2021-068-CR
- Let date
- Friday, April 26, 2024
- Contract
- 62P06 · job page
- District
- District 1
- County
- Dupage
- Highway
- Limits
- (1157-Ft) The proposed improvement consists of culvert repair of the structure located at I-55 at stream (0.9 Mi E. of Cass Ave) in Downers Grove Township, DuPage County.
- Classification
- Culvert repair of the structure located at I-55 at stream (0
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lorig Construction Company Low bidder | $1,281,947 | ||
| 2 | Martam Construction Incorporated | $1,289,686 | +0.6% | |
| 3 | Alliance Contractors, Inc. | $1,753,153 | +36.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lorig Construct… | #2 Martam Construc… | #3 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2010402 | STUMP REMOVAL ACRES | 0.25 | ACRE | $14,000.00 | $10,400.00 | $13,000.00 | |
| 2 | X2300007 | TRAF BAR TERM TY 1 | 2 | EACH | $5,200.00 | $5,389.93 | $5,182.62 | |
| 3 | X5010523 | REM CONC END SEC | 2 | EACH | $1,300.00 | $303.80 | $500.00 | |
| 4 | X5021512 | COFFERDAM TYP 1 IS WW | 1 | EACH | $100.00 | $44,231.51 | $1.00 | |
| 5 | X5810103 | MEMB WTRPRF SYS B STR | 221.5 | SQ YD | $70.00 | $55.77 | $54.00 | |
| 6 | X6050700 | REMOVE INLET BOX | 2 | EACH | $2,400.00 | $433.99 | $1,000.00 | |
| 7 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $2,500.00 | $4,071.14 | $500.00 | |
| 8 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $50,000.00 | $87,428.23 | $14,400.00 | |
| 9 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $5,000.00 | $3,874.00 | $3,725.00 | |
| 10 | Z0012754 | STR REP CON DP = < 5 | 138 | SQ FT | $450.00 | $187.20 | $140.00 | |
| 11 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $12,000.00 | $9,059.82 | $10,000.00 | |
| 12 | Z0022800 | FENCE REMOVAL | 260 | FOOT | $13.01 | $24.14 | $13.01 | |
| 13 | Z0073510 | TEMP TR SIGNAL TIMING | 2 | EACH | $750.00 | $936.00 | $700.00 | |
| 14 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 15 | 20101700 | SUPPLE WATERING | 5 | UNIT | $60.00 | $62.40 | $60.00 | |
| 16 | 20200100 | EARTH EXCAVATION | 90 | CU YD | $100.00 | $130.53 | $10.00 | |
| 17 | 21101505 | TOPSOIL EXC & PLAC | 125 | CU YD | $90.00 | $79.77 | $25.00 | |
| 18 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $5,000.00 | $4,992.00 | $4,800.00 | |
| 19 | 25000400 | NITROGEN FERT NUTR | 30 | POUND | $3.00 | $3.12 | $3.00 | |
| 20 | 25000500 | PHOSPHORUS FERT NUTR | 30 | POUND | $3.00 | $3.12 | $3.00 | |
| 21 | 25000600 | POTASSIUM FERT NUTR | 30 | POUND | $3.00 | $3.12 | $3.00 | |
| 22 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $5,500.00 | $5,616.00 | $5,400.00 | |
| 23 | 25100630 | EROSION CONTR BLANKET | 282 | SQ YD | $3.00 | $2.34 | $2.25 | |
| 24 | 25100635 | HD EROS CONTR BLANKET | 342 | SQ YD | $3.25 | $2.60 | $2.50 | |
| 25 | 28000305 | TEMP DITCH CHECKS | 46 | FOOT | $16.00 | $16.64 | $16.00 | |
| 26 | 28000400 | PERIMETER EROS BAR | 489 | FOOT | $4.00 | $3.74 | $3.60 | |
| 27 | 28000500 | INLET & PIPE PROTECT | 4 | EACH | $400.00 | $416.00 | $400.00 | |
| 28 | 28100107 | STONE RIPRAP CL A4 | 62 | SQ YD | $180.00 | $136.74 | $180.00 | |
| 29 | 28200200 | FILTER FABRIC | 62 | SQ YD | $10.00 | $3.73 | $1.00 | |
| 30 | 30300112 | AGG SUBGRADE IMPR 12 | 399 | SQ YD | $40.00 | $30.16 | $25.00 | |
| 31 | 40600290 | BIT MATLS TACK CT | 172 | POUND | $0.1000 | $0.0100 | $0.0100 | |
| 32 | 40701826 | HMA PAVT FD 7 1/4 | 381 | SQ YD | $110.00 | $98.74 | $94.94 | |
| 33 | 44000100 | PAVEMENT REM | 381 | SQ YD | $34.00 | $25.64 | $20.00 | |
| 34 | 48101202 | AGGREGATE SHLDS B | 33 | CU YD | $180.00 | $250.61 | $160.00 | |
| 35 | 50100100 | REM EXIST STRUCT | 1 | EACH | $125,000.00 | $37,033.31 | $422,400.00 | |
| 36 | 50105220 | PIPE CULVERT REMOV | 200 | FOOT | $51.00 | $11.66 | $50.00 | |
| 37 | 50300225 | CONC STRUCT | 21.8 | CU YD | $2,200.00 | $1,902.05 | $3,540.00 | |
| 38 | 50800105 | REINFORCEMENT BARS | 38,330 | POUND | $1.60 | $2.10 | $2.06 | |
| 39 | 52200015 | PERM SHT PILING | 3,951 | SQ FT | $36.00 | $45.41 | $58.55 | |
| 40 | 54003000 | CONC BOX CUL | 148.2 | CU YD | $1,900.00 | $1,764.15 | $2,580.00 | |
| 41 | 542C1063 | P CUL CL C 2 18 | 200 | FOOT | $91.00 | $96.89 | $145.00 | |
| 42 | 54213453 | END SECTIONS 18 | 2 | EACH | $1,400.00 | $1,276.06 | $1,155.00 | |
| 43 | 54244405 | FL INLT BX MED 542546 | 2 | EACH | $3,700.00 | $5,236.97 | $13,000.00 | |
| 44 | 63000003 | SPBGR TY A 9FT POSTS | 1,355 | FOOT | $40.94 | $42.58 | $40.94 | |
| 45 | 63000370 | LSG OVER CUL 25' SPAN | 100 | FOOT | $43.11 | $24.03 | $43.11 | |
| 46 | 63100045 | TRAF BAR TERM T2 | 2 | EACH | $2,063.96 | $2,146.52 | $2,063.96 | |
| 47 | 63200310 | GUARDRAIL REMOV | 496 | FOOT | $9.09 | $9.45 | $9.09 | |
| 48 | 66500105 | WOV W FENCE 4 | 260 | FOOT | $23.21 | $13.53 | $23.21 | |
| 49 | 66900200 | NON SPL WASTE DISPOSL | 760 | CU YD | $90.00 | $104.69 | $89.00 | |
| 50 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,450.00 | $1,081.60 | $1,300.00 | |
| 51 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,500.00 | $3,744.00 | $2,600.00 | |
| 52 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,500.00 | $1,643.20 | $1,700.00 | |
| 53 | 66901006 | REG SUB MON | 5 | CAL DA | $1,950.00 | $676.00 | $700.00 | |
| 54 | 67100100 | MOBILIZATION | 1 | L SUM | $60,000.00 | $77,381.15 | $105,000.00 | |
| 55 | 70107025 | CHANGEABLE MESSAGE SN | 90 | CAL DA | $40.00 | $36.40 | $35.00 | |
| 56 | 70307130 | TEMP PVT MK L6 T4 TAPE | 310 | FOOT | $1.60 | $1.61 | $1.55 | |
| 57 | 70400100 | TEMP CONC BARRIER | 437.5 | FOOT | $26.00 | $39.76 | $72.50 | |
| 58 | 70600260 | IMP ATTN TEMP FRN TL3 | 2 | EACH | $8,454.60 | $8,792.79 | $8,454.60 | |
| 59 | 72501000 | TERMINAL MARKER - DA | 2 | EACH | $55.14 | $57.35 | $55.14 | |
| 60 | 78000200 | THPL PVT MK LINE 4 | 394 | FOOT | $10.00 | $10.40 | $10.00 | |
| 61 | 78100100 | RAISED REFL PAVT MKR | 3 | EACH | $200.00 | $208.00 | $200.00 | |
| 62 | 78200005 | GRDRAIL REF TYPE A | 41 | EACH | $14.96 | $15.56 | $14.96 |