.00 | |
| 17 | 40600290 | BIT MATLS TACK CT | 99,881 | POUND | $0.8000 | $0.0100 | $0.6100 | $0.0100 | |
| 18 | 40600400 | MIX CR JTS FLANGEWYS | 468 | TON | $75.00 | $50.00 | $100.01 | $75.00 | |
| 19 | 40600982 | HMA SURF REM BUTT JT | 1,318 | SQ YD | $8.00 | $0.0100 | $12.98 | $20.00 | |
| 20 | 40601005 | HMA REPL OVER PATCH | 1,628 | TON | $1.00 | $40.00 | $85.71 | $50.00 | |
| 21 | 40602985 | HMA BC IL-9.5 N70 | 14,255 | TON | $71.75 | $97.40 | $82.63 | $88.00 | |
| 22 | 40603200 | P HMA BC IL-4.75 N50 | 45 | TON | $200.00 | $100.00 | $89.62 | $215.00 | |
| 23 | 40605026 | P HMA SC SMA 9.5 F N80 | 15,369 | TON | $108.25 | $120.00 | $108.49 | $120.00 | |
| 24 | 40733705 | LONG JOINT SEALANT | 50,414 | FOOT | $2.20 | $2.25 | $3.10 | $2.17 | |
| 25 | 42001300 | PROTECTIVE COAT | 2,270 | SQ YD | $1.00 | $1.00 | $2.00 | $1.00 | |
| 26 | 42400200 | PC CONC SIDEWALK 5 | 1,344 | SQ FT | $10.00 | $8.00 | $12.00 | $9.00 | |
| 27 | 42400800 | DETECTABLE WARNINGS | 168 | SQ FT | $32.00 | $32.00 | $45.00 | $32.00 | |
| 28 | 44000156 | HMA SURF REM 1 3/4 | 26,153 | SQ YD | $2.30 | $2.75 | $3.12 | $2.50 | |
| 29 | 44000159 | HMA SURF REM 2 1/2 | 195 | SQ YD | $17.00 | $5.00 | $2.92 | $40.00 | |
| 30 | 44000164 | HMA SURF REM 3 3/4 | 129,526 | SQ YD | $4.10 | $5.50 | $6.97 | $9.10 | |
| 31 | 44000600 | SIDEWALK REM | 1,299 | SQ FT | $9.00 | $3.00 | $2.50 | $3.00 | |
| 32 | 44002219 | HMA RM OV PATCH 4 3/4 | 6,120 | SQ YD | $1.00 | $2.50 | $14.17 | $5.00 | |
| 33 | 44003510 | MEDIAN REMOVAL (PD) | 547 | SQ FT | $5.75 | $2.00 | $3.86 | $5.00 | |
| 34 | 44201765 | CL D PATCH T2 10 | 2,650 | SQ YD | $27.00 | $28.00 | $40.00 | $50.00 | |
| 35 | 44201769 | CL D PATCH T3 10 | 1,540 | SQ YD | $27.00 | $28.00 | $40.01 | $49.00 | |
| 36 | 44201771 | CL D PATCH T4 10 | 1,420 | SQ YD | $27.00 | $28.00 | $40.00 | $48.00 | |
| 37 | 60252800 | CB RECONST | 5 | EACH | $2,150.00 | $2,150.00 | $2,500.00 | $1,250.00 | |
| 38 | 60266600 | VALVE BOX ADJ | 12 | EACH | $425.00 | $425.00 | $300.00 | $350.00 | |
| 39 | 60300305 | FR & LIDS ADJUST | 93 | EACH | $490.00 | $490.00 | $450.00 | $450.00 | |
| 40 | 60404950 | FR & GRATES T24 | 5 | EACH | $485.00 | $485.00 | $650.00 | $450.00 | |
| 41 | 60406000 | FR & LIDS T1 OL | 10 | EACH | $500.00 | $700.00 | $500.00 | $415.00 | |
| 42 | 60406100 | FR & LIDS T1 CL | 28 | EACH | $500.00 | $700.00 | $500.00 | $415.00 | |
| 43 | 66900200 | NON SPL WASTE DISPOSL | 20 | CU YD | $140.00 | $100.00 | $122.27 | $110.00 | |
| 44 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,500.00 | $1,550.00 | $1,390.00 | $1,900.00 | |
| 45 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $4,300.00 | $4,200.00 | $2,300.00 | $2,950.00 | |
| 46 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $500.00 | $2,000.00 | $900.00 | |
| 47 | 66901006 | REG SUB MON | 7 | CAL DA | $475.00 | $600.00 | $790.00 | $680.00 | |
| 48 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,500.00 | $3,500.00 | $3,300.00 | $3,600.00 | |
| 49 | 67100100 | MOBILIZATION | 1 | L SUM | $269,000.00 | $364,000.00 | $385,961.00 | $375,000.00 | |
| 50 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 51 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $620,500.00 | $1.00 | $1.00 | $1.00 | |
| 52 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $29,900.00 | $75,750.00 | $249,918.00 | |
| 53 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 54 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 55 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $8,000.00 | $1,200.00 | $1,200.00 | $1.00 | |
| 56 | 70300100 | SHORT TERM PAVT MKING | 47,628 | FOOT | $0.0100 | $0.0100 | $0.6600 | $0.0100 | |
| 57 | 70300150 | SHRT TRM PAVT MK REM | 15,860 | SQ FT | $0.0100 | $0.0100 | $1.05 | $0.0100 | |
| 58 | 70300210 | TEMP PVT MK LTR & SYM | 2,148 | SQ FT | $0.0100 | $0.0100 | $2.50 | $0.0100 | |
| 59 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 61,676 | FOOT | $0.0100 | $0.0100 | $0.3000 | $0.0100 | |
| 60 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 17,184 | FOOT | $0.0100 | $0.0100 | $0.3000 | $0.0100 | |
| 61 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 97 | FOOT | $0.0100 | $0.0100 | $0.3000 | $0.0100 | |
| 62 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 3,973 | FOOT | $0.0100 | $0.0100 | $0.3000 | $0.0100 | |
| 63 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 2,323 | FOOT | $0.0100 | $0.0100 | $2.50 | $0.0100 | |
| 64 | 70300520 | PAVT MARK TAPE T3 4 | 3,965 | FOOT | $1.00 | $1.25 | $1.25 | $2.00 | |
| 65 | 78000100 | THPL PVT MK LTR & SYM | 2,148 | SQ FT | $4.50 | $5.25 | $5.25 | $4.50 | |
| 66 | 78000200 | THPL PVT MK LINE 4 | 61,676 | FOOT | $0.5500 | $0.5900 | $0.5900 | $0.5500 | |
| 67 | 78000400 | THPL PVT MK LINE 6 | 17,184 | FOOT | $0.8000 | $0.9500 | $0.9500 | $0.8000 | |
| 68 | 78000500 | THPL PVT MK LINE 8 | 97 | FOOT | $1.00 | $1.25 | $1.25 | $1.00 | |
| 69 | 78000600 | THPL PVT MK LINE 12 | 3,973 | FOOT | $2.00 | $3.95 | $3.95 | $2.00 | |
| 70 | 78000650 | THPL PVT MK LINE 24 | 2,323 | FOOT | $4.50 | $5.25 | $5.25 | $4.50 | |
| 71 | 78100100 | RAISED REFL PAVT MKR | 2,720 | EACH | $21.00 | $29.25 | $29.25 | $21.00 | |
| 72 | 78300200 | RAISED REF PVT MK REM | 2,423 | EACH | $4.25 | $12.00 | $9.61 | $8.00 | |
| 73 | 78300202 | PAVMT MRKG REM WTR BL | 39,962 | SQ FT | $0.0100 | $1.00 | $1.00 | $0.0500 | |
| 74 | 85000200 | MAIN EX TR SIG INSTAL | 6 | EACH | $635.70 | $636.00 | $2,300.00 | $2,300.00 | |
| 75 | 88600600 | DET LOOP REPL | 10,977 | FOOT | $15.00 | $15.00 | $16.40 | $16.40 | |
| 76 | 89502376 | REBUILD EX HANDHOLE | 6 | EACH | $1,740.40 | $2,000.00 | $2,200.00 | $2,200.00 |